HeavyHighway Published 07/30/2026. 65 classifications. Covers 1 county: Wayne
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| CEMENT MASONS: HEAVY & HIGHWAY CONSTRUCTION (ROCHESTER CHAPTER) | 38.63 | 25.05 | 63.68 |
| CARPENTER FOOTNOTE: A. PAID HOLIDAYS - NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 38.18 | 26.11 | 64.29 |
| CARPENTERS: PILEDRIVERS (BUILDING CONSTRUCTION) | 29.00 | 18.89 | 47.89 |
| CARPENTERS: PILEDRIVERS (HEAVY & HIGHWAY CONSTRUCTION) | 29.00 | 18.89 | 47.89 |
| ELECTRICIAN (BUTLER, HURON, ROSE AND WOLCOTT TOWNSHIPS) | 50.50 | 35.03 | 85.53 |
| ELECTRICIAN (TOWNSHIPS OF SODUS, WILLIAMSON, ONTARIO, WALWORTH, MARION, MACEDON, PALMYRA) | 44.30 | 30.20 | 74.50 |
| ELECTRICIAN (TOWNSHIPS OF LY0NS, GALEN, ARCADIA AND SAVANNAH) | 45.00 | 31.12 | 76.12 |
| THE HOLIDAY | 31.72 | 29.87 | 61.59 |
| ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN (TRUCK DRIVER) FOOTNOTE: A NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | 42.29 | 30.66 | 72.95 |
| OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | 47.57 | 31.03 | 78.60 |
| ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS LINEMAN & TECHNICIAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | 52.86 | 35.60 | 88.46 |
| THE HOLIDAY | 42.29 | 30.66 | 72.95 |
| ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES : LINEMAN AND TECHNICIAN FOOTNOTE A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | 61.56 | 36.21 | 97.77 |
| EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | 49.25 | 31.15 | 80.40 |
| ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUDING ANY AND ALL FIBER OPTIC GROUND PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES), PIPETYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS, AND MAINTENANCE BONDING OF RAILS; PIPETYPE CABLE INSTALLATION GROUNDMAN TRUCK DRIVER (TRACTOR-TRAILER UNIT) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | 49.25 | 31.15 | 80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Substation:) | 63.14 | 33.82 | 96.96 |
| ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | 64.59 | 42.92 | 107.51 |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | 35.34 | 30.12 | 65.46 |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Substation:) | 35.34 | 30.12 | 65.46 |
| fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | 35.34 | 30.12 | 65.46 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | 55.40 | 31.78 | 87.18 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Substation:) | 55.40 | 31.78 | 87.18 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab | 55.40 | 31.78 | 87.18 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | 49.25 | 31.15 | 80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat | 49.25 | 31.15 | 80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | 49.25 | 31.15 | 80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Substation:) | 49.25 | 31.15 | 80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Substation:) | 61.56 | 36.21 | 97.77 |
| ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins | 61.56 | 36.21 | 97.77 |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | 49.25 | 31.15 | 80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Substation:) | 49.25 | 31.15 | 80.40 |
| fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | 49.25 | 31.15 | 80.40 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | 40.81 | 6.99 | 47.80 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | 20.53 | 6.39 | 26.92 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | 38.73 | 6.93 | 45.66 |
| IMMEDIATELY FOLLOWING THE HOLIDAY | 41.26 | 34.85 | 76.11 |
| AND DERRICKS (STEEL ERECTION); DRAGLINE; DREDGE; DUAL DRUM PAVER; EXCAVATOR (ALL PURPOSE-HYDRAULICLY OPERATED GRADALL OR SIMILAR); FORK LIFT (FACTORY RATED 15' AND OVER); FRONT END LOADER (4CU YD AND OVER); HEAD TOWER (SAUERMAN OR EQUAL); HOIST; SHAFT; HOIST (TWO OR THREE DRUM); HOLLAND LOADER; MAINTENANCE ENGINEER (SHAFT AND TUNNEL); MINE HOIST; MINING MACHINE (MOLE AND SIMILAR TYPES); MUCKING MACHINE OR MOSE; OVERHEAD CRANE (GANTRY OR STRADDLE TYPE); PILE DRIVER; POWER GRADER; QUAD 9, QUARRY MASTER (OR EQUIVALENT); SCRAPER; SHOVEL; SIDE BOOM; SLIP FORM PAVER; TRIPPER/MAINTENANCE ENGINEER (SHAFT AND TUNNEL); TRACTOR DRAWN BELT-TYPE LOADER; TRUCK CRANE; TRUCK OR TRAILER MOUNTED LOG CHIPPER (SELF FEEDER); TUG OPERATOR (MANNED RENTED EQUIPMENT EXCLUDED); TUNNEL SHOVEL FOOTNOTE: B. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 55.38 | 35.75 | 91.13 |
| DUAL DRUM PAVER; EXCAVATOR (ALL PURPOSE-HYDRAULICLY OPERATED GRADALL OR SIMILAR); FORK LIFT (FACTORY RATED 15' AND OVER); FRONT END LOADER (4CU YD AND OVER); HEAD TOWER (SAUERMAN OR EQUAL); HOIST; SHAFT; HOIST (TWO OR THREE DRUM); HOLLAND LOADER; MAINTENANCE ENGINEER (SHAFT AND TUNNEL); MINE HOIST; MINING MACHINE (MOLE AND SIMILAR TYPES); MUCKING MACHINE OR MOSE; OVERHEAD CRANE (GANTRY OR STRADDLE TYPE); PILE DRIVER; POWER GRADER; QUAD 9, QUARRY MASTER (OR EQUIVALENT); SCRAPER; SHOVEL; SIDE BOOM; SLIP FORM PAVER; TRIPPER/MAINTENANCE ENGINEER (SHAFT AND TUNNEL); TRACTOR DRAWN BELT-TYPE LOADER; TRUCK CRANE; TRUCK OR TRAILER MOUNTED LOG CHIPPER (SELF FEEDER); TUG OPERATOR (MANNED RENTED EQUIPMENT EXCLUDED); TUNNEL SHOVEL FOOTNOTE: B. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, REGARDLESS OF THE DAY OF THE WEEK ON WHICH THE HOLIDAY MAY FALL, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 58.43 | 35.00 | 93.43 |
| PROVIDED THE EMPLOYEE WORKS EITHER ON THE WORK DAY IMMEDIATELY PRECEDING THE HOLIDAY OR ON THE SCHEDULED WORK DAY IMMEDIATELY FOLLOWING THE HOLIDAY | 40.79 | 34.85 | 75.64 |
| WORKING DAY AFTER THE HOLIDAY | 54.68 | 35.75 | 90.43 |
| DRILL RIGS, TRACTOR MOUNTED; FRONT END LOADER (UNDER 4 CU. YDS); GRAYCO EPOXY MACHINE; HI-PRESSURE BOILER (15 LBS AND OVER); HOIST (ONE DRUM); HOIST (TWO OR THREE DRUM) (TOPSIDE); KOLMAN PLANT LOADER AND SIMILAR TYPE LOADERS; L.C.M. WORK BOAT OPERATOR; LOCOMOTIVE; MAINTENANCE ENGINEER (TOPSIDE); MAINTENANCE GREASEMAN; MIXER (FOR STABILIZED BASE SELF-PROPELLED); MONORIAL MACHINE; PLANT ENGINEER; PERSONNEL HOIST; PUMP CRETE; READY MIX CONCRETE PLANT; REFRIGERATION EQUIPMENT (FROM SOIL STABILIZATION); ROAD WIDENER; ROLLER (ALL ABOVE SUB-GRADE); SEA MULE; SHOTCRETE MACHINE; SHOVEL (TOPSIDE); TRACTOR WITH DOZER AND/OR PUSHER; TRENCHER; TUGGER HOIST; TUNNEL LOCOMOTIVE; WELDER; WINCH; WINCH CAT FOOTNOTE: B. PAID HOLIDAYS NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, REGARDLESS OF THE DAY OF THE WEEK ON WHICH THE HOLIDAY MAY FALL, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 57.21 | 35.00 | 92.21 |
