Residential Published 05/18/2026. 176 classifications. Covers 8 counties: Imperial, Los Angeles, Orange, Riverside, San Bernardino, San Luis Obispo, Santa Barbara, Ventura
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKERS/INSULATOR (INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS, AND FINISHES TO ALL TYPES OF MECHANICAL SYSTEMS) | 56.32 | 26.52 | 82.84 |
| FIRE STOP TECHNICIAN (APPLICATION OF FIRESTOPPING MATERIALS FOR WALL OPENINGS AND PENETRATIONS IN WALLS, FLOORS, CEILINGS AND CURTAIN WALLS) | 39.94 | 20.65 | 60.59 |
| ASBESTOS REMOVAL WORKER/HAZARDOUS MATERIAL HANDLER (INCLUDES PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPPING, VACUUMING, BAGGING AND DISPOSING OF ALL INSULATION MATERIALS FROM MECHANICAL SYSTEMS, WHETHER THEY CONTAIN ASBESTOS OR NOT) | 23.52 | 13.37 | 36.89 |
| BRICKLAYER; MARBLE SETTER (VENTURA COUNTY) *THE WAGE SCALE FOR PREVAILING WAGE PROJECTS PERFORMED IN BLYTHE, CHINA LAKE, DEATH VALLEY, FORT IRWIN, TWENTY-NINE PALMS, NEEDLES AND 1-15 CORRIDOR (BARSTOW TO THE NEVADA STATE LINE) WILL BE THREE DOLLARS ($3.00) ABOVE THE STANDARD SAN BERNARDINO/RIVERSIDE COUNTY HOURLY WAGE RATE | 50.07 | 20.29 | 70.36 |
| BRICKLAYER; MARBLE SETTER (RIVERSIDE & SAN BERNARDINO COUNTIES) *THE WAGE SCALE FOR PREVAILING WAGE PROJECTS PERFORMED IN BLYTHE, CHINA LAKE, DEATH VALLEY, FORT IRWIN, TWENTY-NINE PALMS, NEEDLES AND 1-15 CORRIDOR (BARSTOW TO THE NEVADA STATE LINE) WILL BE THREE DOLLARS ($3.00) ABOVE THE STANDARD SAN BERNARDINO/RIVERSIDE COUNTY HOURLY WAGE RATE | 50.07 | 20.29 | 70.36 |
| TWENTY-NINE PALMS, NEEDLES AND 1-15 CORRIDOR (BARSTOW TO THE NEVADA STATE LINE) WILL BE THREE DOLLARS ($3.00) ABOVE THE STANDARD SAN BERNARDINO/RIVERSIDE COUNTY HOURLY WAGE RATE | 50.07 | 20.29 | 70.36 |
| BRICKLAYER; MARBLE SETTER (LOS ANGELES COUNTY) *THE WAGE SCALE FOR PREVAILING WAGE PROJECTS PERFORMED IN BLYTHE, CHINA LAKE, DEATH VALLEY, FORT IRWIN, TWENTY-NINE PALMS, NEEDLES AND 1-15 CORRIDOR (BARSTOW TO THE NEVADA STATE LINE) WILL BE THREE DOLLARS ($3.00) ABOVE THE STANDARD SAN BERNARDINO/RIVERSIDE COUNTY HOURLY WAGE RATE | 50.07 | 20.29 | 70.36 |
| BRICKLAYER; MARBLE SETTER (IMPERIAL) | 58.81 | 19.14 | 77.95 |
| BRICKLAYER; MARBLE SETTER (SAN LUIS OBISPO AND SANTA BARBARA COUNTIES) *THE WAGE SCALE FOR PREVAILING WAGE PROJECTS PERFORMED IN BLYTHE, CHINA LAKE, DEATH VALLEY, FORT IRWIN, TWENTY-NINE PALMS, NEEDLES AND 1-15 CORRIDOR (BARSTOW TO THE NEVADA STATE LINE) WILL BE THREE DOLLARS ($3.00) ABOVE THE STANDARD SAN BERNARDINO/RIVERSIDE COUNTY HOURLY WAGE RATE | 50.07 | 20.29 | 70.36 |
| TILE FINISHER | 37.96 | 13.77 | 51.73 |
| MARBLE FINISHER | 43.38 | 15.36 | 58.74 |
| TILE LAYER (SAN LUIS OBISPO AND SANTA BARBARA) | 51.82 | 19.32 | 71.14 |
| TILE LAYER (IMPERIAL, LOS ANGELES, ORANGE, RIVERSIDE, SAN BERNARDINO & VENTURA) | 51.82 | 19.32 | 71.14 |
| TERRAZZO WORKER/SETTER | 49.62 | 15.26 | 64.88 |
| TERRAZZO FINISHER | 42.11 | 14.67 | 56.78 |
| CARPENTER: INSULATION INSTALLER (WORK ON WOOD FRAME SINGLE FAMILY HOMES AND APARTMENTS UP TO AND INCLUDING 4 STORIES) | 25.66 | 15.96 | 41.62 |
| CARPENTER: CABINET INSTALLER (WORK ON WOOD FRAME SINGLE FAMILY HOMES AND APARTMENTS UP TO AND INCLUDING 4 STORIES) | 40.46 | 16.28 | 56.74 |
| CARPENTER: FENCE BUILDER (WORK ON WOOD FRAME SINGLE FAMILY HOMES AND APARTMENTS UP TO AND INCLUDING 4 STORIES) | 39.91 | 15.37 | 55.28 |
| CARPENTER: FRAMER & FINISH CARPENTER (WORK ON WOOD FRAME SINGLE FAMILY HOMES AND APARTMENTS UP TO AND INCLUDING 4 STORIES) | 40.75 | 16.28 | 57.03 |
| CARPENTER: ROOF LOADER OF SHINGLES (WORK ON WOOD FRAME SINGLE FAMILY HOMES AND APARTMENTS UP TO AND INCLUDING 4 STORIES) | 30.08 | 16.28 | 46.36 |
| CARPENTER: SHINGLER (WORK ON WOOD FRAME SINGLE FAMILY HOMES AND APARTMENTS UP TO AND INCLUDING 4 STORIES) | 39.90 | 16.28 | 56.18 |
| CARPENTER: SUBTERRANEAN GARAGE CONCRETE CONSTRUCTION AND CARPENTERS PERFORMING ON GRADE SLAB CONCRETE CONSTRUCTION (WORK ON WOOD FRAME SINGLE FAMILY HOMES AND APARTMENTS UP TO AND INCLUDING 4 STORIES) | 39.38 | 16.28 | 55.66 |
| DRYWALL: STOCKER/SCRAPPER: (2) ALL OTHER WORK | 22.16 | 8.62 | 30.78 |
| DRYWALL: STOCKER/SCRAPPER: (1) WORK ON WOOD-FRAMED SINGLE FAMILY HOMES, AND WOOD-FRAMED APARTMENT BUILDINGS UP TO AND INCLUDING 4 STORIES | 22.16 | 8.62 | 30.78 |
| DRYWALL: DRYWALL INSTALLER/LATHER: (2) ALL OTHER WORK | 51.60 | 16.28 | 67.88 |
| DRYWALL: DRYWALL INSTALLER/LATHER: (1) WORK ON WOOD-FRAMED SINGLE FAMILY HOMES, AND WOOD-FRAMED APARTMENT BUILDINGS UP TO AND INCLUDING 4 STORIES | 32.14 | 16.28 | 48.42 |
| MODULAR FURNITURE INSTALLER | 25.00 | 13.06 | 38.06 |
| ELECTRICIAN: DOES NOT INCLUDE FIRE ALARM, HOLD-UP ALARM, BURGLAR ALARM AND SURVEILLANCE SYSTEMS LOS ANGELES | 37.63 | 8.41 | 46.04 |
| COMMUNICATIONS SYSTEM: INSTALLER COMMUNICATIONS AND SYSTEMS WORK (LOS ANGELES COUNTY) SCOPE OF WORK: INSTALLATION, TESTING, SERVICE AND MAINTENANCE OF SYSTEMS UTILIZING THE TRANSMISSION AND/OR TRANSFERENCE OF VOICE, SOUND, VISION AND DIGITAL FOR COMMERCIAL, EDUCATIONAL, SECURITY AND ENTERTAINMENT PURPOSES FOR THE FOLLOWING: TV MONITORING AND SURVEILLANCE, BACKGROUND - FOREGROUND MUSIC, INTERCOM AND TELEPHONE INTERCONNECT, MICROWAVE TRANSMISSION, MULTI-MEDIA, MULTIPLEX, NURSE CALL SYSTEMS, RADIO PAGE, BURGLAR ALARMS AND FIRE ALARMS. COMMUNICATION SYSTEMS THAT TRANSMIT OR RECEIVE INFORMATION AND/OR CONTROL SYSTEMS THAT ARE INTRINSIC TO THE ABOVE LISTED SYSTEMS; INCLUSION OR EXCLUSION OF TERMINATIONS AND TESTINGS OF CONDUCTORS DETERMINED BY THEIR FUNCTION; EXCLUDING ALL OTHER DATA SYSTEMS OR MULTIPLE SYSTEMS WHICH INCLUDE CONTROL FUNCTION OR POWER SUPPLY; EXCLUDING INSTALLATION OF RACEWAY SYSTEMS, CONDUIT SYSTEMS, LINE VOLTAGE WORK, AND ENERGY MANAGEMENT SYSTEMS | 46.47 | 18.47 | 64.94 |
| ELECTRICIANS (SANTA BARBARA COUNTY) WORK AT VANDENBERG AFB: $3.75 ADDITIONAL PER HOUR | 41.00 | 4.73 | 45.73 |
| OF WORK: INSTALLATION, TESTING, SERVICE AND MAINTENANCE OF SYSTEMS UTILIZING THE TRANSMISSION AND/OR TRANSFERENCE OF VOICE, SOUND, VISION AND DIGITAL FOR COMMERCIAL, EDUCATIONAL, SECURITY AND ENTERTAINMENT PURPOSES FOR THE FOLLOWING: TV MONITORING AND SURVEILLANCE, BACKGROUND - FOREGROUND MUSIC, INTERCOM AND TELEPHONE INTERCONNECT, MICROWAVE TRANSMISSION, MULTI-MEDIA, MULTIPLEX, NURSE CALL SYSTEMS, RADIO PAGE, BURGLAR ALARMS AND FIRE ALARM (SEE LAST PARAGRAPH BELOW) COMMUNICATION SYSTEMS THAT TRANSMIT OR RECEIVE INFORMATION AND/OR CONTROL SYSTEMS THAT ARE INTRINSIC TO THE ABOVE LISTED SYSTEMS; INCLUSION OR EXCLUSION OF TERMINATIONS AND TESTINGS OF CONDUCTORS DETERMINED BY THEIR FUNCTION; EXCLUDING ALL OTHER DATA SYSTEMS OR MULTIPLE SYSTEMS WHICH INCLUDE CONTROL FUNCTION OR POWER SUPPLY; EXCLUDING INSTALLATION OF RACEWAY SYSTEMS, CONDUIT SYSTEMS, LINE VOLTAGE WORK, AND ENERGY MANAGEMENT SYSTEMS FIRE ALARM WORK SHALL BE PERFORMED AT THE CURRENT INSIDE ELECTRICIAN TOTAL COST PACKAGE | 48.13 | 17.49 | 65.62 |
| ELECTRICIAN (RIVERSIDE) | 57.26 | 32.83 | 90.09 |
| COMMUNICATIONS SYSTEM: INSTALLER COMMUNICATIONS AND SYSTEMS WORK (RIVERSIDE AND SAN BERNARDINO COUNTIES) SCOPE OF WORK: INSTALLATION, TESTING, SERVICE AND MAINTENANCE OF SYSTEMS UTILIZING THE TRANSMISSION AND/OR TRANSFERENCE OF VOICE, SOUND, VISION AND DIGITAL FOR COMMERCIAL, EDUCATIONAL, SECURITY AND ENTERTAINMENT PURPOSES FOR THE FOLLOWING: TV MONITORING AND SURVEILLANCE, BACKGROUND - FOREGROUND MUSIC, INTERCOM AND TELEPHONE INTERCONNECT, MICROWAVE TRANSMISSION, MULTI-MEDIA, MULTIPLEX, NURSE CALL SYSTEMS, RADIO PAGE, BURGLAR ALARMS AND FIRE ALARMS COMMUNICATION SYSTEMS THAT TRANSMIT OR RECEIVE INFORMATION AND/OR CONTROL SYSTEMS THAT ARE INTRINSIC TO THE ABOVE LISTED SYSTEMS; INCLUSION OR EXCLUSION OF TERMINATIONS AND TESTINGS OF CONDUCTORS DETERMINED BY THEIR FUNCTION; EXCLUDING ALL OTHER DATA SYSTEMS OR MULTIPLE SYSTEMS WHICH INCLUDE CONTROL FUNCTION OR POWER SUPPLY; EXCLUDING INSTALLATION OF RACEWAY SYSTEMS, CONDUIT SYSTEMS, LINE VOLTAGE WORK, AND ENERGY MANAGEMENT SYSTEMS | 45.23 | 20.47 | 65.70 |
