Residential Published 05/18/2026. 58 classifications. Covers 1 county: Franklin
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| INSULATOR/ASBESTOS WORKER (INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHES TO ALL TYPES OF MECHANICAL SYSTEMS.) | 44.36 | 36.63 | 80.99 |
| BOILERMAKER | 50.62 | 28.82 | 79.44 |
| BRICKLAYERS; CEMENT MASONS; PLASTERERS; STONE MASONS; MARBLE, TILE & TERRAZZO WORKERS (SPRINGFIELD CHAPTER) | 50.81 | 32.27 | 83.08 |
| CARPENTERS (FRANKLIN (ERVING, NORTH ORANGE, ORANGE, WARWICK)) | 43.33 | 27.82 | 71.15 |
| CARPENTER: ALL OTHER WORK (FRANKLIN (EXCEPT ERVING, ORANGE, NORTH ORANGE, WARWICK)) | 43.33 | 27.82 | 71.15 |
| CARPENTER, NEW WOOD FRAME CONSTRUCTION NOT EXCEEDING 4 STORIES INCLUDING BASEMENT (WOOD FRAMING, SIDING AND EXTERIOR TRIM WORK) | 26.55 | 13.02 | 39.57 |
| CARPENTER, NEW WOOD FRAME CONSTRUCTION NOT EXCEEDING 4 STORIES INCLUDING BASEMENT (ALL OTHER CARPENTRY WORK ON WOOD FRAME PROJECTS) | 26.55 | 13.02 | 39.57 |
| FLOOR LAYER: CARPET | 43.23 | 27.79 | 71.02 |
| ELECTRICIAN | 52.16 | 29.56 | 81.72 |
| ELEVATOR MECHANIC FOOTNOTE: A.VACATION 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. B. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING DAY; AND CHRISTMAS DAY | 66.41 | 38.44 | 104.85 |
| POWER EQUIPMENT OPERATORS: GROUP 15 BOOM LENGTHS OVER 350 FEET INCLUDING JIB HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 50.73 | 30.58 | 81.31 |
| POWER EQUIPMENT OPERATORS: GROUP 14 BOOM LENGTHS OVER 300 FEET INCLUDING JIB HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 49.23 | 30.58 | 79.81 |
| POWER EQUIPMENT OPERATORS: GROUP 13 BOOM LENGTHS OVER 250 FEET INCLUDING JIB HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 48.23 | 30.58 | 78.81 |
| POWER EQUIPMENT OPERATORS: GROUP 12 BOOM LENGTHS OVER 200 FEET INCLUDING JIB HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 47.23 | 30.58 | 77.81 |
| POWER EQUIPMENT OPERATORS: GROUP 11 BOOM LENGTHS OVER 150 FEET INCLUDING JIB HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 45.73 | 30.58 | 76.31 |
| POWER EQUIPMENT OPERATORS: GROUP 10 MASTER MECHANIC HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 44.73 | 30.58 | 75.31 |
| POWER EQUIPMENT OPERATORS: GROUP 9 OILER HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 42.72 | 30.58 | 73.30 |
| POWER EQUIPMENT OPERATORS: GROUP 8 TRUCK CRANE CREWS HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 42.41 | 30.58 | 72.99 |
| POWER EQUIPMENT OPERATORS: GROUP 7 COMPRESSORS UP TO 315 CU FT; SMALL MIXERS WITH SKIP; PUMPS UP TO 4 INCHES; POWER HEATERS; OILER; A-FRAME TRUCKS; FORKLIFTS-UP TO 7 FT. LIFT AND UP TO 3 TON CAPACITY; HYDRO BROOM; STUD WELDER. HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 52.73 | 30.58 | 83.31 |
