BuildingHeavyHighwayResidential Published 05/18/2026. 98 classifications. Covers 1 county: Westchester
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| INSULATOR/ASBESTOS WORKER (INCLUDES APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS, AND FINISHES TO ALL TYPES OF MECHANICAL SYTEMS) | 46.62 | 49.30 | 95.92 |
| HAZARDOUS MATERIAL HANDLER (DUTIES LIMITED TO PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPING, VACUUMING, BAGGING AND DISPOSING OF ALL INSULATION MATERIALS WHETHER THEY CONTAIN ASBESTOS OR NOT FROM MECHANICAL SYSTEMS) | 46.62 | 49.30 | 95.92 |
| BOILERMAKER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, THANKSGIVING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY AND GOOD FRIDAY, FRIDAY AFTER THANKSGIVING, CHRISTMAS EVE DAY AND NEW YEAR'S EVE | 68.88 | 49.83 | 118.71 |
| POINTER, CLEANER AND CAULKER | 41.96 | 33.38 | 75.34 |
| MARBLE MASON | 63.92 | 40.20 | 104.12 |
| BRICKLAYERS, STONE MASONS, CEMENT MASONS, PLASTERERS, POINTERS, CAULKERS AND CLEANER (HEAVY & HIGHWAY CONSTRUCTION) | 46.39 | 37.45 | 83.84 |
| BRICKLAYER, CEMENT MASON, PLASTERER & STONEMASON (BUILDING/RESIDENTIAL CONSTRUCTION) | 47.44 | 38.00 | 85.44 |
| TERRAZZO WORKER/SETTER | 64.62 | 37.63 | 102.25 |
| TERRAZZO FINISHER | 49.59 | 34.25 | 83.84 |
| TILE FINISHER | 49.59 | 34.25 | 83.84 |
| MARBLE FINISHER | 49.99 | 37.54 | 87.53 |
| BRICKLAYER (MARBLE POLISHERS) | 52.32 | 36.25 | 88.57 |
| TILE LAYER | 64.40 | 37.13 | 101.53 |
| CARPENTERS: (RESIDENTIAL) | 32.60 | 20.69 | 53.29 |
| CARPENTERS: (HEAVY & HIGHWAY) | 50.12 | 31.73 | 81.85 |
| CARPENTERS (BUILDING) | 50.12 | 31.73 | 81.85 |
| MILLWRIGHT | 60.83 | 58.03 | 118.86 |
| DIVER TENDER | 55.00 | 55.84 | 110.84 |
| DIVER | 75.46 | 55.84 | 131.30 |
| DOCK BUILDER & PILEDRIVERMEN | 60.59 | 55.84 | 116.43 |
| CARPENTERS: (TIMBERMEN) | 55.59 | 55.41 | 111.00 |
| CARPENTERS: (SOFT FLOOR LAYERS) | 59.05 | 48.08 | 107.13 |
| ELECTRICIAN (TELEDATA TECHNICIAN) A. $2.00 PER HOUR NOT TO EXCEED $14.00 PER DAY | 58.75 | 60.50 | 119.25 |
| AFTER THE HOLIDAY | 46.79 | 30.98 | 77.77 |
| OF THE STATE OF NEW YORK PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE AND TWO DAYS AFTER THE HOLIDAY | 58.49 | 35.99 | 94.48 |
| OF THE STATE OF NEW YORK PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE AND TWO DAYS AFTER THE HOLIDAY | 46.79 | 30.98 | 77.77 |
| OF THE STATE OF NEW YORK PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE AND TWO DAYS AFTER THE HOLIDAY | 52.64 | 31.58 | 84.22 |
| AFTER THE HOLIDAY | 35.09 | 30.11 | 65.20 |
| EMPLOYEE WORKS TWO DAYS BEFORE AND TWO DAYS AFTER THE HOLIDAY | 46.79 | 30.98 | 77.77 |
