Building Published 05/18/2026. 33 classifications. Covers 1 county: Butler
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | 45.60 | 35.47 | 81.07 |
| TILE FINISHER | 20.74 | 1.46 | 22.20 |
| TILE SETTER | 30.18 | 13.52 | 43.70 |
| ELECTRICIAN (INCLUDING ALARM INSTALLATION) | 40.64 | 18.29 | 58.93 |
| ELEVATOR MECHANIC A. VACATION PAY: 6% FOR 6 MONTHS TO 5 YEARS SERVICE; 8% WITH 5 OR MORE YEARS OF SERVICE. B. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY AND FRIDAY AFTER, AND CHRISTMAS DAY | 60.69 | 38.44 | 99.13 |
| POWER EQUIPMENT OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | 45.48 | 22.42 | 67.90 |
| POWER EQUIPMENT OPERATOR: OILER | 39.93 | 22.42 | 62.35 |
| POWER EQUIPMENT OPERATOR: BOBCAT/SKID STEER/SKID LOADER | 45.48 | 22.42 | 67.90 |
| IRONWORKER: ORNAMENTAL/REINFORCING | 39.00 | 34.25 | 73.25 |
| IRONWORKER, STRUCTURAL | 27.49 | 13.63 | 41.12 |
| PAINTER: BRUSH, ROLLER, AND SPRAY | 36.18 | 19.97 | 56.15 |
| PLUMBER | 45.90 | 19.94 | 65.84 |
| PIPEFITTER (HVAC PIPE INSTALLATION ONLY) | 45.90 | 19.94 | 65.84 |
| PIPEFITTER (EXCLUDES HVAC PIPE INSTALLATION) | 55.56 | 25.80 | 81.36 |
| SPRINKLER FITTER: FIRE SPRINKLER | 41.83 | 27.60 | 69.43 |
| TRUCK DRIVER: DUMP (ALL TYPES) | 19.63 | 5.26 | 24.89 |
| SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION.$ 22.44 4.70 SHEET METAL WORKER (HVAC DUCT INSTALLATION ONLY) | 24.68 | 6.91 | 31.59 |
| ROOFER | 13.46 | 1.51 | 14.97 |
| OPERATOR: ROLLER | 33.78 | 13.64 | 47.42 |
| OPERATOR: LOADER | 30.35 | 12.04 | 42.39 |
| OPERATOR: GRADER/BLADE | 29.58 | 11.51 | 41.09 |
| OPERATOR: FORKLIFT | 34.83 | 14.16 | 48.99 |
| OPERATOR: CRANE | 33.19 | 14.16 | 47.35 |
| OPERATOR: BULLDOZER | 33.12 | 13.96 | 47.08 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | 20.50 | 3.49 | 23.99 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | 12.99 | 1.67 | 14.66 |
| LABORER: MASON TENDER - BRICK | 19.91 | 6.88 | 26.79 |
| LABORER: COMMON OR GENERAL | 13.00 | 1.36 | 14.36 |
| CEMENT MASON/CONCRETE FINISHER | 17.17 | 2.23 | 19.40 |
| CARPENTER | 17.62 | 1.93 | 19.55 |
| BRICKLAYER, EXCLUDES TILE FINISHER AND TILE SETTER | 21.85 | 3.04 | 24.89 |
| TRUCK DRIVER: LOWBOY TRUCK | 39.89 | 15.85 | 55.74 |
| TRUCK DRIVER: SEMI-TRAILER TRUCK | 39.89 | 15.85 | 55.74 |