Davis-Bacon Rate Lookupfree · sourced from sam.gov · no sign-up

ID20260038 rev 2

Heavy  Published 05/18/2026. 24 classifications. Covers 1 county: Bingham

Check that the construction type above matches your contract. A county usually has several determinations and their rates differ. Verify at sam.gov.
ClassificationBase rateFringeTotal
CARPENTER: EXCLUDES FORM WORK (ADAMS, BEAR LAKE, BINGHAM, BOISE, BUTTE, BONNEVILLE, CAMAS, CARIBOU, CASSIA, CLARK, CUSTER, ELMORE, FRANKLIN, FREMONT, GEM, GOODING, IDAHO (SOUTH OF THE 46TH PARALLEL), JEFFERSON, JEROME, LEMHI, LINCOLN, MADISON, MINIDOKA, ONEIDA, OWYHEE, PAYETTE, POWER, TETON, TWIN FALLS, VALLEY AND WASHINGTON COUNTIES) ZONE PAY: ZONE 1 0-30 MILES: FREE ZONE 2 MORE THAN 30-60 MILES: $2.00/PER HOUR ZONE 3 MORE THAN 60 MILES: $3.00/PER HOUR IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE35.6818.2453.92
ELECTRICIAN40.0018.7458.74
POWER EQUIPMENT OPERATOR: GROUP 7 CRANE (OVER 50 TONS), TOWER CRANE ZONE PAY: ZONE CENTERS BOISE, TWIN FALLS, POCATELLO, AND IDAHO FALLS ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES $30.00/PER DAY ZONE 3 MORE THAN 60 MILES $35.00/PER DAY. CRANE LONG BOOM PAY: A. CRANE BOOMS, 100FT TO 150FT, FIFTEEN CENTS OVER SCALE B CRANE BOOMS, 150 FT TO 200 FT, THIRTY CENTS OVER SCALE C. CRANE BOOMS, OVER 200 FT., FORTY-FIVE CENTS OVER SCALE37.3516.1053.45
POWER EQUIPMENT OPERATOR: GROUP 6 CRANE (UP TO AND INCLUDING 50 TON) ZONE PAY: ZONE CENTERS BOISE, TWIN FALLS, POCATELLO, AND IDAHO FALLS ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES $30.00/PER DAY ZONE 3 MORE THAN 60 MILES $35.00/PER DAY. CRANE LONG BOOM PAY: A. CRANE BOOMS, 100FT TO 150FT, FIFTEEN CENTS OVER SCALE B CRANE BOOMS, 150 FT TO 200 FT, THIRTY CENTS OVER SCALE C. CRANE BOOMS, OVER 200 FT., FORTY-FIVE CENTS OVER SCALE36.9816.1053.08
POWER EQUIPMENT OPERATOR: GROUP 3 FORKLIFT ZONE PAY: ZONE CENTERS: BOISE, TWIN FALLS, POCATELLO, AND IDAHO FALLS ZONE 1 0 - 30 MILES FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY36.3316.1052.43
IRONWORKER, STRUCTURAL33.3722.9856.35
LABORER: GROUP 3 ASPHALT INCLUDING RAKER, SHOVELER, SPREADER, AND DISTRIBUTOR33.8316.5050.33
LABORER: GROUP 1 FLAGGER33.6316.5050.13
WATER & SEWER LINES: OPERATOR - EXCAVATOR22.07—22.07
TRUCK DRIVER: WATER TRUCK24.5711.2235.79
TRUCK DRIVER: LOWBOY TRUCK21.0012.1033.10
TRUCK DRIVER: DUMP TRUCK17.53—17.53
OPERATOR: CONCRETE BATCH PLANT24.9411.9636.90
OPERATOR: LOADER (FRONT END)21.336.1127.44
OPERATOR: GRADER/BLADE24.918.7933.70
OPERATOR: FORKLIFT17.00—17.00
OPERATOR: CRANE24.308.3832.68
OPERATOR: BOBCAT/SKID STEER/SKID LOADER21.05—21.05
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE20.795.8026.59
LABORER: PIPELAYER18.233.7722.00
LABORER: COMMON OR GENERAL20.4310.9031.33
IRONWORKER, REINFORCING27.2216.7043.92
CEMENT MASON/CONCRETE FINISHER18.02—18.02
CARPENTER (FORM WORK ONLY)25.279.1034.37
Filing the WH-347 that these rates feed into? I build certified payroll tools, and I will prepare your first weekly filing from your payroll register free, with worker names removed — partly to be useful, partly because real registers are the only way to test the thing properly. hamza.aiemployee@gmail.com. No sign-up on this site, and nothing here is tracked.