Heavy Published 05/18/2026. 29 classifications. Covers 1 county: Emmet
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| CARPENTER, INCLUDES FORM WORK | 30.83 | 21.09 | 51.92 |
| ELECTRICIAN (EXCLUDING THE TOWNSHIP OF WAWATAN) | 36.62 | 23.05 | 59.67 |
| ELECTRICIAN (TOWNSHIP OF WAWATAN) | 37.75 | 25.60 | 63.35 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 4 BROOM/ SWEEPER, FORK TRUCK, TRACTOR | 39.95 | 25.25 | 65.20 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 3 BOOM TRUCK (NON-SWINGING, NON- POWERED TYPE BOOM) | 40.52 | 25.25 | 65.77 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 2 TRENCHER (8-FT DIGGING CAPACITY AND SMALLER) | 41.25 | 25.25 | 66.50 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 1 BORING MACHINE, CRANE, SCRAPER, TRENCHER (OVER 8 FT. DIGGING CAPACITY) | 45.98 | 25.25 | 71.23 |
| OPERATOR: POWER EQUIPMENT: EXCLUDES UNDERGROUND CONSTRUCTION GROUP 5 OILER FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 32.98 | 25.25 | 58.23 |
| OPERATOR: POWER EQUIPMENT: EXCLUDES UNDERGROUND CONSTRUCTION GROUP 4 BOOM TRUCK (NON-SWINGING) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 41.32 | 25.25 | 66.57 |
| OPERATOR: POWER EQUIPMENT: EXCLUDES UNDERGROUND CONSTRUCTION GROUP 3 COMPACTOR; CRANE; SCRAPER FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 44.00 | 25.25 | 69.25 |
| MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 45.68 | 25.25 | 70.93 |
| OPERATOR: POWER EQUIPMENT: EXCLUDES UNDERGROUND CONSTRUCTION GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER. FOOTNOTES CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 48.98 | 25.25 | 74.23 |
| IRONWORKER: STRUCTURAL | 36.55 | 34.04 | 70.59 |
| IRONWORKER: REINFORCING | 36.55 | 34.04 | 70.59 |
| LABORER ((4) GRADE CHECKER) | 22.73 | 12.95 | 35.68 |
| CEMENT MASON/CONCRETE FINISHER | 23.10 | 12.38 | 35.48 |
| TRUCK DRIVER: DUMP TRUCK | 12.63 | 1.25 | 13.88 |
| PLUMBER | 17.53 | 4.17 | 21.70 |
| OPERATOR: LOADER | 13.26 | 8.36 | 21.62 |
| OPERATOR: ROLLER | 13.74 | 7.93 | 21.67 |
| OPERATOR: GRADER/BLADE | 15.50 | 3.62 | 19.12 |
| OPERATOR: BULLDOZER | 16.17 | 9.51 | 25.68 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | 12.98 | 6.12 | 19.10 |
| OPERATOR: BACKHOE/EXCAVATOR | 14.24 | 8.11 | 22.35 |
| LABORER: PIPELAYER | 15.28 | 3.99 | 19.27 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | 15.97 | 3.51 | 19.48 |
| LABORER: LANDSCAPE | 10.89 | 1.74 | 12.63 |
| LABORER: COMMON OR GENERAL | 13.13 | 6.75 | 19.88 |
| TRUCK DRIVER: LOWBOY/SEMI-TRAILER TRUCK FOOTNOTE: A. $470.70 PER WEEK. B. $68.70 DAILY | 33.55 | 0.75 | 34.30 |