| ELECTRICIAN, LINE CONSTRUCTION: (SUBSTATION AND SWITCHING STRUCTURES PIPETYPE CABLE, UNDERGROUND FUILD AND GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATION, FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT HAVING GROUND PROTECTION OR FIBER OPTIC CAPABILITIES, MAINTENANCE JOBS OR PROJECTS; RAIL- ROAD CATENARY INSTALLATION AND MAINTENANCE BONDING OF RAILS; OVERHEAD & UNDERGROUND DISTRIBUTION WORK & MAINTENANCE; OVERHEAD AND UNDER- GROUND TRANSMISSION LINE WORK) MECHANIC PAID HOLIDAYS: A. NEW YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | 46.79 | 30.98 | 77.77 |
| EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | 46.79 | 30.98 | 77.77 |
| ELECTRICIAN, LINE CONSTRUCTION: (SUBSTATION AND SWITCHING STRUCTURES PIPETYPE CABLE, UNDERGROUND FUILD AND GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATION, FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT HAVING GROUND PROTECTION OR FIBER OPTIC CAPABILITIES, MAINTENANCE JOBS OR PROJECTS; RAIL- ROAD CATENARY INSTALLATION AND MAINTENANCE BONDING OF RAILS; OVERHEAD & UNDERGROUND DISTRIBUTION WORK & MAINTENANCE; OVERHEAD AND UNDER- GROUND TRANSMISSION LINE WORK) GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) PAID HOLIDAYS: A. NEW YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | 49.72 | 31.18 | 80.90 |
| AFTER THE HOLIDAY | 52.64 | 31.58 | 84.22 |
| ELECTRICIAN, LINE CONSTRUCTION: (SUBSTATION AND SWITCHING STRUCTURES PIPETYPE CABLE, UNDERGROUND FUILD AND GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATION, FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT HAVING GROUND PROTECTION OR FIBER OPTIC CAPABILITIES, MAINTENANCE JOBS OR PROJECTS; RAIL- ROAD CATENARY INSTALLATION AND MAINTENANCE BONDING OF RAILS; OVERHEAD & UNDERGROUND DISTRIBUTION WORK & MAINTENANCE; OVERHEAD AND UNDER- GROUND TRANSMISSION LINE WORK) FLAGMAN PAID HOLIDAYS: A. NEW YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | 35.09 | 30.11 | 65.20 |
| EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | 58.49 | 35.99 | 94.48 |
| ELECTRICIAN (LINE CONSTRUCTION) TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT (INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR) | 38.73 | 6.93 | 45.66 |
| ELECTRICIAN (LINE CONSTRUCTION) TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT (GROUNDMAN) | 20.53 | 6.39 | 26.92 |
| ELECTRICIAN (LINE CONSTRUCTION) TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT (CABLE SPLICER) | 40.81 | 6.99 | 47.80 |
| WORKED | 59.09 | 45.56 | 104.65 |
| WORKED | 75.14 | 47.45 | 122.59 |
| ELEVATOR MECHANIC (WESTCHESTER COUNTY (TOWNS OF BEDFORD, CORTLAND, LEWISBORO, MT. KISCO, NORTH SALEM, POUND RIDGE, SOMERS, AND YORKTOWN)) FOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. B. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING DAY; AND CHRISTMAS DAY | 76.12 | 38.98 | 115.10 |
| POWER EQUIPMENT OPERATORS: GROUP 6 (BUILDING & RESIDENTIAL CONSTRUCTION) WAREHOUSE MAN NOTES HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 FOOTNOTE: A. NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | 49.26 | 31.32 | 80.58 |
