Building Published 05/18/2026. 42 classifications. Covers 1 county: Lapeer
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | 40.00 | 23.65 | 63.65 |
| BOILERMAKER | 43.50 | 36.74 | 80.24 |
| HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | 33.31 | 23.20 | 56.51 |
| TILE FINISHER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | 28.21 | 20.88 | 49.09 |
| HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | 38.00 | 26.49 | 64.49 |
| CARPENTER (INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION & SCAFFOLD BUILDING) | 36.46 | 23.69 | 60.15 |
| CARPENTER (FLOOR LAYER - CARPET, RESILIENT & VINYL FLOORING) | 35.86 | 23.69 | 59.55 |
| MILLWRIGHT | 42.92 | 39.13 | 82.05 |
| ELECTRICIAN (EXCLUDES ALARM INSTALLATION & LOW VOLTAGE WIRING) | 44.83 | 26.96 | 71.79 |
| ELEVATOR MECHANIC FOOTNOTES: A. PAID HOLIDAYS NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING DAY; AND CHRISTMAS DAY B. EMPLOYER CONTRIBUTES 8% BASIC HOURLY RATE FOR 5 YEARS OR MORE OF SERVICE OF 6% BASIC HOURLY RATE FOR 6 MONTHS TO 5 YEARS OF SERVICE AS VACATION PAY CREDIT | 65.45 | 38.44 | 103.89 |
| OPERATOR: POWER EQUIPMENT: GROUP 7 OILER FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 31.23 | 25.25 | 56.48 |
| OPERATOR: POWER EQUIPMENT: GROUP 6 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) FOOTNOTES CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 33.71 | 25.25 | 58.96 |
| DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 39.57 | 25.25 | 64.82 |
| OPERATOR: POWER EQUIPMENT: GROUP 4 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK (OVER 20' LIFT) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 39.57 | 25.25 | 64.82 |
| JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 41.28 | 25.25 | 66.53 |
| OPERATOR: POWER EQUIPMENT: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER, TOWER CRANE, GANTRY CRANE, WHIRLEY DERRICK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 43.93 | 25.25 | 69.18 |
| OPERATOR: POWER EQUIPMENT: GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER. FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 47.28 | 25.25 | 72.53 |
| IRONWORKER: STRUCTURAL | 36.55 | 35.93 | 72.48 |
| IRONWORKER: REINFORCING | 36.55 | 33.37 | 69.92 |
| IRONWORKER: STRUCTURAL (METAL BUILDING ERECTION ONLY) | 30.02 | 27.43 | 57.45 |
| LABORER: ASBESTOS ABATEMENT (REMOVAL FROM FLOORS, WALLS & CEILINGS) | 39.08 | 15.92 | 55.00 |
| LABORER: LANDSCAPE & IRRIGATION: GROUP 2 LANDSCAPE LABORER: SMALL POWER TOOL OPERATOR, MATERIAL MOVER, TRUCK DRIVER AND LAWN SPRINKLER INSTALLER TENDER | 27.71 | 9.10 | 36.81 |
| LABORER: LANDSCAPE & IRRIGATION: GROUP 1 LANDSCAPE SPECIALIST, INCLUDING AIR, GAS AND DIESEL EQUIPMENT OPERATOR, LAWN SPRINKLER INSTALLER, SKIDSTEER (OR EQUIVALENT) | 29.93 | 9.10 | 39.03 |
| LABORER: COMMON OR GENERAL; GRADE CHECKER; MASON TENDER - BRICK/CEMENT/CONCRETE, PIPELAYER; SANDBLASTER | 29.46 | 16.10 | 45.56 |
| GLAZIER | 37.41 | 18.99 | 56.40 |
| PAINTER: SPRAY (WEST OF HWY. M-53) | 31.01 | 17.29 | 48.30 |
| PAINTER: BRUSH & ROLER (WEST OF HWY. M-53) | 32.58 | 18.12 | 50.70 |
| DRYWALL FINISHER/TAPER: MACHINE WORK (WEST OF HWY M-53) | 27.15 | 15.00 | 42.15 |
| DRYWALL FINISHER/TAPER: HAND WORK (WEST OF HWY M-53) | 27.15 | 15.00 | 42.15 |
| DRYWALL FINISHER/TAPER: DRYWALL SANDING (WEST OF HWY. M-53) | 33.54 | 18.03 | 51.57 |
| PAINTER: DRYWALL FINISHING/TAPING (EAST OF HWY M-53) | 23.79 | 12.02 | 35.81 |
| PAINTER: BRUSH, ROLLER AND SPRAY (EAST OF HWY M-53) | 23.79 | 12.02 | 35.81 |
| CEMENT MASON/CONCRETE FINISHER | 27.77 | 12.88 | 40.65 |
| PLASTERER | 30.63 | 14.07 | 44.70 |
| PLUMBER, EXCLUDES HVAC PIPE AND UNIT INSTALLATION | 46.61 | 22.95 | 69.56 |
| PIPEFITTER, INCLUDES HVAC PIPE AND UNIT INSTALLATION | 46.61 | 22.95 | 69.56 |
| ROOFER | 30.38 | 19.97 | 50.35 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | 41.34 | 27.39 | 68.73 |
| POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 2 LEVEL D WHEN CAPPING LANDFILL) | 42.74 | 21.53 | 64.27 |
| TRUCK DRIVER: TRACTOR HAUL TRUCK | 13.57 | 1.18 | 14.75 |
| IRONWORKER, ORNAMENTAL | 18.48 | 7.93 | 26.41 |
| INSTALLER - OVERHEAD DOOR | 27.98 | — | 27.98 |