| POWER EQUIPMENT OPERATORS: GROUP 6 COMPRESSOR (ONE OR TWO) 315 CU FT TO 900 CU FT; PUMPS 4 INCHES TO 16 INCHES (TOTAL DISCHARGE). HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 34.41 | 30.58 | 64.99 |
| POWER EQUIPMENT OPERATORS: GROUP 5 HOISTS; CONVEYORS; POWER PAVEMENT BREAKERS; SELF-POWERED CONCRETE PAVEMENT FINISHING MACHINES; TWO BAG MIXERS WITH SKIP; MCCARTHY AND SIMILAR DRILLS; BATCH PLANTS (NOT SELF LOADING); BULK CEMENT PLANTS; SELF-PROPELLED MATERIAL SPREADERS; THREE OR MORE 10 KW LIGHT PLANTS; 30 KW OR MORE GENERATORS; POWER BROOM. HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 36.35 | 30.58 | 66.93 |
| POWER EQUIPMENT OPERATORS: GROUP 4 ASPHALT ROLLERS; SELF-POWERED ROLLERS AND COMPACTORS; TRACTOR WITHOUT BLADE DRAWING SHEEPSFOOT ROLLER; RUBBER TIRE ROLLER; VIBRATORY ROLLER OR OTHER TYPE OF COMPACTORS INCLUDING MACHINES FOR PULVERIZING AND AERATING SOIL; YORK RAKE. HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 37.47 | 30.58 | 68.05 |
| POWER EQUIPMENT OPERATORS: GROUP 3 COMBINATION BACKHOE/LOADER UP TO 3/4 CU YD; SCRAPERS UP TO 21 CU YD (STRUCK LOAD, SELF PROPELLED OR TRACTOR DRAWN); TIREMAN; FRONT END LOADERS UP TO 4 YDS; WELL DRILLERS; ENGINEER OR FIREMAN ON HIGH PRESSURE BOILER; SELF-LOADING BATCH PLANT; WELL POINT OPERATORS ELECTRIC PUMPS USED IN WELL POINT SYSTEM; PUMPS, 16 INCHES AND OVER (TOTAL DISCHARGE); COMPRESSOR, ONE OR TWO 900 CU FT AND OVER; POWERED GREASE TRUCK; TUNNEL LOCOMOTIVES AND DINGYS; GROUT PUMPS; HYDRAULIC JACKS; BOOM TRUCK; HYDRAULIC CRANES- UP TO 10 TON. HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 40.70 | 30.58 | 71.28 |
| POWER EQUIPMENT OPERATORS: GROUP 2 ROTARY DRILL WITH MOUNTED COMPRESSOR; COMPRESSOR HOUSE (3 TO 6 COMPRESSORS); ROCK AND EARTH BORING MACHINES (EXCLUDING MCCARTHY AND SIMILAR DRILLS); FRONT END LOADERS 4 CU YDS TO 5 1/2 CU YDS); FORKLIFTS-7 FT LIFT AND OVER 3 TON CAPACITY; SCRAPER 21 YDS AND OVER (STRUCK LOAD); SONIC HAMMER CONSOLE; RECLAIMERS ROAD PLANER/MILLING MACHINE; CAL TRACKS; BALLAST REGULATORS; RAIL ANCHOR MACHINES; SWITCH TAMPERS, ASPHALT PAVERS; MECHANIC; WELDER AND TRANSFER MACHINE. HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 40.92 | 30.58 | 71.50 |
