Heavy Published 05/18/2026. 33 classifications. Covers 1 county: Monroe
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| CARPENTER, INCLUDES FORM WORK | 42.44 | 31.43 | 73.87 |
| ELECTRICIAN | 48.40 | 17.79 | 66.19 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 4 BROOM/ SWEEPER, FORK TRUCK, TRACTOR, BOBCAT/ SKID STEER /SKID LOADER | 39.95 | 25.25 | 65.20 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 3 BOOM TRUCK (NON-SWINGING, NON- POWERED TYPE BOOM) | 40.52 | 25.25 | 65.77 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 2 TRENCHER (8-FT DIGGING CAPACITY AND SMALLER) | 41.25 | 25.25 | 66.50 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 1 BACKHOE/ EXCAVATOR, BORING MACHINE, BULLDOZER, CRANE, GRADER/ BLADE, LOADER, ROLLER, SCRAPER, TRENCHER (OVER 8 FT DIGGING CAPACITY) | 45.98 | 25.25 | 71.23 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 9 OILER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 35.29 | 25.35 | 60.64 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 8 FORKLIFT FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 43.63 | 25.35 | 68.98 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 7 BACKHOE/EXCAVATOR, BOBCAT/SKID LOADER, BORING MACHINE, BROOM/SWEEPER, BULLDOZER, GRADER/BLADE, LOADER, ROLLER, SCRAPER, TRACTOR, TRENCHER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 45.34 | 25.35 | 70.69 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 6 REGULAR CRANE OPERATOR FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 46.31 | 25.35 | 71.66 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 5 CRANE WITH BOOM & JIB OR LEADS 120' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 47.17 | 25.35 | 72.52 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 4 CRANE WITH BOOM & JIB OR LEADS 140' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 47.99 | 25.35 | 73.34 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 3 CRANE WITH BOOM & JIB OR LEADS 220' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 48.29 | 25.35 | 73.64 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 2 CRANE WITH BOOM & JIB OR LEADS 300' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 49.79 | 25.35 | 75.14 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 1 CRANE WITH BOOM & JIB OR LEADS 400' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | 51.29 | 25.35 | 76.64 |
| IRONWORKER: STRUCTURAL AND REINFORCING | 35.50 | 29.20 | 64.70 |
| LANDSCAPE LABORER, EXCLUDES OPEN CUT CONSTRUCTION GROUP 2 LANDSCAPE LABORER: SMALL POWER TOOL OPERATOR, MATERIAL MOVER, TRUCK DRIVER AND LAWN SPRINKLER INSTALLER TENDER | 27.71 | 9.10 | 36.81 |
| LANDSCAPE LABORER, EXCLUDES OPEN CUT CONSTRUCTION GROUP 1 LANDSCAPE SPECIALIST, INCLUDING AIR, GAS AND DIESEL EQUIPMENT OPERATOR, LAWN SPRINKLER INSTALLER AND SKIDSTEER (OR EQUIVALENT) | 29.93 | 9.10 | 39.03 |
| LABORER ((7) LANDSCAPE) | 19.59 | 12.95 | 32.54 |
| LABORER ((524.20) PIPELAYER) | 25.65 | 12.95 | 38.60 |
| LABORER ((4) GRADE CHECKER) | 25.50 | 12.95 | 38.45 |
| LABORER ((2) MASON TENDER-CEMENT/CONCRETE) | 22.11 | 12.95 | 35.06 |
| LABORER ((1) COMMON OR GENERAL) | 25.20 | 12.95 | 38.15 |
| LABORER, EXCLUDES OPEN CUT CONSTRUCTION: GROUP 2 MASON TENDER - CEMENT/CONCRETE | 38.80 | 15.70 | 54.50 |
| LABORER, EXCLUDES OPEN CUT CONSTRUCTION: GROUP 1 COMMON OR GENERAL; GRADE CHECKER | 38.58 | 15.70 | 54.28 |
| PAINTER: SPRAY | 25.86 | 14.75 | 40.61 |
| PAINTER: BRUSH & ROLLER | 25.06 | 14.75 | 39.81 |
| CEMENT MASON/CONCRETE FINISHER | 27.19 | 16.00 | 43.19 |
| PLUMBER | 43.79 | 23.94 | 67.73 |
| TRUCK DRIVER: OFF THE ROAD TRUCK | 20.82 | 3.69 | 24.51 |
| TRUCK DRIVER: LOWBOY/SEMI-TRAILER TRUCK FOOTNOTE: A. $470.70 PER WEEK. B. $68.70 DAILY | 33.65 | 0.75 | 34.40 |
| TRUCK DRIVER: DUMP TRUCK, 8 CU. YDS. AND OVER | 33.50 | 0.75 | 34.25 |
| TRUCK DRIVER: DUMP TRUCK UNDER 8 CU. YDS.; TRACTOR HAUL TRUCK FOOTNOTE: A. $470.70 PER WEEK. B $68.70 DAILY | 33.40 | 0.75 | 34.15 |