Davis-Bacon Rate Lookupfree · sourced from sam.gov · no sign-up

MI20260116 rev 1

Building  Published 05/18/2026. 31 classifications. Covers 1 county: Delta

Check that the construction type above matches your contract. A county usually has several determinations and their rates differ. Verify at sam.gov.
ClassificationBase rateFringeTotal
ASBESTOS WORKER/HEAT & FROST INSULATOR45.2430.5675.80
BOILERMAKER43.5037.6481.14
TILE SETTER32.1924.6556.84
BRICKLAYER32.1924.6556.84
MILLWRIGHT41.0023.4364.43
CARPENTER (INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, AND SOFT FLOOR LAYER - CARPET)34.0123.1457.15
ELECTRICIAN (EXCLUDES LOW VOLTAGE WIRING)33.4321.7855.21
POWER EQUIPMENT OPERATOR: GROUP 3 OILER PREMIUM RATE: MAIN BOOM AND JIB 300 FEET OR LONGER IS $1.50 PER HOUR ABOVE THE 220 FT. BOOM AND JIB RATE. MAIN BOOM AND JIB 400 FEET OR LONGER IS $3.00 PER HOUR ABOVE THE 220 FT. BOOM AND JIB RATE35.8612.5048.36
POWER EQUIPMENT OPERATOR: GROUP 2 FORK TRUCK PREMIUM RATE: MAIN BOOM AND JIB 300 FEET OR LONGER IS $1.50 PER HOUR ABOVE THE 220 FT. BOOM AND JIB RATE. MAIN BOOM AND JIB 400 FEET OR LONGER IS $3.00 PER HOUR ABOVE THE 220 FT. BOOM AND JIB RATE37.2625.0062.26
POWER EQUIPMENT OPERATOR: GROUP 1 BACKHOE, BULLDOZER; CRANE, FRONT END LOADER, EXCAVATOR, PAVER, ROLLER, AND SCRAPER (SELF-PROPELLED AND TRACTOR DRAWN) PREMIUM RATE: MAIN BOOM AND JIB 300 FEET OR LONGER IS $1.50 PER HOUR ABOVE THE 220 FT BOOM AND JIB RATE. MAIN BOOM AND JIB 400 FEET OR LONGER IS $3.00 PER HOUR ABOVE THE 220 FT. BOOM AND JIB RATE40.5125.0065.51
POWER EQUIPMENT OPERATOR: CRANE OPERATOR, MAIN BOOM & JIB 220' OR LONGER PREMIUM RATE: MAIN BOOM AND JIB 300 FEET OR LONGER IS $1.50 PER HOUR ABOVE THE 220 FT. BOOM AND JIB RATE. MAIN BOOM AND JIB 400 FEET OR LONGER IS $3.00 PER HOUR ABOVE THE 220 FT BOOM AND JIB RATE44.9225.0069.92
POWER EQUIPMENT OPERATOR: CRANE OPERATOR, MAIN BOOM & JIB 140' OR LONGER PREMIUM RATE: MAIN BOOM AND JIB 300 FEET OR LONGER IS $1.50 PER HOUR ABOVE THE 220 FT. BOOM AND JIB RATE. MAIN BOOM AND JIB 400 FEET OR LONGER IS $3.00 PER HOUR ABOVE THE 220 FT BOOM AND JIB RATE44.6325.0069.63
POWER EQUIPMENT OPERATOR: CRANE OPERATOR, MAIN BOOM & JIB 120' OR LONGER PREMIUM RATE: MAIN BOOM AND JIB 300 FEET OR LONGER IS $1.50 PER HOUR ABOVE THE 220 FT. BOOM AND JIB RATE. MAIN BOOM AND JIB 400 FEET OR LONGER IS $3.00 PER HOUR ABOVE THE 220 FT BOOM AND JIB RATE43.8125.0068.81
IRONWORKER, REINFORCING AND STRUCTURAL (CONTRACTS LESS THAN $10,000,000) PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY & CHRISTMAS DAY35.2032.9768.17
IRONWORKER, REINFORCING AND STRUCTURAL (CONTRACTS $10,000,000 OR GREATER) PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY & CHRISTMAS DAY35.2032.9768.17
LABORER (COMMON OR GENERAL; MASON TENDER - BRICK; MASON TENDER - CEMENT/CONCRETE; AND SANDBLASTER)28.1813.4541.63
PAINTER (INSULATOR FOAM ONLY)28.7315.9244.65
PAINTER (BRUSH AND SPRAY ONLY)28.7315.9244.65
PAINTER (DRYWALL FINISHING/TAPING ONLY)27.5413.3340.87
CEMENT MASON/CONCRETE FINISHER20.1710.1330.30
PLUMBER (EXCLUDING HVAC PIPE & SYSTEM INSTALLATION).$ 34.59 27.53 PIPEFITTER (HVAC PIPE INSTALLATION ONLY)34.5927.5362.12
PIPEFITTER (EXCLUDES HVAC PIPE & SYSTEM INSTALLATION)45.4428.4373.87
ROOFER26.5015.9542.45
SHEET METAL WORKER (HVAC DUCT & SYSTEM INSTALLATION)27.2429.8557.09
SHEET METAL WORKER (EXCLUDING HVAC DUCT & SYSTEM INSTALLATION)32.7429.8562.59
TRUCK DRIVER: FLATBED TRUCK17.444.5121.95
PAINTER: ROLLER16.582.8419.42
OPERATOR: TRACTOR19.607.3126.91
OPERATOR: GRADER/BLADE24.046.0330.07
LABORER: LANDSCAPE & IRRIGATION14.95—14.95
GLAZIER17.502.2719.77
Filing the WH-347 that these rates feed into? I build certified payroll tools, and I will prepare your first weekly filing from your payroll register free, with worker names removed — partly to be useful, partly because real registers are the only way to test the thing properly. hamza.aiemployee@gmail.com. No sign-up on this site, and nothing here is tracked.