Building  Published 08/13/2026. 40 classifications. Covers 1 county: Somerset

Check that the construction type above matches your contract. A county usually has several determinations and their rates differ. Verify at sam.gov.
ClassificationBase rateFringeTotal
DAY OBSERVED HOLIDAY: 4 HRS. PAY55.8040.8096.60
CEMENT MASON49.6037.9687.56
TILE SETTER64.9037.28102.18
TILE FINISHER (WORK GROUTING ALL EPOXY: $10.00 ADDITIONAL PER DAY.)50.0533.9083.95
CARPENTER: INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORMWORK, BATT AND BLOWN INSULATION57.4234.1791.59
ADDITIONAL FIFTY FEET THEREAFTER.)58.8435.0693.90
ELECTRICIAN: INCLUDING LOW VOLTAGE WIRING (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF FRANKLIN EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD; THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE MIDDLESEX COUNTY LINE; DOES NOT INCLUDE THE TOWNSHIP OF MONTGOMERY WEST AND SOUTH OF A LINE FOLLOWING U.S. HWY. 206 (FORMERLY STATE HWY. 31) NORTH FROM THE MERCER COUNTY LINE TO HARLINGEN RD.; THEN, WEST ALONG HARLINGEN RD. AND THE DUTCHTOWN-ZION ROAD TO THE HILLSBOROUGH TOWNSHIP LINE) (WORK FORTY FT. OR MORE ABOVE THE GROUND OR PROTECTIVE RIGGING (DOES NOT APPLY TO POLE WORK, OR TO USE OF A MANLIFT OR HIGH REACH-TYPE LIFT): 10% PER HOUR ADDITIONAL.) (WORK WITH, OR THE REMOVAL OF, ASBESTOS MATERIALS: 112% TIMES THE JOURNEYMAN RATE.)65.4342.86108.29
RAILROAD TO THE DELAWARE AND RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE MIDDLESEX COUNTY LINE; DOES NOT INCLUDE THE TOWNSHIP OF MONTGOMERY WEST AND SOUTH OF A LINE FOLLOWING U.S. HWY. 206 (FORMERLY STATE HWY. 31) NORTH FROM THE MERCER COUNTY LINE TO HARLINGEN RD.; THEN, WEST ALONG HARLINGEN RD. AND THE DUTCHTOWN-ZION ROAD TO THE HILLSBOROUGH TOWNSHIP LINE) (WORK FORTY FT. OR MORE ABOVE THE GROUND OR PROTECTIVE RIGGING (DOES NOT APPLY TO POLE WORK, OR TO USE OF A MANLIFT OR HIGH REACH-TYPE LIFT): 10% PER HOUR ADDITIONAL.) (WORK WITH, OR THE REMOVAL OF, ASBESTOS MATERIALS 112% TIMES THE JOURNEYMAN RATE.)69.7244.27113.99
CONVEYORS OR MOVING EQUIPMENT OR MACHINERY: 10% PER HOUR ADDITIONAL.)55.8539.7995.64
ELECTRICIAN: CABLE SPLICER (INCLUDING LOW VOLTAGE WIRING) (SOMERSET COUNTY (TOWNSHIP OF FRANKLIN (EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD; THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE MIDDLESEX COUNTY LINE)) (WORK ON LINE VOLTAGE OF 440 VOLTS AND OVER: 10% PER HOUR ADDITIONAL. WORK FROM TRUSSES, SCAFFOLDS AND LADDERS 40 FT. OR MORE FROM THE GROUND OR FLOOR; OR UNDER AIR PRESSURE; OR OVER CONVEYORS OR MOVING EQUIPMENT OR MACHINERY 10% PER HOUR ADDITIONAL.)65.3546.56111.91
HOLIDAY52.8837.5090.38
POWER EQUIPMENT OPERATOR: GROUP 4 BOBCAT/SKID LOADER; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT END LOADER (UNDER 1 CU. YD.); HYDROSEEDER; ROLLER, GRADE; PUMP, HYDRAULIC (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.) PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY56.5937.5094.09
MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION 20% PER HOUR ADDITIONAL.) PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY58.2237.5095.72
POWER EQUIPMENT OPERATOR: GROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH); HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.); SCRAPER; SIDE BOOM (HAZARDOUS WASTE REMOVAL WORK WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.) PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY60.1337.5097.63
STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE DRILL, ROTARY DRILL, SELF-PROPELLED HYDRAULIC DRILL, SELF-POWERED DRILL); ELEVATING GRADER; EXCAVATOR; FRONT END LOADER (5 CU. YD. AND OVER); PILEDRIVER (LENGTH OF BOOM, INCLUDING LENGTH OF LEADS, SHALL DETERMINE PREMIUM RATE APPLICABLE); TRENCHER (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.) PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY61.7237.5099.22
IRONWORKER: STRUCTURAL, ORNAMENTAL, RIGGER (SOMERSET COUNTY (NORTHERN HALF OF COUNTY))52.2450.32102.56
IRONWORKER: REINFORCING (SOMERSET COUNTY (NORTHERN HALF OF COUNTY))49.9450.32100.26
IRONWORKER: STRUCTURAL, ORNAMENTAL, RIGGER (SOMERSET COUNTY (SOUTHERN HALF OF COUNTY))54.2438.4092.64