| CRAWLERS AND TRUCK CRANES INCLUDING ALL TOWER; SELF-PROPELLED HYDRAULIC CRANES 10 TONS AND OVER; DRAGLINES; CLAM SHELLS; CABLEWAYS; SHAFT HOISTS; MUCKING MACHINES DERRICKS; BACKHOES; BULLDOZERS; GRADALLS; ELEVATING GRADERS; PILE DRIVERS; CONCRETE PAVERS; TRENCHING MACHINES; FRONT END LOADERS- 5 1/2 CU YDS AND OVER; DUAL DRUM PAVER; AUTOMATIC GRADER-EXCAVATOR(C.M.I. OR EQUAL); SCRAPERS TOWING PAN OR WAGON; TANDEM DOZERS OR PUSH CATS(2 UNITS IN TANDEM); SHOTCRETE MACHINE; TUNNEL BORING MACHINE; COMBINATION BACKHOE/LOADER 3/4 CU YD HOE OR OVER; JET ENGINE DRYER; TREE SHREDDER; POST HOLE DIGGER; POST HOLE HAMMER; POST EXTRACTOR; TRUCK MOUNTED CONCRETE PUMP WITH BOOM; ROTO-MILL; GRADER; HORIZONTAL DRILLING MACHINE; JOHN HENRY ROCK DRILL AND SIMILAR EQUIPMENT. HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 41.23 | 30.58 | 71.81 |
| IRONWORKER | 41.89 | 33.90 | 75.79 |
| LABORERS: GROUP 6 ASBESTOS ABATEMENT, TOXIC AND HAZARDOUS WASTE LABORERS (FRANKLIN (ORANGE, WARWICK)) | 38.95 | 29.70 | 68.65 |
| LABORERS: GROUP 5 FLAGGER (FRANKLIN (ORANGE, WARWICK)) | 38.95 | 29.70 | 68.65 |
| LABORERS: GROUP 4 BLASTER; POWDERMAN (FRANKLIN (ORANGE, WARWICK)) | 38.95 | 29.70 | 68.65 |
| LABORERS: GROUP 3 AIR TRACK OPERATOR; BLOCK PAVER; RAMMER; CURB SETTER;HYDRAULIC & SIMILAR SELF POWERED DRILLS (FRANKLIN (ORANGE, WARWICK)) | 38.95 | 29.70 | 68.65 |
| LABORERS: GROUP 2 ASPHALT RAKER; FENCE AND GUARD RAIL ERECTOR; LASER BEAM OPERATOR; MASON TENMDER; PIPELAYER; PNEUMATIC DRILL OPERATOR; PNEUMATIC TOOL OPERATOR; WAGON DRILL OPERATOR (FRANKLIN (ORANGE, WARWICK)) | 38.95 | 29.70 | 68.65 |
| LABORERS: GROUP 1 LABORERS; CARPENTER TENDERS; CEMENT FINISHER TENDERS (FRANKLIN (ORANGE, WARWICK)) | 38.95 | 29.70 | 68.65 |
| LABORERS: GROUP 5 POWDERMAN AND BLASTER (FRANKLIN (EXCEPT ORANGE, WARWICK)) | 33.50 | 26.02 | 59.52 |
| LABORERS: GROUP 4 AIR TRACK OPERATORS, BLOCK PAVERS, RAMMERS AND CURB SETTERS (FRANKLIN (EXCEPT ORANGE, WARWICK)) | 33.25 | 26.02 | 59.27 |
| LABORERS: GROUP 3 PRECAST FLOOR AND ROOF PLANK ERECTORS, SIGN ERECTORS, ASBESTOS REMOVAL LABORERS (FRANKLIN (EXCEPT ORANGE, WARWICK)) | 33.25 | 26.02 | 59.27 |
| LABORERS: GROUP 2 ASPHALT RAKERS, CARBIDE CORE DRILLER OPERATORS, CHAIN SAW OPERATORS, PIPELAYERS, JACKHAMMER AND PAVING BREAKER OPERATORS, BARCO TYPE JUMPING TAMPERS, LASER BEAM OPERATORS, CONCRETE PUMP OPERATORS, MASON TENDERS, MORTAR MIXERS, RIDE-ON MOTORIZED BUGGY OPERATORS, WAGON DRILL OPERATORS (FRANKLIN (EXCEPT ORANGE, WARWICK)) | 32.75 | 26.02 | 58.77 |
| LABORERS: GROUP 1 LABORERS, CARPENTER TENDERS, WRECKING LABORERS (FRANKLIN (EXCEPT ORANGE, WARWICK)) | 32.50 | 26.02 | 58.52 |
| LABORERS:, WRECKING: GROUP 6 ASBESTOS, LEAD PAINT, TOXIC AND HAZARDOUS WASTE | 46.25 | 29.70 | 75.95 |
| LABORERS:, WRECKING: GROUP 5 YARDMAN, BURNERS, SAWYERS | 45.35 | 29.70 | 75.05 |
| LABORERS:, WRECKING: GROUP 4 YARDMAN (SALVAGE YARD ONLY) | 42.25 | 29.70 | 71.95 |