| COMMUNCIATION SYSTEM: TECHNICIAN COMMUNICATIONS AND SYSTEMS WORK (RIVERSIDE AND SAN BERNARDINO COUNTIES) SCOPE OF WORK: INSTALLATION, TESTING, SERVICE AND MAINTENANCE OF SYSTEMS UTILIZING THE TRANSMISSION AND/OR TRANSFERENCE OF VOICE, SOUND, VISION AND DIGITAL FOR COMMERCIAL, EDUCATIONAL, SECURITY AND ENTERTAINMENT PURPOSES FOR THE FOLLOWING: TV MONITORING AND SURVEILLANCE, BACKGROUND - FOREGROUND MUSIC, INTERCOM AND TELEPHONE INTERCONNECT, MICROWAVE TRANSMISSION, MULTI-MEDIA, MULTIPLEX, NURSE CALL SYSTEMS, RADIO PAGE, BURGLAR ALARMS AND FIRE ALARMS COMMUNICATION SYSTEMS THAT TRANSMIT OR RECEIVE INFORMATION AND/OR CONTROL SYSTEMS THAT ARE INTRINSIC TO THE ABOVE LISTED SYSTEMS; INCLUSION OR EXCLUSION OF TERMINATIONS AND TESTINGS OF CONDUCTORS DETERMINED BY THEIR FUNCTION; EXCLUDING ALL OTHER DATA SYSTEMS OR MULTIPLE SYSTEMS WHICH INCLUDE CONTROL FUNCTION OR POWER SUPPLY; EXCLUDING INSTALLATION OF RACEWAY SYSTEMS, CONDUIT SYSTEMS, LINE VOLTAGE WORK, AND ENERGY MANAGEMENT SYSTEMS | 33.09 | 15.89 | 48.98 |
| ELECTRICIAN (ORANGE) | 36.66 | 11.26 | 47.92 |
| ELECTRICIAN (SAN BERNARDINO) | 37.63 | 9.57 | 47.20 |
| ELECTRICIAN: 1 TO 3 STORIES (IMPERIAL) | 40.50 | 8.18 | 48.68 |
| ELECTRICIAN (SAN LUIS OBISPO) | 55.50 | 24.42 | 79.92 |
| service and maintenance of systems utilizing the transmission and/or transference of voice, sound, vision and digital for commercial, educational, security and entertainment purposes for the following: TV monitoring and surveillance, background - foreground music, intercom and telephone interconnect, microwave transmission, multi-media, multiplex, nurse call systems, radio page, burglar alarms and fire alarm (see last paragraph below). Communication Systems that transmit or receive information and/or control systems that are intrinsic to the above listed systems; inclusion or exclusion of terminations and testings of conductors determined by their function; excluding all other data systems or multiple systems which include control function or power supply; excluding installation of raceway systems, conduit systems, line voltage work, and energy management systems. Fire alarm work shall be performed at the current inside electrician total cost package | 49.73 | 17.54 | 67.27 |
| service and maintenance of systems utilizing the transmission and/or transference of voice, sound, vision and digital for commercial, educational, security and entertainment purposes for the following: TV monitoring and surveillance, background - foreground music, intercom and telephone interconnect, microwave transmission, multi-media, multiplex, nurse call systems, radio page, burglar alarms and fire alarm (see last paragraph below). Communication Systems that transmit or receive information and/or control systems that are intrinsic to the above listed systems; inclusion or exclusion of terminations and testings of conductors determined by their function; excluding all other data systems or multiple systems which include control function or power supply; excluding installation of raceway systems, conduit systems, line voltage work, and energy management systems. Fire alarm work shall be performed at the current inside electrician total cost package | 30.89 | 11.66 | 42.55 |
| OAK VIEW, OXNARD, SANTA PAULA AND VENTURA | 53.09 | 31.56 | 84.65 |
| CABLE SPLICER ALL WORK WITHIN 32 ROAD MILES OR LESS FROM THE NEAREST BASE POINT (VENTURA) ALL WORK MORE THAN 32 ROAD MILES FROM NEAREST BASE POINT: ADD $5.00 TO THE BASIC HOURLY RATE. BASE POINTS: THE MAIN POST OFFICE IN THE CITIES OF CAMARILLO, OAK VIEW, OXNARD, SANTA PAULA AND VENTURA | 58.40 | 31.72 | 90.12 |
| OF WORK: INSTALLATION, TESTING, SERVICE AND MAINTENANCE OF SYSTEMS UTILIZING THE TRANSMISSION AND/OR TRANSFERENCE OF VOICE, SOUND, VISION AND DIGITAL FOR COMMERCIAL, EDUCATIONAL, SECURITY AND ENTERTAINMENT PURPOSES FOR THE FOLLOWING: TV MONITORING AND SURVEILLANCE, BACKGROUND - FOREGROUND MUSIC, INTERCOM AND TELEPHONE INTERCONNECT, MICROWAVE TRANSMISSION, MULTI-MEDIA, MULTIPLEX, NURSE CALL SYSTEMS, RADIO PAGE, BURGLAR ALARMS AND FIRE ALARM (SEE LAST PARAGRAPH BELOW) COMMUNICATION SYSTEMS THAT TRANSMIT OR RECEIVE INFORMATION AND/OR CONTROL SYSTEMS THAT ARE INTRINSIC TO THE ABOVE LISTED SYSTEMS; INCLUSION OR EXCLUSION OF TERMINATIONS AND TESTINGS OF CONDUCTORS DETERMINED BY THEIR FUNCTION; EXCLUDING ALL OTHER DATA SYSTEMS OR MULTIPLE SYSTEMS WHICH INCLUDE CONTROL FUNCTION OR POWER SUPPLY; EXCLUDING INSTALLATION OF RACEWAY SYSTEMS, CONDUIT SYSTEMS, LINE VOLTAGE WORK, AND ENERGY MANAGEMENT SYSTEMS FIRE ALARM WORK SHALL BE PERFORMED AT THE CURRENT INSIDE ELECTRICIAN TOTAL COST PACKAGE | 46.47 | 19.22 | 65.69 |
| ELEVATOR MECHANIC (SAN LUIS OBISPO) FOOTNOTE A. PAID VACATION: EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YEARS OF SERVICE, AND 6% FOR 6 MONTHS TO 5 YEARS OF SERVICE. B. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY, FRIDAY AFTER THANKSGIVING, AND CHRISTMAS DAY | 84.05 | 38.44 | 122.49 |
| ELEVATOR MECHANIC IMPERIAL, LOS ANGELES, ORANGE, RIVERSIDE, SAN BERNARDINO, SANTA BARBARA AND VENTURA FOOTNOTE: PAID VACATION: EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YEARS OF SERVICE, AND 6% FOR 6 MONTHS TO 5 YEARS OF SERVICE PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY, FRIDAY AFTER THANKSGIVING, AND CHRISTMAS DAY | 69.43 | 38.44 | 107.87 |
| OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 13: CRANE OPERATOR (OVER 300 TONS); DERRICK BARGE OPERATOR (OVER 300 TONS); HELICOPTER PILOT; HOIST OPERATOR, STIFF LEGS, GUY DERRICK OR SIMILAR TYPE (OVER 300 TONS); MOBILE TOWER CRANE OPERATOR (OVER 300 TONS) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 52.65 | 25.25 | 77.90 |
| OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 12: CRANE OPERATOR (OVER 200 TONS UP TO AND INCLUDING 300 TONS MRC); DERRICK BARGE OPERATOR (OVER 200 TONS UP TO AND INCLUDING 300 TONS MRC); HOIST OPERATOR, STIFF LEGS, GUY DERRICK OR SIMILAR TYPE (OVER 200 TONS, UP TO AND INCLUDING 300 TONS MRC); MOBILE TOWER CRANE OPERATOR (OVER 200 TONS, UP TO AND INCLUDING 300 TONS MRC) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 51.65 | 25.25 | 76.90 |
| OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 11: CRANE OPERATOR (OVER 100 TONS AND UP TO AND INCLUDING 200 TONS MRC); DERRICK BARGE OPERATOR (OVER 100 TONS UP TO AND INCLUDING 200 TONS MRC); HOIST OPERATOR, STIFF LEGS, GUY DERRICK OR SIMILAR TYPE (OVER 100 TONS UP TO AND INCLUDING 200 TONS MRC); MOBILE TOWER CRANE OPERATOR (OVER 100 TONS UP TO AND INCLUDING 200 TONS MRC) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 50.65 | 25.25 | 75.90 |
| OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 10: CRANE OPERATOR (OVER 50 TONS AND UP TO AND INCLUDING 100 TONS MRC); DERRICK BARGE OPERATOR (OVER 50 TONS UP TO AND INCLUDING 100 TONS MRC); HOIST OPERATOR, STIFF LEGS, GUY DERRICK OR SIMILAR TYPE (OVER 50 TONS UP TO AND INCLUDING 100 TONS MRC), MOBILE TOWER CRANE OPERATOR (OVER 50 TONS, UP TO AND INCLUDING 100 TONS M.R.C.); TOWER CRANE OPERATOR AND TOWER GANTRY PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 49.65 | 25.25 | 74.90 |
| OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 9: CRANE OPERATOR (OVER 25 TONS AND UP TO AND INCLUDING 50 TONS MRC); DERRICK BARGE OPERATOR (OVER 25 TONS UP TO AND INCLUDING 50 TONS MRC); HIGHLINE CABLEWAY OPERATOR; HOIST OPERATOR, STIFF LEGS, GUY DERRICK OR SIMILAR TYPE (OVER 25 TONS UP TO AND INCLUDING 50 TONS MRC); K-CRANE OPERATOR; POLAR CRANE OPERATOR; SELF ERECTING TOWER CRANE OPERATOR MAXIMUM LIFTING CAPACITY TEN TONS PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 48.65 | 25.25 | 73.90 |
| OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 8: CRANE OPERATOR (UP TO AND INCLUDING 25 TON CAPACITY); CRAWLER TRANSPORTER OPERATOR; DERRICK BARGE OPERATOR (UP TO AND INCLUDING 25 TON CAPACITY); HOIST OPERATOR, STIFF LEGS, GUY DERRICK OR SIMILAR TYPE (UP TO AND INCLUDING 25 TON CAPACITY); SHOVEL, BACKHOE, DRAGLINE, CLAMSHELL OPERATOR (OVER 7 CU. YDS., M.R.C.) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 48.48 | 25.25 | 73.73 |
| OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 7: PEDESTAL CRANE OPERATOR; SHOVEL, BACKHOE, DRAGLINE, CLAMSHELL OPERATOR (OVER 5 CU. YDS. MRC); TOWER CRANE REPAIR; TUGGER HOIST OPERATOR (3 DRUM) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 48.31 | 25.25 | 73.56 |
| OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 6: BRIDGE CRANE OPERATOR; CRETOR CRANE OPERATOR; HOIST OPERATOR (CHICAGO BOOM AND SIMILAR TYPE); LIFT MOBILE OPERATOR; LIFT SLAB MACHINE OPERATOR (VAGTBORG AND SIMILAR TYPES); MATERIAL HOIST AND/OR MANLIFT OPERATOR; POLAR GANTRY CRANE OPERATOR; SELF CLIMBING SCAFFOLD (OR SIMILAR TYPE); SHOVEL, BACKHOE, DRAGLINE, CLAMSHELL OPERATOR (OVER 3/4 YD. AND UP TO 5 CU. YDS. MRC); TUGGER HOIST OPERATOR PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 48.19 | 25.25 | 73.44 |
| OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 5: HYDRAULIC BOOM TRUCK; STINGER CRANE (AUSTIN-WESTERN OR SIMILAR TYPE); TUGGER HOIST OPERATOR (1 DRUM) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 48.08 | 25.25 | 73.33 |
| OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 4: BRIDGE-TYPE UNLOADER AND TURNTABLE OPERATOR; HELICOPTER HOIST OPERATOR PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 47.86 | 25.25 | 73.11 |
| OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 3: A-FRAME OR WINCH TRUCK OPERATOR; ROSS CARRIER OPERATOR (JOBSITE) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 47.72 | 25.25 | 72.97 |
| OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 2: TRUCK CRANE OILER PREMIUM PAY $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 47.43 | 25.25 | 72.68 |
| OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 1: ENGINEER OILER; FORK LIFT OPERATOR (INCLUDES LOED, LULL OR SIMILAR TYPES) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 46.65 | 25.25 | 71.90 |
| OPERATOR: POWER EQUIPMENT GROUP 9: HEAVY DUTY REPAIRMAN PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 49.29 | 25.25 | 74.54 |
| D-5 - 100 FLYWHEEL H.P. AND OVER, OR SIMILAR-BULLDOZER, TAMPER, SCRAPER AND PUSH TRACTOR SINGLE ENGINE); TRACTOR OPERATOR (BOOM ATTACHMENTS), TRAVELING PIPE WRAPPING, CLEANING AND BENDNG MACHINE OPERATOR; TRENCHING MACHINE OPERATOR (OVER 6 FT. DEPTH CAPACITY, MANUFACTURER'S RATING); TRENCHING MACHINE WITH ROAD MINER ATTACHMENT (OVER 6 FT DEPTH CAPACITY): ULTRA HIGH PRESSURE WATERJET CUTTING TOOL SYSTEM MECHANIC; WATER PULL (COMPACTION) OPERATOR PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 48.19 | 25.25 | 73.44 |
| OPERATOR: POWER EQUIPMENT GROUP 7: WELDER - GENERAL PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 49.18 | 25.25 | 74.43 |
| TAR PIPELINING MACHINE OPERATOR; SKIPLOADER OPERATOR (CRAWLER AND WHEEL TYPE, OVER 3/4 YD. AND UP TO AND INCLUDING 1-1/2 YDS.); SLIP FORM PUMP OPERATOR (POWER DRIVEN HYDRAULIC LIFTING DEVICE FOR CONCRETE FORMS); TRACTOR OPERATOR-BULLDOZER, TAMPER-SCRAPER (SINGLE ENGINE, UP TO 100 H.P FLYWHEEL AND SIMILAR TYPES, UP TO AND INCLUDING D-5 AND SIMILAR TYPES); TUGGER HOIST OPERATOR (1 DRUM); ULTRA HIGH PRESSURE WATERJET CUTTING TOOL SYSTEM OPERATOR; VACUUM BLASTING MACHINE OPERATOR PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 48.08 | 25.25 | 73.33 |
| OPERATOR: POWER EQUIPMENT GROUP 5: EQUIPMENT GREASER (GREASE TRUCK/MULTI SHIFT). PREMIUM PAY $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 48.96 | 25.25 | 74.21 |
| MAXIMUM); EQUIPMENT GREASER (GREASE TRUCK); GUARD RAIL POST DRIVER OPERATOR; HIGHLINE CABLEWAY SIGNALMAN; HYDRA-HAMMER-AERO STOMPER; MICRO TUNNELING (ABOVE GROUND TUNNEL); POWER CONCRETE CURING MACHINE OPERATOR; POWER CONCRETE SAW OPERATOR; POWER-DRIVEN JUMBO FORM SETTER OPERATOR; POWER SWEEPER OPERATOR; ROCK WHEEL SAW/TRENCHER; ROLLER OPERATOR (COMPACTING); SCREED OPERATOR (ASPHALT OR CONCRETE); TRENCHING MACHINE OPERATOR (UP TO 6 FT.); VACUUM OR MUCH TRUCK PREMIUM PAY $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 47.86 | 25.25 | 73.11 |
| OPERATOR: POWER EQUIPMENT GROUP 3: ASPHALT-RUBBER BLEND OPERATOR; BOBCAT OR SIMILAR TYPE (SIDE STEER); EQUIPMENT GREASER (RACK); FORD FERGUSON (WITH DRAGTYPE ATTACHMENTS); HELICOPTER RADIOMAN (GROUND); STATIONARY PIPE WRAPPING AND CLEANING MACHINE OPERATOR PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 46.37 | 25.25 | 71.62 |
| PLANT OPERATOR (NURSE TANK OPERATOR); CONCRETE MIXER OPERATOR-SKIP TYPE; CONVEYOR OPERATOR; FIREMAN; FORKLIFT OPERATOR (INCLUDES LOED, LULL OR SIMILAR TYPES OVER 5 TONS; HYDROSTATIC PUMP OPERATOR; OILER CRUSHER (ASPHALT OR CONCRETE PLANT); PETROMAT LAYDOWN MACHINE; PJU SIDE DUM JACK; SCREENING AND CONVEYOR MACHINE OEPRATOR (OR SIMILAR TYPES); SKIPLOADER (WHEEL TYPE UP TO 3/4 YD. WITHOUT ATTACHMENT); TAR POT FIREMAN; TEMPORARY HEATING PLANT OPERATOR; TRENCHING MACHINE OILER PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 46.08 | 25.25 | 71.33 |
| OPERATOR: POWER EQUIPMENT GROUP 25: CONCRETE PUMP OPERATOR-TRUCK MOUNTED; RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH THE TANDEM PUSH-PULL SYSTEM (MULTIPLE ENGINE, EUCLID, CATERPILLAR AND SIMILAR TYPE, OVER 50 CU. YDS STRUCK) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 49.98 | 25.25 | 75.23 |
| OPERATOR: POWER EQUIPMENT GROUP 24: RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH THE TANDEM PUSH-PULL SYSTEM (SINGLE ENGINE, OVER 50 YDS. STRUCK); RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH THE TANDEM PUSH-PULL SYSTEM (MULTIPLE ENGINE, EUCLID, CATERPILLAR AND SIMILAR, OVER 25 YDS. AND UP TO 50 YDS. STRUCK) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 49.81 | 25.25 | 75.06 |
| OPERATOR: POWER EQUIPMENT GROUP 23: RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH THE TANDEM PUSH-PULL SYSTEM (SINGLE ENGINE, CATERPILLAR, EUCLID, ATHEY WAGON AND SIMILAR TYPES WITH ANY AND ALL ATTACHMENTS OVER 25 YDS. AND UP TO AND INCLUDING 50 YDS. STRUCK); RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING WITH THE TANDEM PUSH-PULL SYSTEM (MULTIPLE ENGINE, UP TO AND INCLUDING 25 YDS STRUCK) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 49.69 | 25.25 | 74.94 |
| OPERATOR: POWER EQUIPMENT GROUP 22: RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH THE TANDEM PUSH-PULL SYSTEM (SINGLE ENGINE, UP TO AND INCLUDING 25 YDS. STRUCK) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 49.58 | 25.25 | 74.83 |
| OPERATOR: POWER EQUIPMENT GROUP 21: RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING IN TANDEM (SCRAPERS, BELLY DUMPS AND SIMILAR TYPES IN ANY COMBINATION, EXCLUDING COMPACTION UNITS - MULTIPLE ENGINE, EUCLID, CATERPILLAR AND SIMILAR TYPE, OVER 50 CU. YDS. STRUCK) PREMIUM PAY $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 49.48 | 25.25 | 74.73 |
| OPERATOR: POWER EQUIPMENT GROUP 20: RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING IN TANDEM (SCRAPERS, BELLY DUMPS AND SIMILAR TYPES IN ANY COMBINATION, EXCLUDING COMPACTION UNITS - SINGLE ENGINE, OVER 50 YDS. STRUCK); RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING IN TANDEM (SCRAPERS, BELLY DUMPS, AND SIMILAR TYPES IN ANY COMBINATION, EXCLUDING COMPACTION UNITS - MULTIPLE ENGINE, EUCLID, CATERPILLAR AND SIMILAR, OVER 25 YDS. AND UP TO 50 YDS. STRUCK) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 49.31 | 25.25 | 74.56 |
