Building Published 05/18/2026. 36 classifications. Covers 1 county: Hardin
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| BOILERMAKER | 43.85 | 28.44 | 72.29 |
| ELECTRICIAN | 40.96 | 22.44 | 63.40 |
| POWER EQUIPMENT OPERATOR (DRILL) | 40.65 | 19.60 | 60.25 |
| POWER EQUIPMENT OPERATOR: LOADER | 40.65 | 19.60 | 60.25 |
| POWER EQUIPMENT OPERATOR: CRANE CRANES WITH BOOM 150 FEET & OVER, INCLUDING JIB, SHALL RECEIVE $.75 ABOVE THE WAGE RATE; 250 FEET AND OVER, INCLUDING JIB, SHALL RECEIVE $1.50 ABOVE THE WAGE RATE. ALL CRANES WITH PILING LEADS WILL RECEIVE $.50 ABOVE THE WAGE, REGARDLESS OF BOOM LENGTH | 40.65 | 19.60 | 60.25 |
| POWER EQUIPMENT OPERATOR: FORKLIFT | 40.65 | 19.60 | 60.25 |
| POWER EQUIPMENT OPERATOR (OILER) | 34.99 | 19.60 | 54.59 |
| IRONWORKER: ORNAMENTAL | 37.77 | 23.90 | 61.67 |
| IRONWORKER (STRUCTURAL AND REINFORCING) | 36.17 | 25.80 | 61.97 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | 26.89 | 13.32 | 40.21 |
| LABORER: POWER TOOL OPERATOR | 26.89 | 13.32 | 40.21 |
| PLUMBER | 41.90 | 24.89 | 66.79 |
| PIPEFITTER | 41.90 | 24.89 | 66.79 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | 44.15 | 26.08 | 70.23 |
| SHEET METAL WORKER (INCLUDES HVAC DUCT INSTALLATION) | 40.32 | 25.66 | 65.98 |
| TRUCK DRIVER: DUMP TRUCK | 23.60 | 8.03 | 31.63 |
| TILE SETTER | 22.64 | 6.10 | 28.74 |
| TILE FINISHER | 15.42 | 5.63 | 21.05 |
| ROOFER | 20.61 | 5.12 | 25.73 |
| PAINTER: SPRAY | 22.81 | 11.87 | 34.68 |
| PAINTER (BRUSH AND ROLLER) | 20.83 | 11.84 | 32.67 |
| OPERATOR: ROLLER | 23.60 | 12.65 | 36.25 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | 22.52 | 4.00 | 26.52 |
| OPERATOR: BULLDOZER | 21.49 | 3.84 | 25.33 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | 24.35 | 13.00 | 37.35 |
| LABORER: PIPELAYER | 20.36 | 9.90 | 30.26 |
| LABORER: MASON TENDER - BRICK | 19.24 | 3.79 | 23.03 |
| LABORER: COMMON OR GENERAL | 18.86 | 5.22 | 24.08 |
| CEMENT MASON/CONCRETE FINISHER | 20.21 | 9.70 | 29.91 |
| CARPENTER: FLOOR LAYING-VINYL ONLY | 29.99 | 1.32 | 31.31 |
| CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING AND METAL STUD INSTALLATION, FORMWORK AND FLOOR LAYING - VINYL | 23.54 | 9.10 | 32.64 |
| CARPENTER (FORM WORK ONLY) | 22.19 | 12.25 | 34.44 |
| CARPENTER (DRYWALL HANGING AND METAL STUD INSTALLATION ONLY) | 21.72 | 13.52 | 35.24 |
| CARPENTER (ACOUSTICAL CEILING INSTALLATION ONLY) | 25.77 | 7.40 | 33.17 |
| BRICKLAYER | 24.24 | 8.25 | 32.49 |
| ASBESTOS WORKER/HEAT & FROST INSULATOR | 26.83 | 12.67 | 39.50 |