Residential Published 05/18/2026. 38 classifications. Covers 1 county: Lee
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| OPERATOR: CRANE (CRANES 76 TON TO 129 TON) | 37.57 | 14.90 | 52.47 |
| OPERATOR: CRANE (CRANES 130-300 TON) | 39.38 | 14.90 | 54.28 |
| OPERATOR: CRANE (ALL CRANES OVER 300 TON, ELECTRIC TOWER, LUFFING BOOM CRANES) | 40.40 | 14.90 | 55.30 |
| OPERATOR: CRANE (ALL CRANES 75 TONS AND BELOW) | 37.07 | 14.90 | 51.97 |
| OPERATOR: OILER | 27.53 | 14.90 | 42.43 |
| IRONWORKER: REINFORCING AND STRUCTURAL | 35.25 | 17.32 | 52.57 |
| TRUCK DRIVER: LOWBOY TRUCK | 12.10 | — | 12.10 |
| TRUCK DRIVER, INCLUDES DUMP TRUCK | 10.22 | — | 10.22 |
| SHEET METAL WORKER, EXCLUDES METAL ROOF INSTALLATION | 9.85 | 0.38 | 10.23 |
| ROOFER: METAL ROOF | 16.99 | — | 16.99 |
| ROOFER, INCLUDES BUILT UP, MODIFIED BITUMEN, AND SHAKE & SHINGLE ROOFS (EXCLUDES METAL ROOFS) | 15.65 | — | 15.65 |
| PLUMBER | 14.25 | — | 14.25 |
| PLASTERER | 15.00 | — | 15.00 |
| PAINTER: INCLUDES BRUSH, ROLLER AND SPRAY | 12.40 | — | 12.40 |
| OPERATOR: TRACTOR | 10.20 | — | 10.20 |
| OPERATOR: TRACKHOE | 14.81 | — | 14.81 |
| OPERATOR: SCREED | 10.93 | — | 10.93 |
| OPERATOR: ROLLER | 10.62 | — | 10.62 |
| OPERATOR: LOADER | 12.17 | — | 12.17 |
| OPERATOR: GRADER/BLADE | 14.00 | — | 14.00 |
| OPERATOR: FORKLIFT | 17.50 | — | 17.50 |
| OPERATOR: DISTRIBUTOR | 11.41 | — | 11.41 |
| OPERATOR: BULLDOZER | 14.50 | 2.00 | 16.50 |
| OPERATOR: BACKHOE/EXCAVATOR | 15.25 | — | 15.25 |
| OPERATOR: BACKHOE LOADER COMBO | 17.04 | — | 17.04 |
| OPERATOR: ASPHALT PAVER | 12.00 | — | 12.00 |
| LABORER: LANDSCAPE AND IRRIGATION | 13.54 | — | 13.54 |
| LABORER: ROOF TEAROFF | 9.00 | — | 9.00 |
| LABORER: PIPELAYER | 15.14 | — | 15.14 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | 10.42 | — | 10.42 |
| LABORER: MASON TENDER - BRICK | 11.51 | — | 11.51 |
| LABORER: COMMON OR GENERAL | 9.53 | — | 9.53 |
| IRONWORKER, ORNAMENTAL | 15.25 | — | 15.25 |
| ELECTRICIAN | 14.75 | — | 14.75 |
| DRYWALL HANGER | 12.33 | — | 12.33 |
| CEMENT MASON/CONCRETE FINISHER | 15.90 | — | 15.90 |
| CARPENTER, INCLUDES CABINET INSTALLATION (EXCLUDES DRYWALL HANGING) | 14.09 | — | 14.09 |
| BRICKLAYER | 20.00 | — | 20.00 |