| OPERATOR: POWER EQUIPMENT GROUP 1: BARGEMAN; BRAKEMAN; COMPRESSOR OPERATOR; DITCH WITCH, WITH SEAT OR SIMILAR TYPE EQUIPMENT; ELEVATOR OPERATOR-INSIDE; ENGINEER OILER; FORKLIFT OPERATOR (INCLUDES LOED, LULL OR SIMILAR TYPES UNDER 5 TONS; GENERATOR OPERATOR; GENERATOR, PUMP OR COMPRESSOR PLANT OPERATOR; PUMP OPERATOR; SIGNALMAN; SWITCHMAN PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 45.30 | 25.25 | 70.55 |
| TANDEM (SCRAPERS, BELLY DUMPS AND SIMILAR TYPES IN ANY COMBINATION, EXCLUDING COMPACTION UNITS - SINGLE ENGINE, CATERPILLAR, EUCLID, ATHEY WAGON AND SIMILAR TYPES WITH ANY AND ALL ATTACHMENTS OVER 25 YDS.AND UP TO AND INCLUDING 50 CU. YDS. STRUCK); RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING IN TANDEM (SCRAPERS, BELLY DUMPS AND SIMILAR TYPES IN ANY COMBINATION, EXCLUDING COMPACTION UNITS - MULTIPLE ENGINE, UP TO AND INCLUDING 25 YDS. STRUCK) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 49.19 | 25.25 | 74.44 |
| OPERATOR: POWER EQUIPMENT GROUP 18: RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING IN TANDEM (SCRAPERS, BELLY DUMPS AND SIMILAR TYPES IN ANY COMBINATION, EXCLUDING COMPACTION UNITS - SINGLE ENGINE, UP TO AND INCLUDING 25 YDS. STRUCK) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 49.08 | 25.25 | 74.33 |
| OPERATOR: POWER EQUIPMENT GROUP 17: RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM (MULTIPLE ENGINE, EUCLID, CATERPILLAR AND SIMILAR, OVER 50 CU. YDS STRUCK); TANDEM TRACTOR OPERATOR (OPERATING CRAWLER TYPE TRACTORS IN TANDEM - QUAD 9 AND SIMILAR TYPE) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 48.98 | 25.25 | 74.23 |
| OPERATOR: POWER EQUIPMENT GROUP 16: RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM (SINGLE ENGINE, OVER 50 YDS. STRUCK); RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM (MULTIPLE ENGINE, EUCLID, CATERPILLAR AND SIMILAR, OVER 25 YDS. AND UP TO 50 YDS. STRUCK) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 48.81 | 25.25 | 74.06 |
| OPERATOR: POWER EQUIPMENT GROUP 15: RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM (SINGLE ENGINE, CATERPILLAR, EUCLID, ATHEY WAGON AND SIMILAR TYPES WITH ANY AND ALL ATTACHMENTS OVER 25 YDS. AND UP TO AND INCLUDING 50 YDS. STRUCK); RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM (MULTIPLE ENGINE-UP TO AND INCLUDING 25 YDS. STRUCK) PREMIUM PAY $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 48.69 | 25.25 | 73.94 |
| OPERATOR: POWER EQUIPMENT GROUP 14: CANAL LINER OPERATOR; CANAL TRIMMER OPERATOR; REMOTE- CONTROL EARTH-MOVING EQUIPMENT OPERATOR (OPERATING A SECOND PIECE OF EQUIPMENT: $1.00 PER HOUR ADDITIONAL); WHEEL EXCAVATOR OPERATOR (OVER 750 CU. YDS.) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 48.61 | 25.25 | 73.86 |
| OPERATOR: POWER EQUIPMENT GROUP 13: RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM (SINGLE ENGINE, UP TO AND INCLUDING 25 YDS. STRUCK) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 48.58 | 25.25 | 73.83 |
| HOE RAM OR SIMILAR WITH COMPRESSOR; MASS EXCAVATOR OPERATOR LESS THA 750 CU. YARDS; MECHANICAL FINISHING MACHINE OPERATOR; MOBILE FORM TRAVELER OPERATOR; MOTOR PATROL OPERATOR (MULTI-ENGINE); PIPE MOBILE MACHINE OPERATOR; RUBBER-TIRED EARTH- MOVING EQUIPMENT OPERATOR (MULTIPLE ENGINE, EUCLID, CATERPILLAR AND SIMILAR TYPE, OVER 50 CU. YDS STRUCK); RUBBER-TIRED SELF- LOADING SCRAPER OPERATOR (PADDLE-WHEEL-AUGER TYPE SELF-LOADING - TWO (2) OR MORE UNITS) PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 49.48 | 25.25 | 74.73 |
| OPERATOR: POWER EQUIPMENT GROUP 11: HEAVY DUTY REPAIRMAN - WELDER COMBINATION, WELDER - CERTIFIED PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 49.41 | 25.25 | 74.66 |
| OVER 50 YDS. STRUCK); PNEUMATIC PIPE RAMMING TOOL AND SIMILAR TYPES; PRESTRESSED WRAPPING MACHINE OPERATOR; RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR (SINGLE ENGINE, OVER 50 YDS. STRUCK); RUBBER TIRED EARTH MOVING EQUIPMENT OPERATOR (MULTIPLE ENGINE, EUCLID, CATERPILLAR AND SIMILAR OVER 25 YDS. AND UP TO 50 YDS. STRUCK), TOWER CRANE REPAIRMAN; TRACTOR LOADER OPERATOR (CRAWLER AND WHEEL TYPE OVER 6-1/2 YDS.); WOODS MIXER OPERATOR (AND SIMILAR PUGMILL EQUIPMENT) PREMIUM PAY $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR | 48.31 | 25.25 | 73.56 |
| IRONWORKER (ORNAMENTAL, REINFORCING AND STRUCTURAL) PREMIUM PAY: $9.00 additional per hour at the following locations: China Lake Naval Test Station, Chocolate Mountains Naval Reserve-Niland, Edwards AFB, Fort Irwin Military Station, Fort Irwin Training Center-Goldstone, San Clemente Island, San Nicholas Island, Susanville Federal Prison, 29 Palms - Marine Corps, U.S. Marine Base - Barstow, U.S. Naval Air Facility - Sealey, Vandenberg AFB Army Defense Language Institute - Monterey, Fallon Air Base, Naval Post Graduate School - Monterey, Yermo Marine Corps Logistics CenterPort Hueneme, Port Mugu, U.S. Coast Guard Station - Two Rock | 50.70 | 35.15 | 85.85 |
| IRONWORKER (FENCE ERECTOR) PREMIUM PAY: $9.00 additional per hour at the following locations China Lake Naval Test Station, Chocolate Mountains Naval Reserve-Niland, Edwards AFB, Fort Irwin Military Station, Fort Irwin Training Center-Goldstone, San Clemente Island, San Nicholas Island, Susanville Federal Prison, 29 Palms - Marine Corps, U.S. Marine Base - Barstow, U.S Naval Air Facility - Sealey, Vandenberg AFB Army Defense Language Institute - Monterey, Fallon Air Base, Naval Post Graduate School - Monterey, Yermo Marine Corps Logistics CenterPort Hueneme, Port Mugu, U.S. Coast Guard Station - Two Rock | 45.78 | 26.51 | 72.29 |
| BORING SYSTEM ELECTRONIC TRACKING LOCATOR (SAN LUIS OBISPO AND SANTA BARBARA COUNTIES) (RESIDENTIAL, 4 STORIES) | 38.24 | 20.09 | 58.33 |
| CRIBBER, SHORER, LAGGING, SHEETING AND TRENCH BRACING, HAND-GUIDED LAGGING HAMMER; HEAD ROCK SLINGER; LABORER, ASPHALT-RUBBER DISTRIBUTOR BOOT PERSON; LASER BEAM IN CONNECTION WITH LABORERS' WORK; OVER-SIZE CONCRETE VIBRATOR OPERATOR, 70 LBS AND OVER; PIPELAYER PERFORMING ALL SERVICES IN THE LAYING AND INSTALLATION OF PIPE FROM THE POINT OF RECEIVING PIPE IN THEDITCH UNTIL COMPLETION OF OPERATION, INCLUDING ANY AND ALL FORMS OF TUBULAR MATERIAL, WHETHER PIPE, METALLIC OR NON-METALLIC,CONDUIT AND ANY OTHER STATIONARY TYPE OF TUBULAR DEVICE USED FOR THE CONVEYING OF ANY SUBSTANCE OR ELEMENT, WHETHER WATER, SEWAGE, SOLID GAS, AIR, OR OTHER PRODUCT WHATSOEVER AND WITHOUT REGARD TO THE NATURE OF MATERIAL FROM WHICH THE TUBULAR MATERIAL IS FABRICATED; NO-JOINT PIPE AND STRIPPING OF SAME; PREFABRICATED MANHOLE INSTALLER; SANDBLASTER (NOZZLE PERSON), WATER BLASTING,PORTA SHOT-BLAST; TRAFFIC LANE CLOSURE, CERTIFIED. (SAN LUIS OBISPO AND SANTA BARBARA COUNTIES) (RESIDENTIAL, 4 STORIES) | 37.89 | 20.09 | 57.98 |
| HYDRO SEEDER AND SIMILAR TYPE; IMPACT WRENCH MULTI-PLATE; KETTLE PERSON, POT PERSON AND WORKERS APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME CAUSTIC AND SIMILAR TYPE MATERIALS (""APPLYING"" MEANS APPLYING, DIPPING, BRUSHING OR HANDLING OF SUCH MATERIALS FOR PIPE WRAPPING AND WATERPROOFING); OPERATOR OF PNEUMATIC, GAS, ELECTRIC TOOLS, VIBRATING MACHINE, PAVEMENT BREAKER, AIR BLASTING, COME-ALONGS, AND SIMILAR MECHANICAL TOOLS NOT SEPARATELY CLASSIFIED HEREIN; OPERATION OF REMOTE CONTROLLED ROBOTIC TOOLS IN CONNECTION WITH LABORER'S WORK; PIPELAYER'S BACKUP PERSON, COATING, GROUTING, MAKING OF JOINTS, SEALING, CAULKING, DIAPERING AND INCLUDING RUBBER GASKET JOINTS, POINTING AND ANY AND ALL OTHER SERVICES; POWER POST HOLE DIGGER; ROCK SLINGER; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; STEEL HEADERBOARD AND GUIDELINE SETTER; TAMPER, BARKO, WACKER AND SIMILAR TYPE; TRENCHING MACHINE, HAND-PROPELLED (SAN LUIS OBISPO AND SANTA BARBARA COUNTIES) (RESIDENTIAL, 4 STORIES) | 36.34 | 20.09 | 56.43 |
