Building Published 05/18/2026. 39 classifications. Covers 1 county: Hardin
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR (DUCT, PIPE AND MECHANICAL SYSTEM INSULATION) | 30.20 | 12.38 | 42.58 |
| BOILERMAKER | 33.17 | 24.92 | 58.09 |
| BRICKLAYER | 25.50 | 8.12 | 33.62 |
| ELECTRICIAN | 33.76 | 13.56 | 47.32 |
| POWER EQUIPMENT OPERATOR (CRANES) | 39.47 | 10.39 | 49.86 |
| IRONWORKER: ORNAMENTAL | 28.26 | 8.13 | 36.39 |
| IRONWORKER, STRUCTURAL | 34.35 | 14.44 | 48.79 |
| PLUMBER | 35.96 | 11.68 | 47.64 |
| PIPEFITTER | 42.09 | 12.96 | 55.05 |
| SHEET METAL WORKER (EXCLUDES HVAC DUCT INSTALLATION) | 28.69 | 14.13 | 42.82 |
| TRUCK DRIVER: WATER TRUCK | 12.00 | 4.11 | 16.11 |
| TRUCK DRIVER: SEMI-TRAILER TRUCK | 12.50 | — | 12.50 |
| TRUCK DRIVER: FLATBED TRUCK | 19.65 | 8.57 | 28.22 |
| TRUCK DRIVER: DUMP TRUCK | 12.39 | 1.18 | 13.57 |
| TILE SETTER | 16.17 | — | 16.17 |
| TILE FINISHER | 12.00 | — | 12.00 |
| SHEET METAL WORKER (HVAC DUCT INSTALLATION ONLY) | 26.89 | 10.38 | 37.27 |
| ROOFER | 15.40 | — | 15.40 |
| PAINTER: BRUSH, ROLLER, AND SPRAY | 16.75 | 4.51 | 21.26 |
| OPERATOR: ROLLER | 16.00 | — | 16.00 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | 16.03 | — | 16.03 |
| OPERATOR: MECHANIC | 17.52 | 3.33 | 20.85 |
| OPERATOR: LOADER | 13.55 | 0.94 | 14.49 |
| OPERATOR: GRADER/BLADE | 13.37 | — | 13.37 |
| OPERATOR: FORKLIFT | 17.69 | — | 17.69 |
| OPERATOR: DRILL | 16.22 | 0.34 | 16.56 |
| OPERATOR: BULLDOZER | 19.85 | 0.07 | 19.92 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | 13.93 | — | 13.93 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | 19.74 | — | 19.74 |
| LABORER: LANDSCAPE AND IRRIGATION | 11.04 | 0.36 | 11.40 |
| LABORER: ROOF TEAROFF | 11.28 | — | 11.28 |
| LABORER: PIPELAYER | 13.47 | — | 13.47 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | 10.50 | — | 10.50 |
| LABORER: MASON TENDER - BRICK | 12.87 | — | 12.87 |
| LABORER: COMMON OR GENERAL | 12.15 | — | 12.15 |
| IRONWORKER, REINFORCING | 12.95 | — | 12.95 |
| FORM WORKER | 13.69 | — | 13.69 |
| CEMENT MASON/CONCRETE FINISHER | 13.44 | — | 13.44 |
| CARPENTER, EXCLUDES FORM WORK | 18.57 | 3.09 | 21.66 |