MI20260039 rev 1

Heavy  Published 05/18/2026. 28 classifications. Covers 1 county: Isabella

Check that the construction type above matches your contract. A county usually has several determinations and their rates differ. Verify at sam.gov.
ClassificationBase rateFringeTotal
CARPENTER (FORM WORK ONLY)33.1123.6456.75
ELECTRICIAN (TOWNSHIPS OF BLOOMFIELD, COLDWATER, DEERFIELD, FREMONT, GILMORE, NOTTAWA, ROLLAND & SHERMAN)36.5225.1561.67
ELECTRICIAN (TOWNSHIPS OF LINCOLN & COE)40.0029.9569.95
ELECTRICIAN (TOWNSHIPS OF CHIPPEWA, DENVER, ISABELLA, UNION, VERNON & WISE)40.0026.5266.52
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 4 BROOM/ SWEEPER, FORK TRUCK, TRACTOR39.9525.2565.20
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 3 BOOM TRUCK (NON-SWINGING, NON- POWERED TYPE BOOM)40.5225.2565.77
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 2 TRENCHER (8-FT DIGGING CAPACITY AND SMALLER)41.2525.2566.50
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 1 BACKHOE/ EXCAVATOR, BORING MACHINE, BULLDOZER, CRANE, SCRAPER, LOADER, TRENCHER (OVER 8 FT. DIGGING CAPACITY)45.9825.2571.23
OPERATOR: POWER EQUIPMENT: EXCLUDES UNDERGROUND CONSTRUCTION GROUP 5 OILER FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY32.9825.2558.23
OPERATOR: POWER EQUIPMENT: EXCLUDES UNDERGROUND CONSTRUCTION GROUP 4 BOOM TRUCK (NON-SWINGING) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY41.3225.2566.57
OPERATOR: POWER EQUIPMENT: EXCLUDES UNDERGROUND CONSTRUCTION GROUP 3 BACKHOE/EXCAVATOR; BULLDOZER; COMPACTOR; CRANE; SCRAPER; LOADER FOOTNOTES CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY44.0025.2569.25
MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY45.6825.2570.93
OPERATOR: POWER EQUIPMENT: EXCLUDES UNDERGROUND CONSTRUCTION GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER48.9825.2574.23
IRONWORKER: STRUCTURAL36.5535.9372.48
IRONWORKER: REINFORCING36.5533.3769.92
LABORER ((4) GRADE CHECKER)22.7312.9535.68
CEMENT MASON/CONCRETE FINISHER25.4712.3837.85
PLUMBER/PIPEFITTER43.5022.1065.60
TRUCK DRIVER: DUMP TRUCK14.061.2515.31
OPERATOR: ROLLER13.747.9321.67
OPERATOR: GRADER/BLADE15.503.6219.12
OPERATOR: BOBCAT/SKID STEER/SKID LOADER12.986.1219.10
LABORER: PIPELAYER15.283.9919.27
LABORER: MASON TENDER - CEMENT/CONCRETE15.973.5119.48
LABORER: LANDSCAPE10.891.7412.63
LABORER: COMMON OR GENERAL19.795.9525.74
CARPENTER, EXCLUDES FORM WORK23.976.2930.26
TRUCK DRIVER: LOWBOY/SEMI-TRAILER TRUCK FOOTNOTE: A. $470.70 PER WEEK. B. $68.70 DAILY33.550.7534.30
Filing the WH-347 that these rates feed into? I build certified payroll tools, and I will prepare your first weekly filing from your payroll register free, with worker names removed — partly to be useful, partly because real registers are the only way to test the thing properly. hamza.aiemployee@gmail.com. No sign-up on this site, and nothing here is tracked.