IRONWORKER: REINFORCING (SOMERSET COUNTY (SOUTHERN HALF OF COUNTY))53.2438.4091.64
OR HAZARDOUS WASTE OR MATERIALS; THE LABELING, BAGGING, CARTONING, CRATING, OR OTHER PACKAGING OF MATERIALS FOR DISPOSAL; THE CLEAN-UP OF THE WORKSITE; AND ALL OTHER WORK INCIDENTAL TO THE REMOVAL, ABATEMENT, ENCAPSULATION, ENCLOSURE, AND DECONTAMINATION OF ASBESTOS AND TOXIC OR HAZARDOUS WASTE OR MATERIALS; AND, IN ADDITION, ALL WORK TASKS INVOLVED IN THE MAINTENANCE AND OPERATION OF ENERGY RESOURCE RECOVERY PLANTS (CO-GENERATION PLANTS))28.3721.6249.99
LABORER: MASON TENDER: BRICK/CEMENT/CONCRETE36.5030.2266.72
LABORER: ASPHALT SHOVELER, ASPHALT SPREADER, COMMON OR GENERAL LABORER, LANDSCAPE LABORER, POWER TOOL OPERATOR AND SCREEDMAN35.7530.2265.97
DRYWALL FINISHER/TAPER44.8730.1575.02
PAINTER: BRUSH AND ROLLER45.5529.8675.41
PAINTER: PAPERHANGER45.5529.8675.41
PAINTER: SPRAY45.5529.8675.41
GLAZIER (WORK WELDING OR USING A CUTTING TORCH $1.00 PER HOUR ADDITIONAL.) (WORK ON A SWING STAGE SCAFFOLD; ON A PIPE SCAFFOLD PROVIDING THE WORKING HEIGHT OF THE PLATFORM IS 30 FT. OR ABOVE; AND ON MOTORIZED LIFTS PROVIDED THAT THE HEIGHT OF THE LIFT PLATFORM IS ABOVE THE SECOND FLOOR OR ABOVE THIRTY FEET: $1.00 PER HOUR ADDITIONAL.)52.6831.2983.97
PLASTERER38.3731.6470.01
PLUMBER: EXCLUDING HVAC PIPE INSTALLATION (SOMERSET COUNTY (TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL))59.5746.45106.02
PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION (SOMERSET COUNTY (TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL))59.5746.45106.02
PLUMBER/PIPEFITTER: SERVICE AND REPAIR (SOMERSET COUNTY (TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL))46.2329.2375.46
PLUMBER: EXCLUDING HVAC PIPE INSTALLATION (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL))62.0945.05107.14
PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL))56.3450.80107.14
(SOMERSET COUNTY (NORTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE ALONG ROUTE #206 NORTH TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY LINE))44.5232.2576.77
ROOFER: SLATE AND TILE (SOMERSET COUNTY (SOUTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE NORTH ALONG ROUTE #206 TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY LINE) (MOPPER, AND OPERATOR OF FELT-LAYING MACHINE $0.50 PER HOUR ADDITIONAL.) ( WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A FELT-LAYING MACHINE OR SLAG-DISPENSING MACHINE IS USED: $0.50 PER HOUR ADDITIONAL.) (PAID HOLIDAY: THE LAST WORKING DAY BEFORE CHRISTMAS, TO BE PAID AT THE RATE OF FOUR HOURS PAY.)38.9521.8560.80
ROOFER: SHINGLES (SOMERSET COUNTY (SOUTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE NORTH ALONG ROUTE #206 TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY LINE) (MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $0.50 PER HOUR ADDITIONAL.) (WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A FELT-LAYING MACHINE OR SLAG-DISPENSING MACHINE IS USED: $0.50 PER HOUR ADDITIONAL.) (PAID HOLIDAY: THE LAST WORKING DAY BEFORE CHRISTMAS, TO BE PAID AT THE RATE OF FOUR HOURS PAY.)35.9521.8557.80
ROOFER: ALL OTHER WORK (SOMERSET COUNTY (SOUTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE NORTH ALONG ROUTE #206 TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY LINE) (MOPPER, AND OPERATOR OF FELT-LAYING MACHINE $0.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A FELT-LAYING MACHINE OR SLAG-DISPENSING MACHINE IS USED: $0.50 PER HOUR ADDITIONAL.) (PAID HOLIDAY: THE LAST WORKING DAY BEFORE CHRISTMAS, TO BE PAID AT THE RATE OF FOUR HOURS PAY.)46.0334.2780.30
SPRINKLER FITTER: FIRE SPRINKLERS (SOMERSET COUNTY (TOWNSHIPS OF BRANCHBURG AND MONTGOMERY; BOROUGH OF ROCKY HILL))49.9741.3591.32
SPRINKLER FITTER: FIRE SPRINKLERS (SOMERSET COUNTY (REMAINDER OF COUNTY))67.9739.35107.32
SHEET METAL WORKER: INCLUDING HVAC DUCT INSTALLATION51.3051.55102.85
Filing the WH-347 that these rates feed into? I build certified payroll tools, and I will prepare your first weekly filing from your payroll register free, with worker names removed — partly to be useful, partly because real registers are the only way to test the thing properly. hamza.aiemployee@gmail.com. No sign-up on this site, and nothing here is tracked.