| CONCRETE, THE HANDLING OF THE CHUTE FROM READYMIX TRUCKS, SUCH AS WALLS, SLABS, DECKS, FLOORS, FOUNDATION, FOOTINGS, CURB, GUTTERS AND SIDEWALKS; CONCRETE CURER, IMPERVIOUS MEMBRANE AND FORM OILER; CUTTING TORCH OPERATOR (DEMOLITION); FINE GRADER, HIGHWAYS AND STREET PAVING, AIRPORT, RUNWAYS AND SIMILAR TYPE HEAVY CONSTRUCTION; GAS, OIL AND/OR WATER PIPELINE WRAPPER - POT TENDER AND FORM PERSON; GUINEA CHASER; HEADERBOARD PERSON - ASPHALT INSTALLATION OF ALL ASPHALT OVERLAY FABRIC AND MATERIALS USED FOR REINFORCING ASPHALT; LABORER, PACKING ROD STEEL AND PANS; MEMBRANE VAPOR BARRIER INSTALLER; POWER BROOM SWEEPER (SMALL); RIPRAP STONEPAVER, PLACING STONE OR WET SACKED CONCRETE; ROTO SCRAPER AND TILLER; SANDBLASTER (POT TENDER); SEPTIC TANK DIGGER AND INSTALLER (LEAD); TANK SCALER AND CLEANER; TREE CLIMBER, FALLER, CHAIN SAW OPERATOR, PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDER; UNDERGROUND LABORER, INCLUDING CAISSON BELLOWER (SAN LUIS OBISPO AND SANTA BARBARA COUNTIES) (RESIDENTIAL, 4 STORIES) | 35.79 | 20.09 | 55.88 |
| LOADER, PILER AND DEBRIS HANDLER; FLAG PERSON; GAS, OIL AND/OR WATER PIPELINE LABORER; LABORER, ASPHALT-RUBBER MATERIAL LOADER; LABORER, GENERAL OR CONSTRUCTION; LABORER, GENERAL CLEAN-UP; LABORER, LANDSCAPING; LABORER, JETTING; LABORER, TEMPORARY WATER AND AIR LINES; MATERIAL HOSE OPERATOR (WALLS, SLABS, FLOORS AND DECKS); PLUGGING, FILLING OF SHEE BOLT HOLES; DRY PACKING OF CONCRETE AND PATCHING; POST HOLE DIGGER (MANUAL);RAILROAD MAINTENANCE, REPAIR TRACK PERSON AND ROAD BEDS;STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORERS; RIGGING ANDSIGNALING; SCALER; SLIP FORM RAISER; SLURRY SEAL CREW (MIXER OPERATOR, APPLICATOR OPERATOR, SQUEEGEE PERSON, SHUTTLE PERSON, TOP PERSON), FILLING OF CRACKS BY ANY METHOD ON ANY SURFACE; TAR AND MORTAR; TOOL CRIB OR TOOL HOUSE LABORER; TRAFFIC CONTROL BY ANY METHOD; WINDOW CLEANER; WIRE MESH PULLING - ALL CONCRETE POURING OPERATIONS (SAN LUIS OBISPO AND SANTA BARBARA COUNTIES) (RESIDENTIAL, 4 STORIES) | 35.24 | 20.09 | 55.33 |
| BRICK TENDER (SAN LUIS OBISPO AND SANTA BARBARA COUNTIES) | 42.60 | 22.13 | 64.73 |
| BRICK TENDER (LOS ANGELES COUNTY) | 42.60 | 22.13 | 64.73 |
| BORING SYSTEM ELECTRONIC TRACKING LOCATOR (LOS ANGELES COUNTY) (RESIDENTIAL, 4 STORIES) | 42.23 | 23.30 | 65.53 |
| WALLS OR FLAT WORK, SCORING OLD OR NEW CONCRETE; CRIBBER, SHORER, LAGGING, SHEETING AND TRENCH BRACING, HAND-GUIDED LAGGING HAMMER; HEAD ROCK SLINGER; LABORER, ASPHALT-RUBBER DISTRIBUTOR BOOT PERSON; LASER BEAM IN CONNECTION WITH LABORERS' WORK; OVER-SIZE CONCRETE VIBRATOR OPERATOR, 70 LBS AND OVER; PIPELAYER PERFORMING ALL SERVICES IN THE LAYING AND INSTALLATION OF PIPE FROM THE POINT OF RECEIVING PIPE IN THEDITCH UNTIL COMPLETION OF OPERATION, INCLUDING ANY AND ALL FORMS OF TUBULAR MATERIAL, WHETHER PIPE, METALLIC OR NON-METALLIC,CONDUIT AND ANY OTHER STATIONARY TYPE OF TUBULAR DEVICE USED FOR THE CONVEYING OF ANY SUBSTANCE OR ELEMENT, WHETHER WATER, SEWAGE, SOLID GAS, AIR, OR OTHER PRODUCT WHATSOEVER AND WITHOUT REGARD TO THE NATURE OF MATERIAL FROM WHICH THE TUBULAR MATERIAL IS FABRICATED; NO-JOINT PIPE AND STRIPPING OF SAME; PREFABRICATED MANHOLE INSTALLER; SANDBLASTER (NOZZLE PERSON), WATER BLASTING,PORTA SHOT-BLAST; TRAFFIC LANE CLOSURE, CERTIFIED. (LOS ANGELES COUNTY) (RESIDENTIAL, 4 STORIES) | 41.88 | 23.30 | 65.18 |
| HYDRO SEEDER AND SIMILAR TYPE; IMPACT WRENCH MULTI-PLATE; KETTLE PERSON, POT PERSON AND WORKERS APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME CAUSTIC AND SIMILAR TYPE MATERIALS (""APPLYING"" MEANS APPLYING, DIPPING, BRUSHING OR HANDLING OF SUCH MATERIALS FOR PIPE WRAPPING AND WATERPROOFING); OPERATOR OF PNEUMATIC, GAS, ELECTRIC TOOLS, VIBRATING MACHINE, PAVEMENT BREAKER, AIR BLASTING, COME-ALONGS, AND SIMILAR MECHANICAL TOOLS NOT SEPARATELY CLASSIFIED HEREIN; OPERATION OF REMOTE CONTROLLED ROBOTIC TOOLS IN CONNECTION WITH LABORER'S WORK; PIPELAYER'S BACKUP PERSON, COATING, GROUTING, MAKING OF JOINTS, SEALING, CAULKING, DIAPERING AND INCLUDING RUBBER GASKET JOINTS, POINTING AND ANY AND ALL OTHER SERVICES; POWER POST HOLE DIGGER; ROCK SLINGER; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; STEEL HEADERBOARD AND GUIDELINE SETTER; TAMPER, BARKO, WACKER AND SIMILAR TYPE; TRENCHING MACHINE, HAND-PROPELLED (LOS ANGELES COUNTY) (RESIDENTIAL, 4 STORIES) | 40.33 | 23.30 | 63.63 |
| CONCRETE, THE HANDLING OF THE CHUTE FROM READYMIX TRUCKS, SUCH AS WALLS, SLABS, DECKS, FLOORS, FOUNDATION, FOOTINGS, CURB, GUTTERS AND SIDEWALKS; CONCRETE CURER, IMPERVIOUS MEMBRANE AND FORM OILER; CUTTING TORCH OPERATOR (DEMOLITION); FINE GRADER, HIGHWAYS AND STREET PAVING, AIRPORT, RUNWAYS AND SIMILAR TYPE HEAVY CONSTRUCTION; GAS, OIL AND/OR WATER PIPELINE WRAPPER - POT TENDER AND FORM PERSON; GUINEA CHASER; HEADERBOARD PERSON - ASPHALT INSTALLATION OF ALL ASPHALT OVERLAY FABRIC AND MATERIALS USED FOR REINFORCING ASPHALT; LABORER, PACKING ROD STEEL AND PANS; MEMBRANE VAPOR BARRIER INSTALLER; POWER BROOM SWEEPER (SMALL); RIPRAP STONEPAVER, PLACING STONE OR WET SACKED CONCRETE; ROTO SCRAPER AND TILLER; SANDBLASTER (POT TENDER); SEPTIC TANK DIGGER AND INSTALLER (LEAD); TANK SCALER AND CLEANER; TREE CLIMBER, FALLER, CHAIN SAW OPERATOR, PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDER; UNDERGROUND LABORER, INCLUDING CAISSON BELLOWER (LOS ANGELES COUNTY) (RESIDENTIAL, 4 STORIES) | 39.78 | 23.30 | 63.08 |
| LOADER, PILER AND DEBRIS HANDLER; FLAG PERSON; GAS, OIL AND/OR WATER PIPELINE LABORER; LABORER, ASPHALT-RUBBER MATERIAL LOADER; LABORER, GENERAL OR CONSTRUCTION; LABORER, GENERAL CLEAN-UP; LABORER, LANDSCAPING; LABORER, JETTING; LABORER, TEMPORARY WATER AND AIR LINES; MATERIAL HOSE OPERATOR (WALLS, SLABS, FLOORS AND DECKS); PLUGGING, FILLING OF SHEE BOLT HOLES; DRY PACKING OF CONCRETE AND PATCHING; POST HOLE DIGGER (MANUAL);RAILROAD MAINTENANCE, REPAIR TRACK PERSON AND ROAD BEDS;STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORERS; RIGGING ANDSIGNALING; SCALER; SLIP FORM RAISER; SLURRY SEAL CREW (MIXER OPERATOR, APPLICATOR OPERATOR, SQUEEGEE PERSON, SHUTTLE PERSON, TOP PERSON), FILLING OF CRACKS BY ANY METHOD ON ANY SURFACE; TAR AND MORTAR; TOOL CRIB OR TOOL HOUSE LABORER; TRAFFIC CONTROL BY ANY METHOD; WINDOW CLEANER; WIRE MESH PULLING - ALL CONCRETE POURING OPERATIONS (LOS ANGELES COUNTY) (RESIDENTIAL, 4 STORIES) | 39.23 | 23.30 | 62.53 |
| ASBESTOS REMOVAL LABORER SCOPE OF WORK: INCLUDES SITE MOBILIZATION, INITIAL SITE CLEANUP, SITE PREPARATION, REMOVAL OF ASBESTOS CONTAINING MATERIAL AND TOXIC WASTE (INCLUDING LEAD ABATEMENT AND ANY OTHER TOXIC MATERIAL), ENCAPSULATION, ENCLOSURE AND DISPOSAL OF ASBESTOS CONTAINING MATERIALS AND TOXIC WASTE(INCLUDING LEAD ABATEMENT AND ANY OTHER TOXIC MATERIALS) BY HAND OR WITH EQUIPMENT OR MACHINERY; SCAFFOLDING, FABRICATION OF TEMPORARY WOODEN BARRIERS AND ASSEMBLY OF DECONTAMINATION STATIONS | 46.48 | 25.93 | 72.41 |
| LABORERS: (2) ALL OTHER WORK RESIDENTIAL, 3 STORIES AND UNDER | 46.00 | 22.70 | 68.70 |
| LABORERS: (1) CLEANUP, FENCING (CHAIN LINK OR WOOD), LANDSCAPING RESIDENTIAL, 3 STORIES AND UNDER | 45.00 | 22.70 | 67.70 |
| BORING SYSTEM ELECTRONIC TRACKING LOCATOR (VENTURA COUNTY) (RESIDENTIAL, 4 STORIES) | 38.24 | 20.09 | 58.33 |
