Building Published 05/18/2026. 32 classifications. Covers 1 county: Crawford
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| BOILERMAKER | 46.00 | 36.25 | 82.25 |
| BRICKLAYER | 41.15 | 23.90 | 65.05 |
| TILE SETTER | 34.09 | 19.91 | 54.00 |
| TILE FINISHER | 28.50 | 18.15 | 46.65 |
| CARPENTER (INCLUDING DRYWALL HANGING & FORM WORK) | 44.19 | 21.85 | 66.04 |
| CARPENTER (FLOOR LAYING-CARPET AND VINYL ONLY) | 40.08 | 21.85 | 61.93 |
| ELECTRICIAN (INCLUDING LOW VOLTAGE WIRING INSTALLER; ALARM, COMPUTER & TELEPHONE INSTALLATION) | 40.50 | 23.26 | 63.76 |
| ELEVATOR MECHANIC. FOOTNOTES: A) EMPLOYER CONTRIBUTES 8% OF REGULAR BASIC HOURLY RATE AS AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YEARS OF SERVICE, AND 6% FOR LESS THAN 5 YEARS OF SERVICE B) EIGHT PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY FRIDAY AFTER THANKSGIVING DAY, VETERANS' DAY AND CHRISTM | 62.73 | 38.44 | 101.17 |
| POWER EQUIPMENT OPERATORS: ROLLER | 39.06 | 30.38 | 69.44 |
| POWER EQUIPMENT OPERATORS: PAVER | 39.06 | 30.38 | 69.44 |
| POWER EQUIPMENT OPERATORS: LOADER | 39.06 | 30.38 | 69.44 |
| POWER EQUIPMENT OPERATORS: GRADER/BLADE | 39.06 | 30.38 | 69.44 |
| POWER EQUIPMENT OPERATORS: FORKLIFT | 39.06 | 30.38 | 69.44 |
| POWER EQUIPMENT OPERATORS: CRANE | 39.06 | 30.38 | 69.44 |
| POWER EQUIPMENT OPERATORS: BOBCAT/SKID LOADER | 39.06 | 30.38 | 69.44 |
| POWER EQUIPMENT OPERATORS: BACKHOE/EXCAVATOR | 39.06 | 30.38 | 69.44 |
| IRONWORKER, ORNAMENTAL, REINFORCING AND STRUCTURAL | 41.67 | 31.25 | 72.92 |
| LABORER: COMMON OR GENERAL; ASPHALT SHOVELER; PIPELAYER | 30.33 | 15.30 | 45.63 |
| LABORER: BRICK & CEMENT/CONCRETE MASON TENDER | 32.23 | 15.30 | 47.53 |
| GLAZIER | 40.00 | 24.25 | 64.25 |
| PAINTER (DRYWALL FINISHING/TAPING) | 34.90 | 17.21 | 52.11 |
| PAINTER (BRUSH AND ROLLER) | 33.90 | 17.21 | 51.11 |
| CEMENT MASON/CONCRETE FINISHER | 36.63 | 9.85 | 46.48 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATION (MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK OVER $7.0 MILLION) | 50.60 | 30.13 | 80.73 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATION (MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK $7.0 MILLION & UNDER) | 48.66 | 22.79 | 71.45 |
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION (MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK OVER $7.0 MILLION) | 50.60 | 30.13 | 80.73 |
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION (MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK $7.0 MILLION & UNDER) | 48.66 | 22.79 | 71.45 |
| ROOFER | 40.00 | 22.05 | 62.05 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | 45.94 | 27.52 | 73.46 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION | 52.00 | 27.12 | 79.12 |
| PAINTER: SPRAY | 17.78 | — | 17.78 |
| OPERATOR: HOIST | 26.02 | 13.01 | 39.03 |