| POWER EQUIPMENT OPERATORS: GROUP 5-B (BUILDING & RESIDENTIAL CONSTRUCTION) UTILITY MAN NOTES HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 FOOTNOTE: A. NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | 47.00 | 31.32 | 78.32 |
| POWER EQUIPMENT OPERATORS: GROUP 5-A (BUILDING & RESIDENTIAL CONSTRUCTION) MASTER MECHANIC NOTES HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 FOOTNOTE: A. NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | 61.95 | 31.32 | 93.27 |
| POWER EQUIPMENT OPERATORS: GROUP 5 (BUILDING & RESIDENTIAL CONSTRUCTION) MOTORIZED ROLLER (WALK BEHIND) NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM 50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 FOOTNOTE: A NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | 49.53 | 31.32 | 80.85 |
| POWER EQUIPMENT OPERATORS: GROUP 4-B (BUILDING & RESIDENTIAL CONSTRUCTION) COMPRESSOR TO 125 FEET; DUST; DUST COLLECTOR; HEATER ALL TYPES; PUMP; PUMP STATION (WATER AND SEWER); STEAM JENNY; SWEEPER; CHIPPER; MULCHER. NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 FOOTNOTE A. NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | 45.94 | 31.32 | 77.26 |
| MIXER-CONCRETE-UNDER 21E; MULCHING GRASS SPREADER; PUMP-GYPSUM, ETC., PUMP-PLASTER-GROUT -FIREPROOFING; SHOP MECHANIC (NOT EMPLOYED ON JOB SITE); ROLLER UNDER 4 TON; SPREADING AND FINE GRADING MACHINE; STEEL CUTTING MACHINE; SYPHON PUMP-AIR-STEAM; TAR JOINT MACHINE; TURBO JET BURNER OR SIMILAR EQUIPMENT; VIBRATOR (1 TO 5); FINE GRADING MACHINE; ROOF HOIST (TUGGER HOIST); TELEVISION CAMERAS-WATER- SEWER-GAS-ETC. NOTES HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 FOOTNOTE: A. NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | 54.33 | 31.32 | 85.65 |
| POWER EQUIPMENT OPERATORS: GROUP 3-B (BUILDING & RESIDENTIAL CONSTRUCTION) COMPRESSOR OVER 125 CU FEET; CONVEYOR BELT MACHINE REGARDLESS OF SIZE; LIGHTING UNIT (PORTABLE & GENERATOR); WELDING MACHINE (STEEL ERECTION AND EXCAVATION); AND COMPRESSOR PLANT; STUD MACHINE; LADDER HOIST NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 FOOTNOTE: A. NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | 52.25 | 31.32 | 83.57 |
| PUMP; FIREMEN; FORKLIFT; FORKLIFT (ELECTRIC); JOY DRILL OR SIMILAR TRACTOR DRILLING MACHINE; LOADER - 1 1/2 YARDS AND UNDER; LOCOMOTIVE (ALL SIZES); MIXER CONCRETE - 21E AND OVER; PORTABLE ASPHALT PLANT; PORTABLE BATCH PLANT; PORTABLE CRUSHER; QUARRY MASTER; STONE CRUSHER; WELL DRILLING MACHINE AND WELL POINT SYSTEM; CHERRY PICKER UNDER 10 TONS; HYDRAULIC CRANE UNDER 10 TONS; CONCERT BUFFY; ONE YARD AN UP RIDE ON DUMPER (BENFORD OR SIMILAR) NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 FOOTNOTE: A. NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | 54.88 | 31.32 | 86.20 |