| WALLS OR FLAT WORK, SCORING OLD OR NEW CONCRETE; CRIBBER, SHORER, LAGGING, SHEETING AND TRENCH BRACING, HAND-GUIDED LAGGING HAMMER; HEAD ROCK SLINGER; LABORER, ASPHALT-RUBBER DISTRIBUTOR BOOT PERSON; LASER BEAM IN CONNECTION WITH LABORERS' WORK; OVER-SIZE CONCRETE VIBRATOR OPERATOR, 70 LBS AND OVER; PIPELAYER PERFORMING ALL SERVICES IN THE LAYING AND INSTALLATION OF PIPE FROM THE POINT OF RECEIVING PIPE IN THEDITCH UNTIL COMPLETION OF OPERATION, INCLUDING ANY AND ALL FORMS OF TUBULAR MATERIAL, WHETHER PIPE, METALLIC OR NON-METALLIC,CONDUIT AND ANY OTHER STATIONARY TYPE OF TUBULAR DEVICE USED FOR THE CONVEYING OF ANY SUBSTANCE OR ELEMENT, WHETHER WATER, SEWAGE, SOLID GAS, AIR, OR OTHER PRODUCT WHATSOEVER AND WITHOUT REGARD TO THE NATURE OF MATERIAL FROM WHICH THE TUBULAR MATERIAL IS FABRICATED; NO-JOINT PIPE AND STRIPPING OF SAME; PREFABRICATED MANHOLE INSTALLER; SANDBLASTER (NOZZLE PERSON), WATER BLASTING,PORTA SHOT-BLAST; TRAFFIC LANE CLOSURE, CERTIFIED (VENTURA COUNTY) (RESIDENTIAL, 4 STORIES) | 37.89 | 20.09 | 57.98 |
| HYDRO SEEDER AND SIMILAR TYPE; IMPACT WRENCH MULTI-PLATE; KETTLE PERSON, POT PERSON AND WORKERS APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME CAUSTIC AND SIMILAR TYPE MATERIALS (""APPLYING"" MEANS APPLYING, DIPPING, BRUSHING OR HANDLING OF SUCH MATERIALS FOR PIPE WRAPPING AND WATERPROOFING); OPERATOR OF PNEUMATIC, GAS, ELECTRIC TOOLS, VIBRATING MACHINE, PAVEMENT BREAKER, AIR BLASTING, COME-ALONGS, AND SIMILAR MECHANICAL TOOLS NOT SEPARATELY CLASSIFIED HEREIN; OPERATION OF REMOTE CONTROLLED ROBOTIC TOOLS IN CONNECTION WITH LABORER'S WORK; PIPELAYER'S BACKUP PERSON, COATING, GROUTING, MAKING OF JOINTS, SEALING, CAULKING, DIAPERING AND INCLUDING RUBBER GASKET JOINTS, POINTING AND ANY AND ALL OTHER SERVICES; POWER POST HOLE DIGGER; ROCK SLINGER; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; STEEL HEADERBOARD AND GUIDELINE SETTER; TAMPER, BARKO, WACKER AND SIMILAR TYPE; TRENCHING MACHINE, HAND-PROPELLED (VENTURA COUNTY) (RESIDENTIAL, 4 STORIES) | 36.34 | 20.09 | 56.43 |
| CONCRETE, THE HANDLING OF THE CHUTE FROM READYMIX TRUCKS, SUCH AS WALLS, SLABS, DECKS, FLOORS, FOUNDATION, FOOTINGS, CURB, GUTTERS AND SIDEWALKS; CONCRETE CURER, IMPERVIOUS MEMBRANE AND FORM OILER; CUTTING TORCH OPERATOR (DEMOLITION); FINE GRADER, HIGHWAYS AND STREET PAVING, AIRPORT, RUNWAYS AND SIMILAR TYPE HEAVY CONSTRUCTION; GAS, OIL AND/OR WATER PIPELINE WRAPPER - POT TENDER AND FORM PERSON; GUINEA CHASER; HEADERBOARD PERSON - ASPHALT INSTALLATION OF ALL ASPHALT OVERLAY FABRIC AND MATERIALS USED FOR REINFORCING ASPHALT; LABORER, PACKING ROD STEEL AND PANS; MEMBRANE VAPOR BARRIER INSTALLER; POWER BROOM SWEEPER (SMALL); RIPRAP STONEPAVER, PLACING STONE OR WET SACKED CONCRETE; ROTO SCRAPER AND TILLER; SANDBLASTER (POT TENDER); SEPTIC TANK DIGGER AND INSTALLER (LEAD); TANK SCALER AND CLEANER; TREE CLIMBER, FALLER, CHAIN SAW OPERATOR, PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDER; UNDERGROUND LABORER, INCLUDING CAISSON BELLOWER (VENTURA COUNTY) (RESIDENTIAL, 4 STORIES) | 35.79 | 20.09 | 55.88 |
| LOADER, PILER AND DEBRIS HANDLER; FLAG PERSON; GAS, OIL AND/OR WATER PIPELINE LABORER; LABORER, ASPHALT-RUBBER MATERIAL LOADER; LABORER, GENERAL OR CONSTRUCTION; LABORER, GENERAL CLEAN-UP; LABORER, LANDSCAPING; LABORER, JETTING; LABORER, TEMPORARY WATER AND AIR LINES; MATERIAL HOSE OPERATOR (WALLS, SLABS, FLOORS AND DECKS); PLUGGING, FILLING OF SHEE BOLT HOLES; DRY PACKING OF CONCRETE AND PATCHING; POST HOLE DIGGER (MANUAL);RAILROAD MAINTENANCE, REPAIR TRACK PERSON AND ROAD BEDS;STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORERS; RIGGING ANDSIGNALING; SCALER; SLIP FORM RAISER; SLURRY SEAL CREW (MIXER OPERATOR, APPLICATOR OPERATOR, SQUEEGEE PERSON, SHUTTLE PERSON, TOP PERSON), FILLING OF CRACKS BY ANY METHOD ON ANY SURFACE; TAR AND MORTAR; TOOL CRIB OR TOOL HOUSE LABORER; TRAFFIC CONTROL BY ANY METHOD; WINDOW CLEANER; WIRE MESH PULLING - ALL CONCRETE POURING OPERATIONS (VENTURA COUNTY) (RESIDENTIAL, 4 STORIES) | 35.24 | 20.09 | 55.33 |
| BRICK TENDER (VENTURA COUNTY) | 42.60 | 22.13 | 64.73 |
| BORING SYSTEM ELECTRONIC TRACKING LOCATOR (ORANGE COUNTY) (RESIDENTIAL, 4 STORIES) | 38.24 | 20.09 | 58.33 |
| WALLS OR FLAT WORK, SCORING OLD OR NEW CONCRETE; CRIBBER, SHORER, LAGGING, SHEETING AND TRENCH BRACING, HAND-GUIDED LAGGING HAMMER; HEAD ROCK SLINGER; LABORER, ASPHALT-RUBBER DISTRIBUTOR BOOT PERSON; LASER BEAM IN CONNECTION WITH LABORERS' WORK; OVER-SIZE CONCRETE VIBRATOR OPERATOR, 70 LBS AND OVER; PIPELAYER PERFORMING ALL SERVICES IN THE LAYING AND INSTALLATION OF PIPE FROM THE POINT OF RECEIVING PIPE IN THEDITCH UNTIL COMPLETION OF OPERATION, INCLUDING ANY AND ALL FORMS OF TUBULAR MATERIAL, WHETHER PIPE, METALLIC OR NON-METALLIC,CONDUIT AND ANY OTHER STATIONARY TYPE OF TUBULAR DEVICE USED FOR THE CONVEYING OF ANY SUBSTANCE OR ELEMENT, WHETHER WATER, SEWAGE, SOLID GAS, AIR, OR OTHER PRODUCT WHATSOEVER AND WITHOUT REGARD TO THE NATURE OF MATERIAL FROM WHICH THE TUBULAR MATERIAL IS FABRICATED; NO-JOINT PIPE AND STRIPPING OF SAME; PREFABRICATED MANHOLE INSTALLER; SANDBLASTER (NOZZLE PERSON), WATER BLASTING,PORTA SHOT-BLAST; TRAFFIC LANE CLOSURE, CERTIFIED (ORANGE COUNTY) (RESIDENTIAL, 4 STORIES) | 37.89 | 20.09 | 57.98 |
| HYDRO SEEDER AND SIMILAR TYPE; IMPACT WRENCH MULTI-PLATE; KETTLE PERSON, POT PERSON AND WORKERS APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME CAUSTIC AND SIMILAR TYPE MATERIALS (""APPLYING"" MEANS APPLYING, DIPPING, BRUSHING OR HANDLING OF SUCH MATERIALS FOR PIPE WRAPPING AND WATERPROOFING); OPERATOR OF PNEUMATIC, GAS, ELECTRIC TOOLS, VIBRATING MACHINE, PAVEMENT BREAKER, AIR BLASTING, COME-ALONGS, AND SIMILAR MECHANICAL TOOLS NOT SEPARATELY CLASSIFIED HEREIN; OPERATION OF REMOTE CONTROLLED ROBOTIC TOOLS IN CONNECTION WITH LABORER'S WORK; PIPELAYER'S BACKUP PERSON, COATING, GROUTING, MAKING OF JOINTS, SEALING, CAULKING, DIAPERING AND INCLUDING RUBBER GASKET JOINTS, POINTING AND ANY AND ALL OTHER SERVICES; POWER POST HOLE DIGGER; ROCK SLINGER; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; STEEL HEADERBOARD AND GUIDELINE SETTER; TAMPER, BARKO, WACKER AND SIMILAR TYPE; TRENCHING MACHINE, HAND-PROPELLED (ORANGE COUNTY) (RESIDENTIAL, 4 STORIES) | 36.34 | 20.09 | 56.43 |
| LOADER, PILER AND DEBRIS HANDLER; FLAG PERSON; GAS, OIL AND/OR WATER PIPELINE LABORER; LABORER, ASPHALT-RUBBER MATERIAL LOADER; LABORER, GENERAL OR CONSTRUCTION; LABORER, GENERAL CLEAN-UP; LABORER, LANDSCAPING; LABORER, JETTING; LABORER, TEMPORARY WATER AND AIR LINES; MATERIAL HOSE OPERATOR (WALLS, SLABS, FLOORS AND DECKS); PLUGGING, FILLING OF SHEE BOLT HOLES; DRY PACKING OF CONCRETE AND PATCHING; POST HOLE DIGGER (MANUAL);RAILROAD MAINTENANCE, REPAIR TRACK PERSON AND ROAD BEDS;STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORERS; RIGGING ANDSIGNALING; SCALER; SLIP FORM RAISER; SLURRY SEAL CREW (MIXER OPERATOR, APPLICATOR OPERATOR, SQUEEGEE PERSON, SHUTTLE PERSON, TOP PERSON), FILLING OF CRACKS BY ANY METHOD ON ANY SURFACE; TAR AND MORTAR; TOOL CRIB OR TOOL HOUSE LABORER; TRAFFIC CONTROL BY ANY METHOD; WINDOW CLEANER; WIRE MESH PULLING - ALL CONCRETE POURING OPERATIONS (ORANGE COUNTY) (RESIDENTIAL, 4 STORIES) | 35.24 | 20.09 | 55.33 |
| BRICK TENDER (ORANGE COUNTY) | 42.60 | 22.13 | 64.73 |
| BORING SYSTEM ELECTRONIC TRACKING LOCATOR (SAN BERNARDINO COUNTY) (RESIDENTIAL, 4 STORIES) | 38.24 | 20.09 | 58.33 |
| WALLS OR FLAT WORK, SCORING OLD OR NEW CONCRETE; CRIBBER, SHORER, LAGGING, SHEETING AND TRENCH BRACING, HAND-GUIDED LAGGING HAMMER; HEAD ROCK SLINGER; LABORER, ASPHALT-RUBBER DISTRIBUTOR BOOT PERSON; LASER BEAM IN CONNECTION WITH LABORERS' WORK; OVER-SIZE CONCRETE VIBRATOR OPERATOR, 70 LBS AND OVER; PIPELAYER PERFORMING ALL SERVICES IN THE LAYING AND INSTALLATION OF PIPE FROM THE POINT OF RECEIVING PIPE IN THEDITCH UNTIL COMPLETION OF OPERATION, INCLUDING ANY AND ALL FORMS OF TUBULAR MATERIAL, WHETHER PIPE, METALLIC OR NON-METALLIC,CONDUIT AND ANY OTHER STATIONARY TYPE OF TUBULAR DEVICE USED FOR THE CONVEYING OF ANY SUBSTANCE OR ELEMENT, WHETHER WATER, SEWAGE, SOLID GAS, AIR, OR OTHER PRODUCT WHATSOEVER AND WITHOUT REGARD TO THE NATURE OF MATERIAL FROM WHICH THE TUBULAR MATERIAL IS FABRICATED; NO-JOINT PIPE AND STRIPPING OF SAME; PREFABRICATED MANHOLE INSTALLER; SANDBLASTER (NOZZLE PERSON), WATER BLASTING,PORTA SHOT-BLAST; TRAFFIC LANE CLOSURE, CERTIFIED. (SAN BERNARDINO COUNTY) (RESIDENTIAL, 4 STORIES) | 37.89 | 20.09 | 57.98 |