| PROVIDED THE EMPLOYEE WORKS EITHER ON THE WORK DAY IMMEDIATELY PRECEDING THE HOLIDAY OR ON THE SCHEDULED WORK DAY IMMEDIATELY FOLLOWING THE HOLIDAY | 40.10 | 34.85 | 74.95 |
| GROOVING, MACHINE (RIDE ON), BALLAST REGULATOR, RIDE-ON BOILER (USED IN CONJUNCTION WITH PRODUCTION), BITUMINOUS HEATER, SELF-PROPELLED, BOAT (POWERED), CEMENT AND BIN OPERATOR, COMPRESSORS, DUST COLLECTORS, GENERATORS, PUMPS, WELDING MACHINES, LIGHT PLANTS, HEATERS (HANDS-OFF EQUIPMENT), CONCRETE PAVEMENT SPREADER AND FINISHER, CONCRETE PAVER OR MIXER (16S AND UNDER), CONCRETE SAW (SELF-PROPELLED), CONVEYOR, DECK HAND, DIRECTIONAL DRILL MACHINE LOCATOR, DRILL, (CORE), DRILL, (WELL,) FARM TRACTOR WITH ACCESSORIES, FINE GRADE MACHINE, TAMPER, RIDE-ON, TIE EXTRACTOR, RIDE-ON, TIE HANDLER, RIDE-ON, TIE INSERTER, RIDE-ON, TIE SPACER, RIDE-ON, TIRE REPAIR, TRACK LINER, RIDE-ON, TRACTOR, TRACTOR (WITH TOWED ACCESSORIES), VIBRATORY COMPACTOR, VIBRO TAMP, WELL POINT FOOTNOTE: B. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 51.81 | 35.75 | 87.56 |
| WELL POINT AGGREGATE PLANT; BOILER (USED IN CONJUNCTION WITH PRODUCTION); CEMENT AND BIN OPERATOR; COMPRESSORS (3 OR LESS NOT TO EXCEED 1200 CFM COMBINED CAPACITY); COMPRESSORS (ANY SIZE; BUT SUBJECT TO OTHER PROVISIONS FOR COMPRESSORS); DUST COLLECTORS; GENERATORS; PUMPS; WELDING MACHINES; LIGHT PLANTS (3 OR LESS OF ANY TYPE OR COMBINATION); CONCRETE PAVER OR MIXER (16S AND UNDER); CONCRETE SAW (SELF PROPELLED); FIREMAN; FORM TAMPER; GREASEMAN; HYDRAULIC PUMP (JACKING SYSTEM); JUNIOR ENGINEER; LIGHT PLANTS; MULCHING MACHINE; OILER; PARAPET CONCRETE OR PAVEMENT GRINDER; POWER BROOM (TOWED); POWER HEATERMAN (WHEN USED FOR PRODUCTION); REVINIUS WIDENER; SHELL WINDER; STEAM CLEANER; TRACTOR FOOTNOTE: B PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, REGARDLESS OF THE DAY OF THE WEEK ON WHICH THE HOLIDAY MAY FALL, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 54.42 | 35.00 | 89.42 |
| IMMEDIATELY FOLLOWING THE HOLIDAY | 36.61 | 34.85 | 71.46 |
| WORKING DAY AFTER THE HOLIDAY | 61.38 | 35.75 | 97.13 |
| OPERATING ENGINEER: GROUP 4 (TUNNEL AND SHAFT) CRANE, FRICTION OR LATTICE TYPE WITH BOOM LENGTH 200 FEET AND OVER FOOTNOTE: B. PAID HOLIDAYS NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, REGARDLESS OF THE DAY OF THE WEEK ON WHICH THE HOLIDAY MAY FALL, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 51.41 | 35.00 | 86.41 |
| OPERATING ENGINEER: GROUP 5 (HEAVY AND HIGHWAY) GROUP 5: CRANES 50 TONS AND OVER FOOTNOTE: B PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 59.88 | 35.75 | 95.63 |
| WORKING DAY AFTER THE HOLIDAY | 58.38 | 35.75 | 94.13 |
| OPERATING ENGINEER: GROUP 7 (HEAVY AND HIGHWAY) MASTER MECHANIC FOOTNOTE: B. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 56.81 | 35.75 | 92.56 |