| POWER EQUIPMENT OPERATORS: GROUP 2-A (BUILDING & RESIDENTIAL CONSTRUCTION) COMPACTOR SELF-PROPELLED; GRADER; BULLDOZE D7 AND SIMILAR TRACTORS WITH A DRAW BAR HORSEPOWER OF 100 OR OVER; BULLDOZER D6 AND UNDER; WELDER; SCRAPER 20 YDS STRUCK AND UNDER; MACHINE PULLING SHEEP'S FOOT ROLLER; VIBRATORY ROLLERS. NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM 50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 FOOTNOTE: A NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | 56.97 | 31.32 | 88.29 |
| POWER EQUIPMENT OPERATORS: GROUP 1-B (BUILDING & RESIDENTIAL CONSTRUCTION) COMPRESSOR (STEEL ERECTION); PULSE METER AND PUSH BUTTON BUZZ BOX; ELEVATOR; MECHANIC (OUTSIDE) ALL TYPES; WELDER; SCRAPERS 20 YDS STRUCK AND UNDER; MACHINE PULLING SHEEP'S FOOT ROLLER; VIBRATORY ROLLERS; ROLLER 4 TONS AND OVER. NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 FOOTNOTE A. NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | 54.41 | 31.32 | 85.73 |
| RAM); PAVER (CONCRETE); ROAD BORING MACHINE; ROAD MIX MACHINES; ROSS CARRIER AND SIMILAR MACHINES; POST HOLE DIGGER; SHOVEL (TUNNELS); SIDE BOOM; SPREADER (ASPHALT); SCOOPMOBILE-TRACTOR-SHOVEL OVER 1 1/2 YDS. TRENCHING MACHINES VERMEER CONCRETE SAW TRENCHER AND SIMILAR; TRACTOR TYPE DEMOLITION EQUIPMENT; WINCH TRUCK (A FRAME); HYDRAULIC CRANE OVER 10 TON UP TO 25 TON); CHERRY PICKER OVER 10 TON UP TO 25 TON) NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 FOOTNOTE A. NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | 59.04 | 31.32 | 90.36 |
| POWER EQUIPMENT OPERATORS: GROUP 5-A-5 JERSEY-SPREADER, PAVEMENT BREAKER (AIR RAM); POST HOLE DIGGER (HEAVY & HIGHWAY) NOTES LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | 59.19 | 35.25 | 94.44 |
| POWER EQUIPMENT OPERATORS: GROUP 5-A-4 HOIST ENGINEER- STEEL -SUB STRUCTURE (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) 50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | 70.41 | 35.25 | 105.66 |
| POWER EQUIPMENT OPERATORS: GROUP 5-A-3 ENGINEER-- PILE DRIVER (HEAVY & HIGHWAY) NOTES LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | 75.13 | 35.25 | 110.38 |
| POWER EQUIPMENT OPERATORS: GROUP 5-A-2 ENGINEER - ALL TOWER CRANES, ALL CLIMBING CRANES AND ALL CRANES OF 100 TON CAPACITY OR GREATER (3900 MANITOWAC OR SIMILAR) IRRESPECTIVE OF MANUFACTURER AND REGARDLESS OF HOW THE SAME IS RIGGED (EXCEPT FOR PILE RIGS). (HEAVY & HIGHWAY) NOTES LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | 77.82 | 35.25 | 113.07 |
| POWER EQUIPMENT OPERATORS: GROUP 5-A-1 MASTER MECHANIC (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | 64.02 | 35.25 | 99.27 |
| POWER EQUIPMENT OPERATORS: GROUP 5 OILER (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | 64.02 | 35.25 | 99.27 |
