| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| CARPENTER (FORM WORK ONLY) | 33.89 | 24.06 | 57.95 |
| LINE CONSTRUCTION: TRUCK DRIVER FOOTNOTE: A. 6 OBSERVED HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; & CHRISTMAS DAY. EMPLOYEES WHO WORK ON A HOLIDAY SHALL BE PAID AT A RATE OF DOUBLE THEIR APPLICABLE CLASSIFIED STRAIGHT-TIME RATES FOR THE WORK PERFORMED ON SUCH HOLIDAY | 16.93 | 9.77 | 26.70 |
| LINE CONSTRUCTION: LINEMAN | 43.84 | 18.80 | 62.64 |
| LINE CONSTRUCTION: GROUNDMAN | 25.77 | 14.10 | 39.87 |
| LINE CONSTRUCTION: EQUIPMENT OPERATOR | 39.15 | 17.58 | 56.73 |
| ELECTRICIAN | 40.96 | 22.44 | 63.40 |
| POWER EQUIPMENT OPERATOR GROUP 4 OILER; PUMP OPERATORS ON CRANES WITH BOOMS 150 FEET AND OVER (INCLUDING JIB) SHALL RECEIVE $1.00 ABOVE GROUP 1 RATE; 250 FEET AND OVER INCLUDING JIB SHALL RECEIVE $1.50 ABOVE CLASS 1 RATE. COMBINATION RATE: ALL CRANE OPERATORS OPERATING CRANES, WHERE THE LENGTH OF THE BOOM IN COMBINATION WITH THE LENGTH OF THE PILING LEADS EQUAL OR EXCEEDS 150 FEET, SHALL RECEIVE $1.00 ABOVE THE GROUP 1 RATE. EMPLOYEES ASSIGNED TO WORK BELOW GROUND LEVEL ARE TO BE PAID 10% ABOVE BASIC WAGE RATE. THIS DOES NOT APPLY TO OPEN CUT WORK | 38.37 | 19.60 | 57.97 |
| POWER EQUIPMENT OPERATOR GROUP 2 BOBCAT/SKID STEER/SKID LOADER; CONCRETE PUMP OPERATORS ON CRANES WITH BOOMS 150 FEET AND OVER (INCLUDING JIB) SHALL RECEIVE $1.00 ABOVE GROUP 1 RATE; 250 FEET AND OVER INCLUDING JIB SHALL RECEIVE $1.50 ABOVE CLASS 1 RATE. COMBINATION RATE: ALL CRANE OPERATORS OPERATING CRANES, WHERE THE LENGTH OF THE BOOM IN COMBINATION WITH THE LENGTH OF THE PILING LEADS EQUAL OR EXCEEDS 150 FEET, SHALL RECEIVE $1.00 ABOVE THE GROUP 1 RATE. EMPLOYEES ASSIGNED TO WORK BELOW GROUND LEVEL ARE TO BE PAID 10% ABOVE BASIC WAGE RATE. THIS DOES NOT APPLY TO OPEN CUT WORK | 38.69 | 19.60 | 58.29 |
| LENGTH OF THE PILING LEADS EQUAL OR EXCEEDS 150 FEET, SHALL RECEIVE $1.00 ABOVE THE GROUP 1 RATE EMPLOYEES ASSIGNED TO WORK BELOW GROUND LEVEL ARE TO BE PAID 10% ABOVE BASIC WAGE RATE. THIS DOES NOT APPLY TO OPEN CUT WORK | 41.55 | 19.60 | 61.15 |
| IRONWORKER: ORNAMENTAL AND REINFORCING | 36.17 | 25.80 | 61.97 |
| LABORER: GRADE CHECKER & SIGNAL MAN | 26.87 | 19.66 | 46.53 |
| LABORER: CHIPPING GUNS, FORM-STRIPPING & VIBRATING PLATE | 27.12 | 19.66 | 46.78 |
| LABORER: FLAGGER | 35.52 | 14.45 | 49.97 |
| LABORER: CONCRETE SAW (HAND HELD/WALK BEHIND) | 35.69 | 14.45 | 50.14 |
| LABORER: CARPENTER TENDER & CONCRETE WORKER | 28.94 | 17.59 | 46.53 |
| LABORER: BLASTER, TUNNEL; CONCRETE FINISHING & POWDERMAN | 29.84 | 17.59 | 47.43 |
| TRUCK DRIVER: DUMP TRUCK | 16.80 | 4.06 | 20.86 |
| OPERATOR: TRENCHER | 26.34 | 12.58 | 38.92 |
| OPERATOR: ROLLER | 23.39 | 13.00 | 36.39 |
| OPERATOR: MECHANIC | 25.81 | 13.00 | 38.81 |
| OPERATOR: LOADER | 26.50 | 13.00 | 39.50 |
| OPERATOR: BULLDOZER | 24.73 | 15.19 | 39.92 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | 26.43 | 13.00 | 39.43 |
| LABORER: PIPELAYER | 23.90 | 9.76 | 33.66 |
| LABORER: COMMON OR GENERAL | 20.36 | 10.62 | 30.98 |
| LABORER: BACKFILLER | 20.21 | 10.19 | 30.40 |
| IRONWORKER, STRUCTURAL | 25.46 | 17.49 | 42.95 |
| OPERATOR: FORKLIFT | 40.05 | 19.10 | 59.15 |