Heavy Published 05/18/2026. 33 classifications. Covers 1 county: Summit
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| LINE CONSTRUCTION: LINEMAN | 58.83 | 21.21 | 80.04 |
| OPERATOR: POWER EQUIPMENT: (5) ASPHALT ROLLER, BOBCAT/SKID LOADER, FRONT END LOADER(UNDER 2 CU YDS.), OILER | 36.55 | 18.62 | 55.17 |
| OPERATOR: POWER EQUIPMENT: (4) ASPHALT PAVER, BULLDOZER, FRONT END LOADER(2 TO 5 CU. YDS.), GRADE SETTER, OIL DISTRIBUTOR, SCRAPER | 37.79 | 18.62 | 56.41 |
| OPERATOR: POWER EQUIPMENT: (3) BACKHOE/EXCAVATOR, FRONT END LOADER(OVER 5 CU.YDS.) | 39.01 | 18.62 | 57.63 |
| OPERATOR: POWER EQUIPMENT: (1)MECHANIC-EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION | 41.71 | 18.62 | 60.33 |
| OPERATOR: POWER EQUIPMENT (6) SCREED | 36.55 | 18.62 | 55.17 |
| OPERATOR: POWER EQUIPMENT ((7) ROLLER(DIRT AND GRADE COMPACTION)) | 34.25 | 18.62 | 52.87 |
| OPERATOR: POWER EQUIPMENT ((2A)BLADE/GRADER) | 40.32 | 18.62 | 58.94 |
| OPERATOR: POWER EQUIPMENT BACKHOE/EXCAVATOR/TRACKHOE, BLADE/GRADER, BOOM, BULLDOZER, MECHANIC: NATURAL GAS PIPELINE CONSTRUCTION ONLY | 35.68 | 17.57 | 53.25 |
| OPERATOR: POWER EQUIPMENT OILER: NATURAL GAS PIPELINE CONSTRUCTION ONLY | 22.03 | 11.88 | 33.91 |
| IRONWORKER | 32.68 | 27.55 | 60.23 |
| LABORER: POT TENDER AND SAND BLASTER: NATURAL GAS PIPELINE CONSTRUCTION ONLY | 20.85 | 8.65 | 29.50 |
| LABORER: COMMON OR GENERAL, PIPELAYER: NATURAL GAS PIPELINE CONSTRUCTION ONLY | 20.59 | 8.65 | 29.24 |
| LABORER: (5)HAND HELD DRILL | 21.65 | 8.65 | 30.30 |
| LABORER: (3) MASON TENDER (CEMENT/CONCRETE), HAND HELD SAW, JACKHAMMER, POWER SAW) | 20.85 | 8.65 | 29.50 |
| LABORER: (1)FLAGGER | 20.59 | 8.65 | 29.24 |
| LABORER: (1) COMMON OR GENERAL: EXCLUDING NATURAL GAS PIPELINE & WATER/SEWER LINE CONSTRUCTION | 20.59 | 8.65 | 29.24 |
| WATER & SEWER LINES OPERATOR-BACKHOE/EXCAVATOR/TRACKHOE | 15.57 | — | 15.57 |
| WATER & SEWER LINES: LABORER, COMMON OR GENERAL | 12.81 | — | 12.81 |
| TRUCK DRIVER (EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION) | 14.40 | 3.99 | 18.39 |
| OPERATOR: TRACKHOE (EXCLUDING NATURAL GAS PIPELINE AND WATER/SEWER LINE CONSTRUCTION) | 19.98 | — | 19.98 |
| OPERATOR: CRANE | 28.97 | 9.40 | 38.37 |
| LABORER: PIPELAYER (EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION) | 14.00 | — | 14.00 |
| LABORER: LANDSCAPE | 7.25 | — | 7.25 |
| ELECTRICIAN | 23.74 | 7.64 | 31.38 |
| CEMENT MASON/CONCRETE FINISHER | 17.08 | 3.14 | 20.22 |
| CARPENTER, INCLUDES FORM WORK | 14.63 | 0.97 | 15.60 |
| TRUCK DRIVER ZONE 2: GROUP 3 | 41.90 | 15.75 | 57.65 |
| TRUCK DRIVER ZONE 2: GROUP 2 | 46.02 | 15.75 | 61.77 |
| TRUCK DRIVER ZONE 2: GROUP 1 | 46.65 | 15.75 | 62.40 |
| TRUCK DRIVER ZONE 1: GROUP 3 | 40.37 | 15.10 | 55.47 |
| TRUCK DRIVER ZONE 1: GROUP 2 | 40.75 | 15.10 | 55.85 |
| TRUCK DRIVER ZONE 1: GROUP 1 | 41.39 | 15.10 | 56.49 |