Residential Published 05/18/2026. 20 classifications. Covers 1 county: Winnebago
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| TILE SETTER | 38.52 | 21.86 | 60.38 |
| CARPENTER (INCLUDING SOFT FLOOR LAYER AND BATT/BLOWN INSULATION) | 37.19 | 26.60 | 63.79 |
| ELECTRICIAN | 30.61 | 28.17 | 58.78 |
| ELEVATOR MECHANIC FOOTNOTES: A. EMPLOYER CONTRIBUTES 8% OF REGULAR BASIC HOURLY RATE AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YEARS OF SERVICE, AND 6% FOR UNDER 5 YEARS OF SERVICE. B. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, FRIDAY AFTER THANKSGIVING DAY, VETERANS' DAY AND CHRISTMAS DAY | 65.17 | 38.44 | 103.61 |
| OPERATOR: POWER EQUIPMENT: GROUP 4 OILERS; PREMIUM PAY: LONG BOOM: CRANES & DERRICKS 90' TO 150' INCLUDING JIB RECEIVE AN EXTRA $.50 PER HOUR. CRANES & DERRICKS OVER 150' INCLUDING JIB RECEIVE AN EXTRA $.50 PER HOUR PLUS AN ADDITIONAL $.10 FOR EACH ADDITIONAL 10' OF BOOM OR JIB CAPACITY PAY: CRANES & DERRICKS WITH MAXIMUM CAPACITY EXCEEDING 50 TON WITH LESS THAN 90' OF BOOM OR JIB SHALL BE COMPENSATED $.01 PER HOUR FOR EACH TON OF THE RATED CAPACITY IN EXCESS OF 50 TON LONG BOOM PAY AND CAPACITY PAY CANNOT BE COMBINED. CRANE MOUNTED EARTH AUGER, RAISED AND BLIND HOLE DRILLS, AND TRUCK MOUNTED DRILL RIGS RECEIVE AN EXTRA $.50 PER HOUR. CRETER CRANES WHEN THE CRETER CRANE IS EQUIPPED WITH A CONVEYOR SYSTEM CAPABLE OF EXTENDING 70' OR MORE, THE ENGINEER SHALL RECEIVE AN EXTRA $.50 PER HOUR TRUCK MOUNTED CONCRETE PUMPS: WHEN THE TRUCK MOUNTED CONCRETE PUMP IS EQUIPPED WITH A BOOM, WHICH IS CAPABLE OF EXTENDING 90' OR MORE, THE ENGINEER SHALL RECEIVE $.50 PER HOUR EXTRA | 51.60 | 51.05 | 102.65 |
| TRUCK MOUNTED CONCRETE PUMPS: WHEN THE TRUCK MOUNTED CONCRETE PUMP IS EQUIPPED WITH A BOOM, WHICH IS CAPABLE OF EXTENDING 90' OR MORE, THE ENGINEER SHALL RECEIVE $.50 PER HOUR EXTRA | 53.60 | 51.05 | 104.65 |
| PER HOUR); *-REQUIRES OILER PREMIUM PAY: LONG BOOM: CRANES & DERRICKS 90' TO 150' INCLUDING JIB RECEIVE AN EXTRA $.50 PER HOUR. CRANES & DERRICKS OVER 150' INCLUDING JIB RECEIVE AN EXTRA $.50 PER HOUR PLUS AN ADDITIONAL $.10 FOR EACH ADDITIONAL 10' OF BOOM OR JIB. CAPACITY PAY: CRANES & DERRICKS WITH MAXIMUM CAPACITY EXCEEDING 50 TON WITH LESS THAN 90' OF BOOM OR JIB SHALL BE COMPENSATED $.01 PER HOUR FOR EACH TON OF THE RATED CAPACITY IN EXCESS OF 50 TON. LONG BOOM PAY AND CAPACITY PAY CANNOT BE COMBINED. CRANE MOUNTED EARTH AUGER, RAISED AND BLIND HOLE DRILLS, AND TRUCK MOUNTED DRILL RIGS RECEIVE AN EXTRA $.50 PER HOUR. CRETER CRANES: WHEN THE CRETER CRANE IS EQUIPPED WITH A CONVEYOR SYSTEM CAPABLE OF EXTENDING 70' OR MORE, THE ENGINEER SHALL RECEIVE AN EXTRA $.50 PER HOUR. TRUCK MOUNTED CONCRETE PUMPS: WHEN THE TRUCK MOUNTED CONCRETE PUMP IS EQUIPPED WITH A BOOM, WHICH IS CAPABLE OF EXTENDING 90' OR MORE, THE ENGINEER SHALL RECEIVE $.50 PER HOUR EXTRA | 56.05 | 51.05 | 107.10 |
