Building Published 05/18/2026. 30 classifications. Covers 1 county: Schoolcraft
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | 45.24 | 30.56 | 75.80 |
| BOILERMAKER | 43.50 | 37.64 | 81.14 |
| TILE SETTER | 32.19 | 24.65 | 56.84 |
| BRICKLAYER | 32.19 | 24.65 | 56.84 |
| MILLWRIGHT | 41.00 | 23.43 | 64.43 |
| CARPENTER (INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL FINISHING/TAPING, DRYWALL HANGING, FORM WORK, AND SOFT FLOOR LAYER - CARPET) | 34.01 | 23.14 | 57.15 |
| ELECTRICIAN (EXCLUDES LOW VOLTAGE WIRING) | 33.43 | 21.78 | 55.21 |
| POWER EQUIPMENT OPERATOR: GROUP 3 OILER PREMIUM RATE: MAIN BOOM AND JIB 300 FEET OR LONGER IS $1.50 PER HOUR ABOVE THE 220 FT. BOOM AND JIB RATE. MAIN BOOM AND JIB 400 FEET OR LONGER IS $3.00 PER HOUR ABOVE THE 220 FT. BOOM AND JIB RATE | 35.86 | 12.50 | 48.36 |
| POWER EQUIPMENT OPERATOR: GROUP 2 FORK TRUCK PREMIUM RATE: MAIN BOOM AND JIB 300 FEET OR LONGER IS $1.50 PER HOUR ABOVE THE 220 FT. BOOM AND JIB RATE. MAIN BOOM AND JIB 400 FEET OR LONGER IS $3.00 PER HOUR ABOVE THE 220 FT. BOOM AND JIB RATE | 37.26 | 25.00 | 62.26 |
| POWER EQUIPMENT OPERATOR: GROUP 1 BACKHOE, BULLDOZER; CRANE, FRONT END LOADER, EXCAVATOR, PAVER, ROLLER, AND SCRAPER (SELF-PROPELLED AND TRACTOR DRAWN) PREMIUM RATE: MAIN BOOM AND JIB 300 FEET OR LONGER IS $1.50 PER HOUR ABOVE THE 220 FT BOOM AND JIB RATE. MAIN BOOM AND JIB 400 FEET OR LONGER IS $3.00 PER HOUR ABOVE THE 220 FT. BOOM AND JIB RATE | 40.51 | 25.00 | 65.51 |
| POWER EQUIPMENT OPERATOR: CRANE OPERATOR, MAIN BOOM & JIB 220' OR LONGER PREMIUM RATE: MAIN BOOM AND JIB 300 FEET OR LONGER IS $1.50 PER HOUR ABOVE THE 220 FT. BOOM AND JIB RATE. MAIN BOOM AND JIB 400 FEET OR LONGER IS $3.00 PER HOUR ABOVE THE 220 FT BOOM AND JIB RATE | 44.92 | 25.00 | 69.92 |
| POWER EQUIPMENT OPERATOR: CRANE OPERATOR, MAIN BOOM & JIB 140' OR LONGER PREMIUM RATE: MAIN BOOM AND JIB 300 FEET OR LONGER IS $1.50 PER HOUR ABOVE THE 220 FT. BOOM AND JIB RATE. MAIN BOOM AND JIB 400 FEET OR LONGER IS $3.00 PER HOUR ABOVE THE 220 FT BOOM AND JIB RATE | 44.63 | 25.00 | 69.63 |
| POWER EQUIPMENT OPERATOR: CRANE OPERATOR, MAIN BOOM & JIB 120' OR LONGER PREMIUM RATE: MAIN BOOM AND JIB 300 FEET OR LONGER IS $1.50 PER HOUR ABOVE THE 220 FT. BOOM AND JIB RATE. MAIN BOOM AND JIB 400 FEET OR LONGER IS $3.00 PER HOUR ABOVE THE 220 FT BOOM AND JIB RATE | 43.81 | 25.00 | 68.81 |
| IRONWORKER, REINFORCING AND STRUCTURAL (CONTRACTS LESS THAN $10,000,000) PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY & CHRISTMAS DAY | 35.20 | 32.97 | 68.17 |
| IRONWORKER, REINFORCING AND STRUCTURAL (CONTRACTS $10,000,000 OR GREATER) PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY & CHRISTMAS DAY | 35.20 | 32.97 | 68.17 |
| LABORER (COMMON OR GENERAL; MASON TENDER - BRICK; MASON TENDER - CEMENT/CONCRETE; AND SANDBLASTER) | 28.18 | 13.45 | 41.63 |
| PAINTER (INSULATOR FOAM ONLY) | 28.73 | 15.92 | 44.65 |
| PAINTER (BRUSH AND SPRAY ONLY) | 28.73 | 15.92 | 44.65 |
| CEMENT MASON/CONCRETE FINISHER | 20.17 | 10.13 | 30.30 |
| PLUMBER (EXCLUDING HVAC PIPE & SYSTEM INSTALLATION).$ 34.59 27.53 PIPEFITTER (HVAC PIPE INSTALLATION ONLY) | 34.59 | 27.53 | 62.12 |
| PIPEFITTER (EXCLUDES HVAC PIPE & SYSTEM INSTALLATION) | 45.44 | 28.43 | 73.87 |
| SHEET METAL WORKER (HVAC DUCT & SYSTEM INSTALLATION) | 27.24 | 29.85 | 57.09 |
| SHEET METAL WORKER (EXCLUDING HVAC DUCT & SYSTEM INSTALLATION) | 32.74 | 29.85 | 62.59 |
| TRUCK DRIVER: FLATBED TRUCK | 17.44 | 4.51 | 21.95 |
| ROOFER | 19.10 | 8.00 | 27.10 |
| PAINTER: ROLLER | 16.58 | 2.84 | 19.42 |
| OPERATOR: TRACTOR | 19.60 | 7.31 | 26.91 |
| OPERATOR: GRADER/BLADE | 24.04 | 6.03 | 30.07 |
| LABORER: LANDSCAPE & IRRIGATION | 14.95 | — | 14.95 |
| GLAZIER | 17.50 | 2.27 | 19.77 |