| LABORERS:, WRECKING: GROUP 3 SMALL BACKHOES, LOADERS ON TRACKS, BOBCAT TYPE LOADERS, HYDRAULIC ""BROCK"" TYPE HAMMER OPERATORS, CONCRETE CUTTING SAWS | 47.25 | 29.70 | 76.95 |
| LABORERS:, WRECKING: GROUP 2 BURNERS, JACKHAMMERS | 47.00 | 29.70 | 76.70 |
| LABORERS:, WRECKING: GROUP 1 ADZEMAN, WRECKING LABORER | 46.25 | 29.70 | 75.95 |
| PAINTER: SPRAY, SANDBLAST | 39.48 | 31.85 | 71.33 |
| PAINTER: BRUSH, TAPER | 38.08 | 31.85 | 69.93 |
| PLUMBER AND STEAMFITTER (FRANKLIN (ORANGE)) | 55.00 | 31.57 | 86.57 |
| THE HOLIDAY BY THE SAME EMPLOYER | 52.26 | 31.05 | 83.31 |
| PLUMBER AND STEAMFITTER (FRANKLIN (MONROE, ROWE, AND THE WESTERN PART OF CHARLEMONT)) FOOTNOTE FOR PLUMBERS & STEAMFITTERS: A. PAID HOLIDAYS INDEPENDENCE DAY AND LABOR DAY, PROVIDED THE EMPLOYEE HAS BEEN EMPLOYED SEVEN DAYS PRIOR TO THE HOLIDAY BY THE SAME EMPLOYER | 52.26 | 31.05 | 83.31 |
| ROOFERS (PITCH, SLATE, TILE AND PRECAST CONCRETE) | 42.48 | 30.14 | 72.62 |
| ROOFERS (COMPOSITION ROOFERS & DAMP WATERPROOFERS) | 42.48 | 30.14 | 72.62 |
| SHEET METAL WORKER | 43.48 | 36.46 | 79.94 |
| TRUCK DRIVERS: GROUP 7 TRAILERS FOR EARTH MOVING EQUIPMENT (DOUBLE HOOKUP) POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM. FOOTNOTES: A PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | 41.82 | 37.35 | 79.17 |
| TRUCK DRIVERS: GROUP 6 SPECIALIZED EARTH MOVING EQUIPMENT OVER 35 TONS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM. FOOTNOTES: A PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | 41.53 | 37.35 | 78.88 |
| TRUCK DRIVERS: GROUP 5 SPECIALIZED EARTH MOVING EQUIPMENT UNDER 35 TONS OTHER THAN CONVENTIONAL TYPE TRUCKS; LOW BED; VACHUAL; MECHANICS, PAVING RESTORATION EQUIPMENT POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM. FOOTNOTES: A PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | 41.24 | 37.35 | 78.59 |
| TRUCK DRIVERS: GROUP 4 FOUR AND FIVE AXLE EQUIPMENT POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM. FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | 41.14 | 37.35 | 78.49 |
| TRUCK DRIVERS: GROUP 3 THREE AXLE EQUIPMENT AND TIREMAN POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM. FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | 41.02 | 37.35 | 78.37 |
| TRUCK DRIVERS: GROUP 2 TWO AXLE EQUIPMENT; & FORKLIFT OPERATOR POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM. FOOTNOTES: A PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | 40.95 | 37.35 | 78.30 |
| TRUCK DRIVERS: GROUP 1 STATION WAGONS; PANEL TRUCKS; AND PICKUP TRUCKS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM. FOOTNOTES: A PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | 40.78 | 37.35 | 78.13 |