| HYDRO SEEDER AND SIMILAR TYPE; IMPACT WRENCH MULTI-PLATE; KETTLE PERSON, POT PERSON AND WORKERS APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME CAUSTIC AND SIMILAR TYPE MATERIALS (""APPLYING"" MEANS APPLYING, DIPPING, BRUSHING OR HANDLING OF SUCH MATERIALS FOR PIPE WRAPPING AND WATERPROOFING); OPERATOR OF PNEUMATIC, GAS, ELECTRIC TOOLS, VIBRATING MACHINE, PAVEMENT BREAKER, AIR BLASTING, COME-ALONGS, AND SIMILAR MECHANICAL TOOLS NOT SEPARATELY CLASSIFIED HEREIN; OPERATION OF REMOTE CONTROLLED ROBOTIC TOOLS IN CONNECTION WITH LABORER'S WORK; PIPELAYER'S BACKUP PERSON, COATING, GROUTING, MAKING OF JOINTS, SEALING, CAULKING, DIAPERING AND INCLUDING RUBBER GASKET JOINTS, POINTING AND ANY AND ALL OTHER SERVICES; POWER POST HOLE DIGGER; ROCK SLINGER; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; STEEL HEADERBOARD AND GUIDELINE SETTER; TAMPER, BARKO, WACKER AND SIMILAR TYPE; TRENCHING MACHINE, HAND-PROPELLED (SAN BERNARDINO COUNTY) (RESIDENTIAL, 4 STORIES) | 36.34 | 20.09 | 56.43 |
| CONCRETE, THE HANDLING OF THE CHUTE FROM READYMIX TRUCKS, SUCH AS WALLS, SLABS, DECKS, FLOORS, FOUNDATION, FOOTINGS, CURB, GUTTERS AND SIDEWALKS; CONCRETE CURER, IMPERVIOUS MEMBRANE AND FORM OILER; CUTTING TORCH OPERATOR (DEMOLITION); FINE GRADER, HIGHWAYS AND STREET PAVING, AIRPORT, RUNWAYS AND SIMILAR TYPE HEAVY CONSTRUCTION; GAS, OIL AND/OR WATER PIPELINE WRAPPER - POT TENDER AND FORM PERSON; GUINEA CHASER; HEADERBOARD PERSON - ASPHALT INSTALLATION OF ALL ASPHALT OVERLAY FABRIC AND MATERIALS USED FOR REINFORCING ASPHALT; LABORER, PACKING ROD STEEL AND PANS; MEMBRANE VAPOR BARRIER INSTALLER; POWER BROOM SWEEPER (SMALL); RIPRAP STONEPAVER, PLACING STONE OR WET SACKED CONCRETE; ROTO SCRAPER AND TILLER; SANDBLASTER (POT TENDER); SEPTIC TANK DIGGER AND INSTALLER (LEAD); TANK SCALER AND CLEANER; TREE CLIMBER, FALLER, CHAIN SAW OPERATOR, PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDER; UNDERGROUND LABORER, INCLUDING CAISSON BELLOWER (SAN BERNARDINO COUNTY) (RESIDENTIAL, 4 STORIES) | 35.79 | 20.09 | 55.88 |
| LOADER, PILER AND DEBRIS HANDLER; FLAG PERSON; GAS, OIL AND/OR WATER PIPELINE LABORER; LABORER, ASPHALT-RUBBER MATERIAL LOADER; LABORER, GENERAL OR CONSTRUCTION; LABORER, GENERAL CLEAN-UP; LABORER, LANDSCAPING; LABORER, JETTING; LABORER, TEMPORARY WATER AND AIR LINES; MATERIAL HOSE OPERATOR (WALLS, SLABS, FLOORS AND DECKS); PLUGGING, FILLING OF SHEE BOLT HOLES; DRY PACKING OF CONCRETE AND PATCHING; POST HOLE DIGGER (MANUAL);RAILROAD MAINTENANCE, REPAIR TRACK PERSON AND ROAD BEDS;STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORERS; RIGGING ANDSIGNALING; SCALER; SLIP FORM RAISER; SLURRY SEAL CREW (MIXER OPERATOR, APPLICATOR OPERATOR, SQUEEGEE PERSON, SHUTTLE PERSON, TOP PERSON), FILLING OF CRACKS BY ANY METHOD ON ANY SURFACE; TAR AND MORTAR; TOOL CRIB OR TOOL HOUSE LABORER; TRAFFIC CONTROL BY ANY METHOD; WINDOW CLEANER; WIRE MESH PULLING - ALL CONCRETE POURING OPERATIONS (SAN BERNARDINO COUNTY) (RESIDENTIAL, 4 STORIES) | 35.24 | 20.09 | 55.33 |
| BRICK TENDER (SAN BERNARDINO COUNTY) | 42.60 | 22.13 | 64.73 |
| LABORERS:, STRIPING/SLURRY SEAL: GROUP 4 STRIPER LAYOUT AND APPLICATION OF TRAFFIC STRIPES AND MARKINGS; HOT THERMO PLASTIC; TAPE TRAFFIC STRIPES AND MARKINGS, INCLUDING TRAFFIC CONTROL; OPERATION OF ALL RELATED MACHINERY AND EQUIPMENT | 54.35 | 23.97 | 78.32 |
| LABORERS:, STRIPING/SLURRY SEAL: GROUP 3 TRAFFIC DELINEATING DEVICE APPLICATOR: LAYOUT AND APPLICATION OF PAVEMENT MARKERS, DELINEATING SIGNS, RUMBLE AND TRAFFIC BARS, ADHESIVES, GUIDE MARKERS, OTHER TRAFFIC DELINEATING DEVICES INCLUDING TRAFFIC CONTROL. THIS CATEGORY INCLUDES ALL TRAFFIC RELATED SURFACE PREPARATION (SANDBLASTING, WATERBLASTING, GRINDING) AS PART OF THE APPLICATION PROCESS TRAFFIC PROTECTIVE DELINEATING SYSTEM INSTALLER REMOVES, RELOCATES, INSTALLS, PERMANENTLY AFFIXED ROADSIDE AND PARKING DELINEATION BARRICADES, FENCING, CABLE ANCHOR, GUARD RAIL, REFERENCE SIGNS, MONUMENT MARKERS; OPERATION OF ALL RELATED MACHINERY AND EQUIPMENT; POWER BROOM SWEEPER | 52.61 | 23.97 | 76.58 |
| LABORERS:, STRIPING/SLURRY SEAL: GROUP 2 TRAFFIC SURFACE ABRASIVE BLASTER; POT TENDER - REMOVAL OF ALL TRAFFIC LINES AND MARKINGS BY ANY METHOD (SANDBLASTING, WATERBLASTING, GRINDING, ETC.) AND PREPARATION OF SURFACE FOR COATINGS. TRAFFIC CONTROL PERSON: CONTROLLING AND DIRECTING TRAFFIC THROUGH BOTH CONVENTIONAL AND MOVING LANE CLOSURES; OPERATION OF ALL RELATED MACHINERY AND EQUIPMENT | 50.60 | 23.97 | 74.57 |
| LABORERS:, STRIPING/SLURRY SEAL: GROUP 1 PROTECTIVE COATING, PAVEMENT SEALING, INCLUDING REPAIR AND FILLING OF CRACKS BY ANY METHOD ON ANY SURFACE IN PARKING LOTS, GAME COURTS AND PLAYGROUNDS; CARSTOPS; OPERATION OF ALL RELATED MACHINERY AND EQUIPMENT; EQUIPMENT REPAIR TECHNICIAN | 49.30 | 23.97 | 73.27 |
| LABORERS: HORIZONTAL DIRECTIONAL DRILLING: (4) ELECTRONIC TRACKING LOCATOR | 51.96 | 20.86 | 72.82 |
| LABORERS: HORIZONTAL DIRECTIONAL DRILLING: (3) HORIZONTAL DIRECTIONAL DRILL OPERATOR | 49.96 | 20.86 | 70.82 |
| LABORERS: HORIZONTAL DIRECTIONAL DRILLING: (2) VEHICLE OPERATOR/HAULER | 48.11 | 20.86 | 68.97 |
| LABORERS: HORIZONTAL DIRECTIONAL DRILLING: (1) DRILLING CREW LABORER | 47.94 | 20.86 | 68.80 |
| BORING SYSTEM ELECTRONIC TRACKING LOCATOR (IMPERIAL AND RIVERSIDE COUNTIES) | 38.24 | 20.09 | 58.33 |
| WALLS OR FLAT WORK, SCORING OLD OR NEW CONCRETE; CRIBBER, SHORER, LAGGING, SHEETING AND TRENCH BRACING, HAND-GUIDED LAGGING HAMMER; HEAD ROCK SLINGER; LABORER, ASPHALT-RUBBER DISTRIBUTOR BOOT PERSON; LASER BEAM IN CONNECTION WITH LABORERS' WORK; OVER-SIZE CONCRETE VIBRATOR OPERATOR, 70 LBS AND OVER; PIPELAYER PERFORMING ALL SERVICES IN THE LAYING AND INSTALLATION OF PIPE FROM THE POINT OF RECEIVING PIPE IN THEDITCH UNTIL COMPLETION OF OPERATION, INCLUDING ANY AND ALL FORMS OF TUBULAR MATERIAL, WHETHER PIPE, METALLIC OR NON-METALLIC,CONDUIT AND ANY OTHER STATIONARY TYPE OF TUBULAR DEVICE USED FOR THE CONVEYING OF ANY SUBSTANCE OR ELEMENT, WHETHER WATER, SEWAGE, SOLID GAS, AIR, OR OTHER PRODUCT WHATSOEVER AND WITHOUT REGARD TO THE NATURE OF MATERIAL FROM WHICH THE TUBULAR MATERIAL IS FABRICATED; NO-JOINT PIPE AND STRIPPING OF SAME; PREFABRICATED MANHOLE INSTALLER; SANDBLASTER (NOZZLE PERSON), WATER BLASTING,PORTA SHOT-BLAST; TRAFFIC LANE CLOSURE, CERTIFIED (IMPERIAL AND RIVERSIDE COUNTIES) | 37.89 | 20.09 | 57.98 |
| HYDRO SEEDER AND SIMILAR TYPE; IMPACT WRENCH MULTI-PLATE; KETTLE PERSON, POT PERSON AND WORKERS APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME CAUSTIC AND SIMILAR TYPE MATERIALS (""APPLYING"" MEANS APPLYING, DIPPING, BRUSHING OR HANDLING OF SUCH MATERIALS FOR PIPE WRAPPING AND WATERPROOFING); OPERATOR OF PNEUMATIC, GAS, ELECTRIC TOOLS, VIBRATING MACHINE, PAVEMENT BREAKER, AIR BLASTING, COME-ALONGS, AND SIMILAR MECHANICAL TOOLS NOT SEPARATELY CLASSIFIED HEREIN; OPERATION OF REMOTE CONTROLLED ROBOTIC TOOLS IN CONNECTION WITH LABORER'S WORK; PIPELAYER'S BACKUP PERSON, COATING, GROUTING, MAKING OF JOINTS, SEALING, CAULKING, DIAPERING AND INCLUDING RUBBER GASKET JOINTS, POINTING AND ANY AND ALL OTHER SERVICES; POWER POST HOLE DIGGER; ROCK SLINGER; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; STEEL HEADERBOARD AND GUIDELINE SETTER; TAMPER, BARKO, WACKER AND SIMILAR TYPE; TRENCHING MACHINE, HAND-PROPELLED (IMPERIAL AND RIVERSIDE COUNTIES) | 36.34 | 20.09 | 56.43 |