| AND TRENCHING MACHINES*. *-REQUIRES OILER PREMIUM PAY: LONG BOOM: CRANES & DERRICKS 90' TO 150' INCLUDING JIB RECEIVE AN EXTRA $.50 PER HOUR. CRANES & DERRICKS OVER 150' INCLUDING JIB RECEIVE AN EXTRA $.50 PER HOUR PLUS AN ADDITIONAL $.10 FOR EACH ADDITIONAL 10' OF BOOM OR JIB CAPACITY PAY: CRANES & DERRICKS WITH MAXIMUM CAPACITY EXCEEDING 50 TON WITH LESS THAN 90' OF BOOM OR JIB SHALL BE COMPENSATED $.01 PER HOUR FOR EACH TON OF THE RATED CAPACITY IN EXCESS OF 50 TON LONG BOOM PAY AND CAPACITY PAY CANNOT BE COMBINED. CRANE MOUNTED EARTH AUGER, RAISED AND BLIND HOLE DRILLS, AND TRUCK MOUNTED DRILL RIGS RECEIVE AN EXTRA $.50 PER HOUR. CRETER CRANES WHEN THE CRETER CRANE IS EQUIPPED WITH A CONVEYOR SYSTEM CAPABLE OF EXTENDING 70' OR MORE, THE ENGINEER SHALL RECEIVE AN EXTRA $.50 PER HOUR TRUCK MOUNTED CONCRETE PUMPS: WHEN THE TRUCK MOUNTED CONCRETE PUMP IS EQUIPPED WITH A BOOM, WHICH IS CAPABLE OF EXTENDING 90' OR MORE, THE ENGINEER SHALL RECEIVE $.50 PER HOUR EXTRA | 56.75 | 51.05 | 107.80 |
| LABORER | 19.88 | 11.87 | 31.75 |
| PAINTER: BRUSH, ROLLER, SPRAY, SANDBLASTING, PAPERHANGER, DRYWALL FINISHING, TAPER, AND SPRAY STRUCTURAL STEEL (BOONE, JO DAVIESS, LEE, OGLE, STEPHENSON AND WINNEBAGO COUNTIES) | 45.15 | 29.41 | 74.56 |
| PLASTERER (WINNEBAGO COUNTY) | 37.90 | 37.66 | 75.56 |
| CEMENT MASON/CONCRETE FINISHER (WINNEBAGO COUNTY) | 41.03 | 36.39 | 77.42 |
| PLUMBER | 55.54 | 31.43 | 86.97 |
| ROOFER | 50.25 | 30.43 | 80.68 |
| SHEET METAL WORKER (INCLUNDING HVAC) | 39.47 | 31.55 | 71.02 |
| LABORERS: PLANTSMAN | 9.00 | — | 9.00 |
| TRUCK DRIVER: 6 AXLES (BOONE AND WINNEBAGO COUNTIES) FOOTNOTE: AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES | 48.93 | 26.70 | 75.63 |
| TRUCK DRIVER: 5 AXLES (BOONE AND WINNEBAGO COUNTIES) FOOTNOTE: AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES | 48.82 | 26.70 | 75.52 |
| TRUCK DRIVER: 4 AXLES (BOONE AND WINNEBAGO COUNTIES) FOOTNOTE: AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES | 48.62 | 26.70 | 75.32 |
| TRUCK DRIVER: 2 - 3 AXLES (BOONE AND WINNEBAGO COUNTIES) FOOTNOTE: AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES | 48.47 | 26.70 | 75.17 |