Highway Published 05/18/2026. 43 classifications. Covers 1 county: Newton
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN | 33.30 | 11.63 | 44.93 |
| TRUCK DRIVER: SEMI/TRAILER TRUCK | 12.50 | — | 12.50 |
| TRUCK DRIVER: DUMP TRUCK (ALL TYPES) | 10.68 | — | 10.68 |
| TRUCK DRIVER: WATER TRUCK | 9.63 | — | 9.63 |
| TRUCK DRIVER: OFF THE ROAD TRUCK | 12.31 | — | 12.31 |
| TRUCK DRIVER: MECHANIC | 12.15 | — | 12.15 |
| TRUCK DRIVER: LOWBOY TRUCK | 11.00 | — | 11.00 |
| TRUCK DRIVER: FLATBED TRUCK | 13.29 | — | 13.29 |
| SURVEYOR (STAKING, MARKING AND BRUSH CLEARING) | 12.34 | — | 12.34 |
| OPERATOR: TRENCHER | 13.75 | — | 13.75 |
| OPERATOR: TRACTOR | 9.41 | — | 9.41 |
| OPERATOR: SCRAPER | 12.00 | — | 12.00 |
| OPERATOR: ROLLER (ALL TYPES) | 11.13 | — | 11.13 |
| OPERATOR: PILEDRIVER | 15.13 | — | 15.13 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | 12.75 | — | 12.75 |
| OPERATOR: OILER | 13.00 | — | 13.00 |
| OPERATOR: MIXER | 12.42 | — | 12.42 |
| OPERATOR: MILLING MACHINE | 14.96 | — | 14.96 |
| OPERATOR: MECHANIC | 16.25 | — | 16.25 |
| OPERATOR: LOADER | 14.31 | — | 14.31 |
| OPERATOR: GRADER/BLADE | 15.13 | — | 15.13 |
| OPERATOR: DRILL | 19.22 | — | 19.22 |
| OPERATOR: DISTRIBUTOR | 12.00 | — | 12.00 |
| OPERATOR: CRANE | 20.10 | — | 20.10 |
| OPERATOR: CONCRETE SAW | 13.92 | — | 13.92 |
| OPERATOR: BULLDOZER | 14.23 | — | 14.23 |
| OPERATOR: BROOM/SWEEPER | 10.17 | — | 10.17 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | 13.74 | — | 13.74 |
| OPERATOR: ASPHALT SPREADER | 15.33 | — | 15.33 |
| LABORER: LABORER-CONES/ BARRICADES/BARRELS - SETTER/MOVER/SWEEPER | 10.69 | — | 10.69 |
| LABORER: PIPELAYER | 12.27 | — | 12.27 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | 11.30 | — | 11.30 |
| LABORER: GRADE CHECKER | 12.41 | — | 12.41 |
| LABORER: FLAGGER | 10.00 | — | 10.00 |
| LABORER: COMMON OR GENERAL | 10.19 | — | 10.19 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | 10.68 | — | 10.68 |
| IRONWORKER, REINFORCING | 15.28 | — | 15.28 |
| INSTALLER - SIGN | 12.08 | — | 12.08 |
| INSTALLER - GUARDRAIL | 11.68 | — | 11.68 |
| HIGHWAY/PARKING LOT STRIPING: TRUCK DRIVER (LINE STRIPING TRUCK) | 11.44 | — | 11.44 |
| CEMENT MASON/CONCRETE FINISHER | 13.57 | — | 13.57 |
| CARPENTER, EXCLUDES FORM WORK | 14.21 | — | 14.21 |
| CARPENTER (FORM WORK ONLY) | 12.96 | — | 12.96 |