| COMPRESSOR - COMPRESSOR PLANT; PAINT COMPRESSOR-STEEL ERECTION; CONVEYOR BELT MACHINE; LIGHTING UNIT (PORTABLE & GENERATOR); OILER; PUMPS - PUMP STATION-WATER-SEWER- GYPSUM- PLASTER, ETC.; ROLLER-MOTORIZED (WALK-BEHIND); WELDING MACHINE (STEEL ERECTION EXCAVATION); WELL POINT SYSTEM; BENDING MACHINE; DUST COLLECTOR; MIXER - CONCRETE UNDER 21-E; HEATER ALL TYPES; STEAM JENNY; SYPHON PUMP-AIR-STEAM; TAR JOINT MACHINE; VIBRATOR (1 TO 5); COMPRESSOR TRUCK MOUNTED (2-6) (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | 44.19 | 35.25 | 79.44 |
| POWER EQUIPMENT OPERATORS: GROUP 4-A SERVICE MEN (FUEL OR GREASE TRUCK). (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) 50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | 51.57 | 35.25 | 86.82 |
| LOADER - 1 1/2 YARDS AND UNDER; LOCOMOTIVE (ALL SIZES), MAINTENANCE ENGINEER; MACHINE PULLING SHEEPS FOOT ROLLER; MATERIAL HOPPER; MIXER CONCRETE - 21-E AND OVER; MULCHING GRASS SPREADER; PORTABLE ASPHALT PLANT, PORTABLE BATCH PLANT, PORTABLE CRUSHER; POWERHOUSE PLANT; QUARRY MASTER; ROLLER UNDER 4 TON; SPREADING AND FINE GRADING MACHINE; STEEL CUTTING MACHINE; STONE CRUSHER; SWEEPER; TURBOJET BURNER OR SIMILAR; WELL DRILLING MACHINE ; WINCH TRUCK ""A"" FRAME. JOHN HENRY DRILL OR SIMILAR (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | 56.81 | 35.25 | 92.06 |
| POWER EQUIPMENT OPERATORS: GROUP 2-B MECHANIC (OUTSIDE) ALL TYPES (HEAVY & HIGHWAY) NOTES LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | 59.67 | 35.25 | 94.92 |
| POWER EQUIPMENT OPERATORS: GROUP 2-A BALLAST REGULATORS; COMPACTOR SELF-PROPELLED; COW TRACKS; FUSION MACHINE; RAIL ANCHOR MACHINES; ROLLER 4 TON AND OVER; SCRAPERS - 20 YARDS STRUCK; SWITCH TAMPERS; VIBRATORY ROLLER, ETC. (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) 50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | 57.84 | 35.25 | 93.09 |
| POWER EQUIPMENT OPERATORS: GROUP 1-B ROAD PAVER, ASPHALT (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | 63.70 | 35.25 | 98.95 |
| SKIDDER; MOVABLE CONCRETE BARRIER TRANSFER & TRANSPORT VEHICLE; MUCKING MACHINES; OVERHEAD CRANE; PAVER (CONCCRETE); PULSEMETER; PUSH BUTTON (BUZZ BOX) ELEVATOR; ROAD MIX MACHINES; ROBOT HAMMER (BROCK OR SIMILAR), ROSS CARRIER AND SIMILAR MACHINES; SHOVELS (TUNNELS); SIDE BOOM; SLIP FORM MACHINE; SPREADER (ASPHALT); SCOOPMOBILE-TRACTOR-SHOVEL OVER 1 1/2 YARDS; TRENCHING MACHINES; TELEPHIES- VERMEER CONCRETE SAW TRENCHER AND/OR SIMILAR; TRACTOR-TYPE DEMOLITION EQUIPMENT, WHIRLY (HEAVY & HIGHWAY) NOTES LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | 60.42 | 35.25 | 95.67 |
| POWER EQUIPMENT OPERATORS: GROUP 1 BOOM TRUCK; CHERRY PICKER; CLAMSHELL; CRANE, (CRAWLER, TRUCK); DRAGLINE; ROUGH TERRAIN CRANE (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) 50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | 68.63 | 35.25 | 103.88 |
| IRONWORKER, STRUCTURAL (WESTCHESTER COUNTY) | 58.95 | 92.02 | 150.97 |
| IRONWORKER (METALLIC LATHERS AND REINFORCING IRONWORKERS) | 57.00 | 32.96 | 89.96 |
| IRONWORKER (STONE DERRICKMAN) | 60.40 | 60.14 | 120.54 |
