Building Published 05/18/2026. 32 classifications. Covers 1 county: Jefferson
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR (DUCT, PIPE, & MECHANICAL SYSTEM INSULATION) | 43.25 | 27.29 | 70.54 |
| BRICKLAYER (INCLUDES POINTING, CAULKING, AND CLEANING) | 33.45 | 20.14 | 53.59 |
| TILE SETTER | 31.81 | 17.50 | 49.31 |
| MILLWRIGHT | 30.20 | 23.83 | 54.03 |
| ELECTRICIAN (INCLUDES LOW VOLTAGE WIRING AND INSTALLATION OF ALARMS, HVAC/TEMPERATURE CONTROLS AND SOUND AND COMMUNICATION SYSTEMS) | 43.50 | 28.38 | 71.88 |
| POWER EQUIPMENT OPERATOR: CRANE | 49.61 | 31.85 | 81.46 |
| LABORER: MASON TENDER - BRICK | 27.03 | 25.45 | 52.48 |
| LABORER: COMMON OR GENERAL | 27.03 | 25.45 | 52.48 |
| LABORER (MASON TENDER - CEMENT/CONCRETE) | 27.03 | 25.45 | 52.48 |
| PAINTER (SPRAY) | 29.90 | 25.36 | 55.26 |
| DRYWALL FINISHER/TAPER | 30.90 | 25.36 | 56.26 |
| PIPEFITTER (EXCLUDES HVAC PIPE INSTALLATION) | 31.43 | 23.61 | 55.04 |
| ROOFER | 35.80 | 25.99 | 61.79 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | 45.06 | 30.71 | 75.77 |
| SHEET METAL WORKER, INCLUDING INSTALLATION OF HVAC DUCT, METAL FLASHING, AND SIDING (ALUMINUM, METAL, VINYL) | 28.11 | 17.75 | 45.86 |
| PLUMBER, INCLUDES HVAC PIPE INSTALLATION | 33.72 | 16.03 | 49.75 |
| PAINTER (BRUSH AND ROLLER) | 22.32 | 13.95 | 36.27 |
| OPERATOR: ROLLER | 27.74 | 5.89 | 33.63 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | 30.19 | 17.42 | 47.61 |
| OPERATOR: FORKLIFT | 33.14 | 21.04 | 54.18 |
| OPERATOR: BULLDOZER | 31.60 | 21.52 | 53.12 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | 36.17 | 17.76 | 53.93 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | 33.62 | 17.98 | 51.60 |
| LABORER: PIPELAYER | 20.47 | — | 20.47 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | 20.89 | 10.46 | 31.35 |
| LABORER: ASBESTOS ABATEMENT (REMOVAL FROM FLOORS, WALLS, & CEILINGS) | 29.18 | 17.72 | 46.90 |
| IRONWORKER, STRUCTURAL | 29.41 | 21.63 | 51.04 |
| IRONWORKER, REINFORCING | 28.00 | 21.43 | 49.43 |
| IRONWORKER, ORNAMENTAL | 28.70 | 22.02 | 50.72 |
| GLAZIER | 29.52 | 11.47 | 40.99 |
| CEMENT MASON/CONCRETE FINISHER | 30.61 | 5.82 | 36.43 |
| CARPENTER, INCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, AND METAL STUD INSTALLATION | 25.70 | 15.85 | 41.55 |