| IMMEDIATELY FOLLOWING THE HOLIDAY. EXCAVATION AND PAVING CLASSIFICATIONS | 43.26 | 34.85 | 78.11 |
| IMMEDIATELY FOLLOWING THE HOLIDAY. EXCAVATION AND PAVING CLASSIFICATIONS | 60.84 | 35.00 | 95.84 |
| IRONWORKERS: ORNAMENTAL, REINFORCING STONE DERRICKMAN, RIGGER, RODMAN, STRUCTURAL MACHINERY MOVERS FENCE ERECTORS, PRECAST CONCRETE ERECTOR (TOWNSHIPS OF ARCADIA, LYONS, MACEDON, MARION, ONTARIO, PALMYRA, SODUS, WALWORTH AND WILLIAMSON) | 35.75 | 30.80 | 66.55 |
| IRONWORKERS:: SHEETER (TOWNSHIPS OF ARCADIA, LYONS, MACEDON, MARION, ONTARIO, PALMYRA, SODUS, WALWORTH AND WILLIAMSON) | 36.00 | 30.80 | 66.80 |
| IRONWORKER: STRUCTURAL, ORNAMENTAL, REINFORCING, PRE-CAST CONCRETE ERECTOR, MACHINERY MOVER & RIGGER, FENCE ERECTOR, STONE DERRICK-MAN WELDER, SHEETER, SHEETER, BUCKER-UP (REMAINDER OF COUNTY) | 37.16 | 30.68 | 67.84 |
| LABORERS: GROUP 1 (HEAVY AND HIGHWAY:) FLAGGERS FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 32.96 | 25.30 | 58.26 |
| LABORERS: GROUP 2 (HEAVY AND HIGHWAY:) LABORERS FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 33.66 | 25.30 | 58.96 |
| LABORERS: GROUP 3 (HEAVY AND HIGHWAY:) RAKERS, DRILLERS, PIPELAYERS AND TORCH OPERATORS FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 33.86 | 25.30 | 59.16 |
| LABORERS: GROUP 4 (HEAVY AND HIGHWAY:) BLASTERS FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 34.69 | 25.30 | 59.99 |
| LABORERS: GROUP 5 (HEAVY AND HIGHWAY:) HAZARDOUS WASTE REMOVAL. FOOTNOTES: A. PAID HOLIDAYS NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 35.44 | 25.30 | 60.74 |
| TRUCK DRIVER GROUP 1 PICK-UPS; PANEL TRUCKS; FLATBOY MATERIALS TRUCKS (STRAIGHT JOBS); SINGLE AXLE DUMP TRUCKS; DUMPSTERS; RECEIVERS; GREASERS; TRUCK TIREMAN. HAZARDOUS WASTE SITE WORK RECEIVES AN ADDITIONAL $1.50 PER HOUR FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAOBR DAY; THANKSGIVING DAY; CHRISTMAS DAY | 31.39 | 27.77 | 59.16 |
| TRUCK DRIVER GROUP 2 TANDEMS; BATCH TRUCK; MECHANICS. HAZARDOUS WASTE SITE WORK RECEIVES AN ADDITIONAL $1.50 PER HOUR FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAOBR DAY; THANKSGIVING DAY; CHRISTMAS DAY | 31.44 | 27.77 | 59.21 |
| TRUCK DRIVER GROUP 3 SEMI-TRAILERS; LOW-BOY TRUCKS; ASPHALT DISTRIBUTOR TRUCKS; AGITATOR; MIXER TRUCKS AND DUMPCRETE TYPE VEHICLES; TRUCK MECHANIC; FUEL TRUCK. HAZARDOUS WASTE SITE WORK RECEIVES AN ADDITIONAL $1.50 PER HOUR FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAOBR DAY; THANKSGIVING DAY; CHRISTMAS DAY | 31.49 | 27.77 | 59.26 |
| TRUCK DRIVER GROUP 4 SPECIALIZED EARTH MOVING EQUIPMENT - EUCLID TYPE OR SIMILAR OFF-HIGHWAY EQUIPMENT, WHERE NOT SELF-LOADED; STRADDLE (ROSS) CARRIER; SELF-CONTAINED CONCRETE UNIT. HAZARDOUS WASTE SITE WORK RECEIVES AN ADDITIONAL $1.50 PER HOUR FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAOBR DAY; THANKSGIVING DAY; CHRISTMAS DAY | 31.64 | 27.77 | 59.41 |
| TRUCK DRIVER GROUP 5 OFF-HIGHWAY TANDEM BACK DUMP; TWIN ENGINE EQUIPMENT; DOUBLE-HITCHED EQUIPMENT SHERE NOT SELF-LOADED. HAZARDOUS WASTE SITE WORK RECEIVES AN ADDITIONAL $1.50 PER HOUR FOOTNOTE: A PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAOBR DAY; THANKSGIVING DAY; CHRISTMAS DAY | 31.79 | 27.77 | 59.56 |