| IRONWORKER: ORNAMENTAL | 48.15 | 67.62 | 115.77 |
| LABORERS: GROUP 7 ASBESTOS AND TOXIC WASTE LABORER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERANS' DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 51.64 | 28.98 | 80.62 |
| LABORERS: GROUP 6 FLAGPERSON FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERANS' DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 42.96 | 28.98 | 71.94 |
| LABORERS: GROUP 5 COMMON LABORERS, SIGNAL PERSON AND PIT PERSON , TRUCK SPOTTERS, POWDER PERSON, LANDSCAPE AND NURSERY PERSON, DUMP PERSON FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERANS' DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 49.56 | 28.98 | 78.54 |
| LABORERS: GROUP 4 GENERAL CONCRETE LABORERS-ANYTHING PERTAINING TO CONCRETE, AGGREGATE OR CONCRETE MATERIAL HANDLING, PUDDLERS, ASPHALT WORKER, ROCK SCALERS, VIBRATOR OPERATOR, BIT GRINDER, CONCRETE GRINDER, AIR TAMPERS AND ALL TAMPERS NOT COVERED BY ANY OTHER CLASSIFICATION, FORM PIN PULLER, PUMPS AND THEIR OPERATION, SERVICE OF AIR POWER, EPOXY AND WATERPROOFING WORKER, FINE GRADE PERSON BETWEEN FORMS, BARCO RAMMER, GUARD AND GUIDE RAIL AND LINK FENCE, STEEL KINGS. FOOTNOTE A. PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERANS' DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 49.93 | 28.98 | 78.91 |
| LABORERS: GROUP 3 ASPHALT CURB MACHINE OPERATOR, JEEPER OPERATOR, PAVEMENT BREAKER OPERATOR, POWER SAW OPERATOR, JACK HAMMER DRILLER. ALL TYPES OF PHEUMATIC TOOLS GASOLINE DRILLER, CONCRETE SAW, GUNNITING, RAILROAD SPIKE PULLER AND SANDBLASTING, PIPE LAYER, DECK WINCHES ON SCOWS, POWER BUGGY OPERATOR, POWER WHEELBARROW OPERATOR. FOOTNOTE A. PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERANS' DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 50.29 | 28.98 | 79.27 |
| LABORERS: GROUP 2 BURNER, JUMBO DRILLER, JOY DRILLER, WAGON DRILLER, AIR TRACK DRILLER, HYDRAULIC DRILLER, CONCRETE FORM ALIGNER, CONCRETE FORM AND CURB FORM HIGHWAY (STEEL), ASPHALT SCREEDMAN, ASPHALT RAKER. FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERANS' DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 50.71 | 28.98 | 79.69 |
| LABORERS: GROUP 1 BLASTERS. FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERANS' DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 52.11 | 28.98 | 81.09 |
| LABORER (BUILDING) | 44.05 | 32.40 | 76.45 |
| LABORER (RESIDENTIAL) | 42.40 | 19.30 | 61.70 |
| PAINTER (SPRAY, SCAFFOLD, SANDBLASTING) | 47.75 | 44.11 | 91.86 |
| PAINTER (PAINTERS, PAPERHANGER, DRYWALL FINISHERS & LEAD ABATEMENT WORKER) | 44.75 | 44.11 | 88.86 |
| PAINTER (GLAZIERS) | 49.20 | 57.20 | 106.40 |
| PAINTERS: (STRUCTURAL STEEL AND BRIDGE) | 56.25 | 55.14 | 111.39 |
| PLUMBER AND STEAMFITTER (ZONE 1) | 65.07 | 45.35 | 110.42 |
| ROOFER | 50.25 | 32.62 | 82.87 |
| SPRINKLER FITTER | 57.20 | 32.66 | 89.86 |
| SHEET METAL WORKER | 55.29 | 47.43 | 102.72 |
| WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND EMPLOYER SHALL CONTRIBUTE $.20 TO THE FUND ON THE SAME BASIS FOR ALL HOURS PAID TO EMPLOYEES IN THE FORM OF HOLIDAY PAY OR VACATION PAY. IN ADDITION TO THE BENEFITS PAID FOR HEALTH-WELFARE AND PENSION FOR UP TO 40 HOURS WORKED AN ADDITIONAL $.25 IS PAID FOR EACH HOUR WORKED. THE EMPLOYER SHALL GRANT 3 CALENDAR DAYS OFF WITHOUT LOSS OF PAY TO AN EMPLOYEE WHO HAS DEATH IN HIS/HER IMMEDIATE FAMILY, INCLUSIVE OF THE DAY OF THE FUNERAL | 48.63 | 38.93 | 87.56 |
| WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND EMPLOYER SHALL CONTRIBUTE $.20 TO THE FUND ON THE SAME BASIS FOR ALL HOURS PAID TO EMPLOYEES IN THE FORM OF HOLIDAY PAY OR VACATION PAY. IN ADDITION TO THE BENEFITS PAID FOR HEALTH-WELFARE AND PENSION FOR UP TO 40 HOURS WORKED AN ADDITIONAL $.25 IS PAID FOR EACH HOUR WORKED. THE EMPLOYER SHALL GRANT 3 CALENDAR DAYS OFF WITHOUT LOSS OF PAY TO AN EMPLOYEE WHO HAS DEATH IN HIS/HER IMMEDIATE FAMILY, INCLUSIVE OF THE DAY OF THE FUNERAL | 50.26 | 38.93 | 89.19 |
| WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND EMPLOYER SHALL CONTRIBUTE $.20 TO THE FUND ON THE SAME BASIS FOR ALL HOURS PAID TO EMPLOYEES IN THE FORM OF HOLIDAY PAY OR VACATION PAY. IN ADDITION TO THE BENEFITS PAID FOR HEALTH-WELFARE AND PENSION FOR UP TO 40 HOURS WORKED AN ADDITIONAL $.25 IS PAID FOR EACH HOUR WORKED. THE EMPLOYER SHALL GRANT 3 CALENDAR DAYS OFF WITHOUT LOSS OF PAY TO AN EMPLOYEE WHO HAS DEATH IN HIS/HER IMMEDIATE FAMILY, INCLUSIVE OF THE DAY OF THE FUNERAL | 50.51 | 38.93 | 89.44 |
| WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND EMPLOYER SHALL CONTRIBUTE $.20 TO THE FUND ON THE SAME BASIS FOR ALL HOURS PAID TO EMPLOYEES IN THE FORM OF HOLIDAY PAY OR VACATION PAY. IN ADDITION TO THE BENEFITS PAID FOR HEALTH-WELFARE AND PENSION FOR UP TO 40 HOURS WORKED AN ADDITIONAL $.25 IS PAID FOR EACH HOUR WORKED. THE EMPLOYER SHALL GRANT 3 CALENDAR DAYS OFF WITHOUT LOSS OF PAY TO AN EMPLOYEE WHO HAS DEATH IN HIS/HER IMMEDIATE FAMILY, INCLUSIVE OF THE DAY OF THE FUNERAL | 49.88 | 38.93 | 88.81 |
| WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND EMPLOYER SHALL CONTRIBUTE $.20 TO THE FUND ON THE SAME BASIS FOR ALL HOURS PAID TO EMPLOYEES IN THE FORM OF HOLIDAY PAY OR VACATION PAY. IN ADDITION TO THE BENEFITS PAID FOR HEALTH-WELFARE AND PENSION FOR UP TO 40 HOURS WORKED AN ADDITIONAL $.25 IS PAID FOR EACH HOUR WORKED. THE EMPLOYER SHALL GRANT 3 CALENDAR DAYS OFF WITHOUT LOSS OF PAY TO AN EMPLOYEE WHO HAS DEATH IN HIS/HER IMMEDIATE FAMILY, INCLUSIVE OF THE DAY OF THE FUNERAL | 50.38 | 38.93 | 89.31 |
| WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND EMPLOYER SHALL CONTRIBUTE $.20 TO THE FUND ON THE SAME BASIS FOR ALL HOURS PAID TO EMPLOYEES IN THE FORM OF HOLIDAY PAY OR VACATION PAY. IN ADDITION TO THE BENEFITS PAID FOR HEALTH-WELFARE AND PENSION FOR UP TO 40 HOURS WORKED AN ADDITIONAL $.25 IS PAID FOR EACH HOUR WORKED. THE EMPLOYER SHALL GRANT 3 CALENDAR DAYS OFF WITHOUT LOSS OF PAY TO AN EMPLOYEE WHO HAS DEATH IN HIS/HER IMMEDIATE FAMILY, INCLUSIVE OF THE DAY OF THE FUNERAL | 50.01 | 38.93 | 88.94 |
| WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND EMPLOYER SHALL CONTRIBUTE $.20 TO THE FUND ON THE SAME BASIS FOR ALL HOURS PAID TO EMPLOYEES IN THE FORM OF HOLIDAY PAY OR VACATION PAY. IN ADDITION TO THE BENEFITS PAID FOR HEALTH-WELFARE AND PENSION FOR UP TO 40 HOURS WORKED AN ADDITIONAL $.25 IS PAID FOR EACH HOUR WORKED. THE EMPLOYER SHALL GRANT 3 CALENDAR DAYS OFF WITHOUT LOSS OF PAY TO AN EMPLOYEE WHO HAS DEATH IN HIS/HER IMMEDIATE FAMILY, INCLUSIVE OF THE DAY OF THE FUNERAL | 49.26 | 38.93 | 88.19 |
| WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND EMPLOYER SHALL CONTRIBUTE $.20 TO THE FUND ON THE SAME BASIS FOR ALL HOURS PAID TO EMPLOYEES IN THE FORM OF HOLIDAY PAY OR VACATION PAY. IN ADDITION TO THE BENEFITS PAID FOR HEALTH-WELFARE AND PENSION FOR UP TO 40 HOURS WORKED AN ADDITIONAL $.25 IS PAID FOR EACH HOUR WORKED. THE EMPLOYER SHALL GRANT 3 CALENDAR DAYS OFF WITHOUT LOSS OF PAY TO AN EMPLOYEE WHO HAS DEATH IN HIS/HER IMMEDIATE FAMILY, INCLUSIVE OF THE DAY OF THE FUNERAL | 49.13 | 38.93 | 88.06 |
| WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND EMPLOYER SHALL CONTRIBUTE $.20 TO THE FUND ON THE SAME BASIS FOR ALL HOURS PAID TO EMPLOYEES IN THE FORM OF HOLIDAY PAY OR VACATION PAY. IN ADDITION TO THE BENEFITS PAID FOR HEALTH-WELFARE AND PENSION FOR UP TO 40 HOURS WORKED AN ADDITIONAL $.25 IS PAID FOR EACH HOUR WORKED. THE EMPLOYER SHALL GRANT 3 CALENDAR DAYS OFF WITHOUT LOSS OF PAY TO AN EMPLOYEE WHO HAS DEATH IN HIS/HER IMMEDIATE FAMILY, INCLUSIVE OF THE DAY OF THE FUNERAL | 48.96 | 38.93 | 87.89 |
| WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND EMPLOYER SHALL CONTRIBUTE $.20 TO THE FUND ON THE SAME BASIS FOR ALL HOURS PAID TO EMPLOYEES IN THE FORM OF HOLIDAY PAY OR VACATION PAY. IN ADDITION TO THE BENEFITS PAID FOR HEALTH-WELFARE AND PENSION FOR UP TO 40 HOURS WORKED AN ADDITIONAL $.25 IS PAID FOR EACH HOUR WORKED. THE EMPLOYER SHALL GRANT 3 CALENDAR DAYS OFF WITHOUT LOSS OF PAY TO AN EMPLOYEE WHO HAS DEATH IN HIS/HER IMMEDIATE FAMILY, INCLUSIVE OF THE DAY OF THE FUNERAL | 48.51 | 38.93 | 87.44 |
| WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND EMPLOYER SHALL CONTRIBUTE $.20 TO THE FUND ON THE SAME BASIS FOR ALL HOURS PAID TO EMPLOYEES IN THE FORM OF HOLIDAY PAY OR VACATION PAY. IN ADDITION TO THE BENEFITS PAID FOR HEALTH-WELFARE AND PENSION FOR UP TO 40 HOURS WORKED AN ADDITIONAL $.25 IS PAID FOR EACH HOUR WORKED. THE EMPLOYER SHALL GRANT 3 CALENDAR DAYS OFF WITHOUT LOSS OF PAY TO AN EMPLOYEE WHO HAS DEATH IN HIS/HER IMMEDIATE FAMILY, INCLUSIVE OF THE DAY OF THE FUNERAL | 51.26 | 38.93 | 90.19 |