Heavy Published 05/18/2026. 37 classifications. Covers 1 county: St Clair
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| BOILERMAKER | 43.50 | 36.74 | 80.24 |
| PILEDRIVERMAN | 38.48 | 30.22 | 68.70 |
| CARPENTER, INCLUDES FORM WORK | 42.44 | 31.43 | 73.87 |
| LINE CONSTRUCTION: LINEMEN/CABLE SPLICER | 61.06 | 25.11 | 86.17 |
| ELECTRICIAN | 51.32 | 28.54 | 79.86 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 4 BROOM/ SWEEPER, FORK TRUCK, TRACTOR, BOBCAT/ SKID STEER /SKID LOADER | 39.95 | 25.25 | 65.20 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 3 BOOM TRUCK (NON-SWINGING, NON- POWERED TYPE BOOM) | 40.52 | 25.25 | 65.77 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 2 TRENCHER (8-FT DIGGING CAPACITY AND SMALLER) | 41.25 | 25.25 | 66.50 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 1 BACKHOE/ EXCAVATOR, BORING MACHINE, BULLDOZER, CRANE, GRADER/ BLADE, LOADER, ROLLER, SCRAPER, TRENCHER (OVER 8 FT DIGGING CAPACITY) | 45.98 | 25.25 | 71.23 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 9 OILER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 35.29 | 25.35 | 60.64 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 8 FORKLIFT FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 43.63 | 25.35 | 68.98 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 7 BACKHOE/EXCAVATOR, BOBCAT/SKID LOADER, BORING MACHINE, BROOM/SWEEPER, BULLDOZER, GRADER/BLADE, LOADER, ROLLER, SCRAPER, TRACTOR, TRENCHER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 45.34 | 25.35 | 70.69 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 6 REGULAR CRANE OPERATOR FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 46.31 | 25.35 | 71.66 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 5 CRANE WITH BOOM & JIB OR LEADS 120' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 47.17 | 25.35 | 72.52 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 4 CRANE WITH BOOM & JIB OR LEADS 140' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 47.99 | 25.35 | 73.34 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 3 CRANE WITH BOOM & JIB OR LEADS 220' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 48.29 | 25.35 | 73.64 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 2 CRANE WITH BOOM & JIB OR LEADS 300' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 49.79 | 25.35 | 75.14 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 1 CRANE WITH BOOM & JIB OR LEADS 400' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 51.29 | 25.35 | 76.64 |
| IRONWORKER: STRUCTURAL | 36.55 | 35.93 | 72.48 |
| IRONWORKER: REINFORCING | 36.55 | 33.37 | 69.92 |
| LANDSCAPE LABORER, EXCLUDES OPEN CUT CONSTRUCTION GROUP 2 LANDSCAPE LABORER: SMALL POWER TOOL OPERATOR, MATERIAL MOVER, TRUCK DRIVER AND LAWN SPRINKLER INSTALLER TENDER | 27.71 | 9.10 | 36.81 |
| LANDSCAPE LABORER, EXCLUDES OPEN CUT CONSTRUCTION GROUP 1 LANDSCAPE SPECIALIST, INCLUDING AIR, GAS AND DIESEL EQUIPMENT OPERATOR, LAWN SPRINKLER INSTALLER AND SKIDSTEER (OR EQUIVALENT) | 29.93 | 9.10 | 39.03 |
| LABORER ((7) LANDSCAPE) | 18.29 | 12.85 | 31.14 |
| LABORER ((5) PIPELAYER) | 23.84 | 13.52 | 37.36 |
| LABORER ((4) GRADE CHECKER) | 23.70 | 13.15 | 36.85 |
| LABORER ((2) MASON TENDER-CEMENT/CONCRETE) | 23.53 | 13.15 | 36.68 |
| LABORER ((1) COMMON OR GENERAL) | 23.39 | 13.15 | 36.54 |
| LABORER: COMMON OR GENERAL; GRADE CHECKER; MASON TENDER - CEMENT/CONCRETE; PIPELAYER (EXCLUDES OPEN CUT CONSTRUCTION) | 30.35 | 17.90 | 48.25 |
| PAINTER: SPRAY | 24.79 | 12.02 | 36.81 |
| PAINTER: BRUSH & ROLLER | 23.79 | 12.02 | 35.81 |
| CEMENT MASON/CONCRETE FINISHER | 32.23 | 22.11 | 54.34 |
| PLUMBER | 35.77 | 35.13 | 70.90 |
| PIPEFITTER | 40.41 | 29.35 | 69.76 |
| TRUCK DRIVER: OFF THE ROAD TRUCK | 20.82 | 3.69 | 24.51 |
| TRUCK DRIVER: LOWBOY/SEMI-TRAILER TRUCK FOOTNOTE: A. $470.70 PER WEEK. B. $68.70 DAILY | 33.55 | 0.75 | 34.30 |
| TRUCK DRIVER: DUMP TRUCK, 8 CU. YDS. AND OVER | 33.40 | 0.75 | 34.15 |
| TRUCK DRIVER: DUMP TRUCK UNDER 8 CU. YDS.; TRACTOR HAUL TRUCK FOOTNOTE: A. $470.70 PER WEEK. B $68.70 DAILY | 33.30 | 0.75 | 34.05 |