Building Published 05/18/2026. 29 classifications. Covers 1 county: Carter
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| BOILERMAKER | 33.70 | 24.41 | 58.11 |
| ELECTRICIAN (LOW VOLTAGE WIRING, ALARM INSTALLATION, AND SOUND AND COMMUNICATIONS SYSTEMS INSTALLATION ONLY) | 21.60 | — | 21.60 |
| POWER EQUIPMENT OPERATOR: GROUP 4 CRANES WITH BOOM INCL. JIB LESS THAN 100 FT AND LESS THAN 3 CU. YD.; OVERHEAD MONORAIL CRANE AND BULLDOZER | 34.07 | 19.05 | 53.12 |
| POWER EQUIPMENT OPERATOR: GROUP 3 ALL CRANE TYPE EQUIPMENT 50 TON CAPACITY AND LARGER CRANES, AND LESS THAN 100 TON CAPACITY. CRANE EQUIPMENT (AS RATED BY MFG.) 3 CU. YD. AND OVER GUY DERRICK WHIRLEY POWER DRIVEN HOLE DIGGER (WITH 30' AND LONGER MAST) | 35.40 | 19.05 | 54.45 |
| POWER EQUIPMENT OPERATOR: GROUP 2 ALL CRANE TYPE EQUIPMENT 100 TON CAPACITY AND LARGER CRANES, AND LESS THAN 200 TON CAPACITY | 36.14 | 19.05 | 55.19 |
| POWER EQUIPMENT OPERATOR: GROUP 10 OILER | 27.25 | 19.05 | 46.30 |
| POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANES | 38.09 | 19.05 | 57.14 |
| IRONWORKER, STRUCTURAL | 32.10 | 17.38 | 49.48 |
| PIPEFITTER (INCLUDING INSTALLATION OF HVAC ELECTRICAL/TEMPERATURE CONTROLS AND HVAC PIPE INSTALLATION) | 41.00 | 16.03 | 57.03 |
| SHEET METAL WORKER (INCLUDING HVAC DUCT INSTALLATION) | 33.38 | 16.36 | 49.74 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | 21.52 | 6.00 | 27.52 |
| ROOFER | 15.00 | 0.29 | 15.29 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATION | 18.00 | 3.23 | 21.23 |
| PAINTER: BRUSH, ROLLER AND SPRAY | 12.32 | — | 12.32 |
| OPERATOR: FORKLIFT | 18.02 | — | 18.02 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | 16.83 | — | 16.83 |
| LABORER: PIPELAYER | 11.65 | — | 11.65 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | 13.04 | — | 13.04 |
| LABORER: MASON TENDER - BRICK | 12.00 | — | 12.00 |
| LABORER: COMMON OR GENERAL | 11.58 | 0.77 | 12.35 |
| GLAZIER | 15.27 | 1.46 | 16.73 |
| FORM WORKER | 13.79 | 0.92 | 14.71 |
| FLOOR LAYER (HARDWOOD AND CARPET) | 18.74 | 1.10 | 19.84 |
| ELECTRICIAN | 21.51 | 6.27 | 27.78 |
| CEMENT MASON/CONCRETE FINISHER | 14.50 | — | 14.50 |
| CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, AND FORM WORK | 16.19 | 0.96 | 17.15 |
| CARPENTER (DRYWALL HANGING ONLY) | 14.96 | — | 14.96 |
| CARPENTER (ACOUSTICAL CEILING INSTALLATION ONLY) | 16.20 | — | 16.20 |
| BRICKLAYER | 20.00 | — | 20.00 |