| INSTALLER; CHUCKTENDER; CHUTE HANDLER, POURING CONCRETE, THE HANDLING OF THE CHUTE FROM READYMIX TRUCKS, SUCH AS WALLS, SLABS, DECKS, FLOORS, FOUNDATION, FOOTINGS, CURB, GUTTERS AND SIDEWALKS; CONCRETE CURER, IMPERVIOUS MEMBRANE AND FORM OILER; CUTTING TORCH OPERATOR (DEMOLITION); FINE GRADER, HIGHWAYS AND STREET PAVING, AIRPORT, RUNWAYS AND SIMILAR TYPE HEAVY CONSTRUCTION; GAS, OIL AND/OR WATER PIPELINE WRAPPER - POT TENDER AND FORM PERSON; GUINEA CHASER; HEADERBOARD PERSON - ASPHALT INSTALLATION OF ALL ASPHALT OVERLAY FABRIC AND MATERIALS USED FOR REINFORCING ASPHALT; LABORER, PACKING ROD STEEL AND PANS; MEMBRANE VAPOR BARRIER INSTALLER; POWER BROOM SWEEPER (SMALL); RIPRAP STONEPAVER, PLACING STONE OR WET SACKED CONCRETE; ROTO SCRAPER AND TILLER; SANDBLASTER (POT TENDER); SEPTIC TANK DIGGER AND INSTALLER (LEAD); TANK SCALER AND CLEANER; TREE CLIMBER, FALLER, CHAIN SAW OPERATOR, PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDER; UNDERGROUND LABORER, INCLUDING CAISSON BELLOWER (IMPERIAL AND RIVERSIDE COUNTIES) | 35.79 | 20.09 | 55.88 |
| LOADER, PILER AND DEBRIS HANDLER; FLAG PERSON; GAS, OIL AND/OR WATER PIPELINE LABORER; LABORER, ASPHALT-RUBBER MATERIAL LOADER; LABORER, GENERAL OR CONSTRUCTION; LABORER, GENERAL CLEAN-UP; LABORER, LANDSCAPING; LABORER, JETTING; LABORER, TEMPORARY WATER AND AIR LINES; MATERIAL HOSE OPERATOR (WALLS, SLABS, FLOORS AND DECKS); PLUGGING, FILLING OF SHEE BOLT HOLES; DRY PACKING OF CONCRETE AND PATCHING; POST HOLE DIGGER (MANUAL);RAILROAD MAINTENANCE, REPAIR TRACK PERSON AND ROAD BEDS;STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORERS; RIGGING ANDSIGNALING; SCALER; SLIP FORM RAISER; SLURRY SEAL CREW (MIXER OPERATOR, APPLICATOR OPERATOR, SQUEEGEE PERSON, SHUTTLE PERSON, TOP PERSON), FILLING OF CRACKS BY ANY METHOD ON ANY SURFACE; TAR AND MORTAR; TOOL CRIB OR TOOL HOUSE LABORER; TRAFFIC CONTROL BY ANY METHOD; WINDOW CLEANER; WIRE MESH PULLING - ALL CONCRETE POURING OPERATIONS (IMPERIAL AND RIVERSIDE COUNTIES) | 35.24 | 20.09 | 55.33 |
| BRICK TENDER (IMPERIAL AND RIVERSIDE COUNTIES) | 42.60 | 22.13 | 64.73 |
| LABORERS: PLASTER TENDER (4 STORIES) WORK ON A SWING STAGE SCAFFOLD: $1.00 PER HOUR ADDITIONAL WORK AT MILITARY BASES - $3.00 ADDITIONAL PER HOUR: CORONADO NAVAL AMPHIBIOUS BASE, FORT IRWIN, GEORGE AFB, MARINE CORPS AIR STATION-29 PALMS, IMPERIAL BEACH NAVAL AIR STATION, MARINE CORPS LOGISTICS SUPPLY BASE, MARINE CORPS PICKLE MEADOWS, MOUNTAIN WARFARE TRAINING CENTER, NAVAL AIR FACILITY-SEELEY, NORTH ISLAND NAVAL AIR STATION, VANDENBERG AFB | 39.47 | 23.32 | 62.79 |
| LABORERS: PLASTER TENDER (1 TO 3 STORIES) WORK ON A SWING STAGE SCAFFOLD: $1.00 PER HOUR ADDITIONAL. WORK AT MILITARY BASES - $3.00 ADDITIONAL PER HOUR: CORONADO NAVAL AMPHIBIOUS BASE, FORT IRWIN, GEORGE AFB, MARINE CORPS AIR STATION-29 PALMS, IMPERIAL BEACH NAVAL AIR STATION, MARINE CORPS LOGISTICS SUPPLY BASE, MARINE CORPS PICKLE MEADOWS, MOUNTAIN WARFARE TRAINING CENTER, NAVAL AIR FACILITY-SEELEY, NORTH ISLAND NAVAL AIR STATION, VANDENBERG AFB | 39.47 | 23.32 | 62.79 |
| LABORERS: PLASTER CLEAN-UP LABORER (4 STORIES) WORK ON A SWING STAGE SCAFFOLD: $1.00 PER HOUR ADDITIONAL. WORK AT MILITARY BASES - $3.00 ADDITIONAL PER HOUR: CORONADO NAVAL AMPHIBIOUS BASE, FORT IRWIN, GEORGE AFB, MARINE CORPS AIR STATION-29 PALMS, IMPERIAL BEACH NAVAL AIR STATION, MARINE CORPS LOGISTICS SUPPLY BASE, MARINE CORPS PICKLE MEADOWS, MOUNTAIN WARFARE TRAINING CENTER, NAVAL AIR FACILITY-SEELEY, NORTH ISLAND NAVAL AIR STATION, VANDENBERG AFB | 36.92 | 23.32 | 60.24 |
| LABORERS: PLASTER CLEAN-UP LABORER (1 TO 3 STORIES) WORK ON A SWING STAGE SCAFFOLD: $1.00 PER HOUR ADDITIONAL. WORK AT MILITARY BASES - $3.00 ADDITIONAL PER HOUR: CORONADO NAVAL AMPHIBIOUS BASE, FORT IRWIN, GEORGE AFB, MARINE CORPS AIR STATION-29 PALMS, IMPERIAL BEACH NAVAL AIR STATION, MARINE CORPS LOGISTICS SUPPLY BASE, MARINE CORPS PICKLE MEADOWS, MOUNTAIN WARFARE TRAINING CENTER, NAVAL AIR FACILITY-SEELEY, NORTH ISLAND NAVAL AIR STATION, VANDENBERG AFB | 36.92 | 23.32 | 60.24 |
| PAINTER, INCLUDING LEAD ABATEMENT: (3) JOURNEYMAN & INDUSTRIAL (SAN LUIS OBISPO, SANTA BARBARA & VENTURA) | 34.02 | 16.49 | 50.51 |
| PAINTER, INCLUDING LEAD ABATEMENT: (3) JOURNEYMAN & INDUSTRIAL (IMPERIAL, LOS ANGELES, ORANGE, RIVERSIDE & SAN BERNARDINO) | 34.02 | 16.49 | 50.51 |
| PAINTER, INCLUDING LEAD ABATEMENT: (2) ALL OTHER WORK (IMPERIAL, LOS ANGELES, ORANGE, RIVERSIDE & SAN BERNARDINO) | 32.12 | 16.09 | 48.21 |
| PAINTER, INCLUDING LEAD ABATEMENT: (2) ALL OTHER WORK (SAN LUIS OBISPO, SANTA BARBARA & VENTURA) | 30.04 | 16.03 | 46.07 |
| PAINTER, INCLUDING LEAD ABATEMENT: (1) REPAINT (IMPERIAL, LOS ANGELES, ORANGE, RIVERSIDE & SAN BERNARDINO) | 28.59 | 15.97 | 44.56 |
| PAINTER, INCLUDING LEAD ABATEMENT: (1) REPAINT (SAN LUIS OBISPO, SANTA BARBARA & VENTURA) | 25.40 | 15.87 | 41.27 |
| DRYWALL FINISHER/TAPER IMPERIAL (LOS ANGELES, ORANGE, RIVERSIDE, SAN BERNARDINO, SAN LUIS OBISPO, SANTA BARBARA AND VENTURA COUNTIES) | 32.27 | 14.70 | 46.97 |
| GLAZIER (IMPERIAL) | 52.90 | 22.16 | 75.06 |
| GLAZIER (LOS ANGELES, ORANGE, RIVERSIDE, SAN BERNARDINO, SANTA BARBARA AND VENTURA) FOOTNOTE ADDITIONAL $1.25 PER HOUR FOR WORK IN A CONDO, FROM THE THIRD (3RD) FLOOR AND UP. ADDITIONAL $1.25 PER HOUR FOR WORK ON THE OUTSIDE OF THE BUILDING FROM A SWING STAGE OR ANY SUSPENDED CONTRIVANCE, FROM THE GROUND UP | 53.05 | 30.64 | 83.69 |
| SOFT FLOOR LAYER (IMPERIAL) | 40.77 | 19.37 | 60.14 |
| GLAZIER (SAN LUIS OBISPO) | 49.22 | 30.47 | 79.69 |
| SOFT FLOOR LAYER (LOS ANGELES, ORANGE, RIVERSIDE, SAN BERNARDINO, SAN LUIS OBISPO, SANTA BARBARA AND VENTURA) | 45.15 | 19.43 | 64.58 |
| PLASTERER: 4-STORIES IMPERIAL, KERN, LOS ANGELES, ORANGE, RIVERSIDE, SAN BERNARDINO, SAN LUIS OBISPO, SANTA BARBARA AND VENTURA | 47.37 | 19.64 | 67.01 |
| PLASTERER: 1 - 3 STORIES IMPERIAL, KERN, LOS ANGELES, ORANGE, RIVERSIDE, SAN BERNARDINO, SAN LUIS OBISPO, SANTA BARBARA AND VENTURA | 44.34 | 19.64 | 63.98 |
| CEMENT MASON/CONCRETE FINISHER | 47.70 | 27.07 | 74.77 |
| PLUMBER/PIPEFITTER (RESIDENTIAL) | 48.83 | 22.73 | 71.56 |
| REFRIGERATION MECHANIC: REFRIGERATION FITTER (LOS ANGELES AND ORANGE) | 57.65 | 25.01 | 82.66 |
| PLUMBER (SEWER & STORM DRAIN WORK) | 48.84 | 23.58 | 72.42 |
| PLUMBER (LANDSCAPE/IRRIGATION FITTER) | 44.75 | 26.20 | 70.95 |
| ROOFER (LOS ANGELES, ORANGE, RIVERSIDE, SAN BERNARDINO, SAN LUIS OBISPO, SANTA BARBARA AND VENTURA) FOOTNOTE: Pitch premium: Work on which employees are exposed to pitch fumes or required to handle pitch, pitch base or pitch impregnated products, or any material containing coal tar pitch, the entire roofing crew shall receive $1.75 per hour ""pitch premium"" pay | 51.58 | 20.73 | 72.31 |
| ROOFER (IMPERIAL) | 42.80 | 12.64 | 55.44 |
| SPRINKLER FITTER: (AREA 2) AREA 2: SAN LUIS OBISPO, SANTA BARBARA COUNTIES, VENTURA (does not include Port Hueneme, Port Mugu, the city of Santa Paula, and that part of Ventura County within 25 miles of the city limits of Los Angeles) COUNTIES | 49.69 | 29.72 | 79.41 |
| SPRINKLER FITTER: (AREA 1) AREA 1: IMPERIAL COUNTY; LOS ANGELES COUNTY (does not include the city of Pomona, Catalina Island, and that part of Los Angeles County within 25 miles of the city limits of Los Angeles); ORANGE COUNTY (does not include Catalina Island; San Clemente Island; City of Santa Ana; and remainder of Orange County within 25 miles of the city limits of Los Angeles); RIVERSIDE COUNTY; AND SAN BERNARDINO COUNTY (does not include the northern part of City of Chino, or the cities of Montclair and Ontario) | 50.79 | 29.80 | 80.59 |
| SPRINKLER FITTER (LOS ANGELES COUNTY (THE CITY OF POMONA, CATALINA ISLAND, AND THAT PART OF LOS ANGELES COUNTY WITHIN 25 MILES OF THE CITY LIMITS OF LOS ANGELES); ORANGE COUNTY (SAN CLEMENTE ISLAND, THE CITY OF SANTA ANA, AND THAT PART OF ORANGE COUNTY WITHIN 25 MILES OF THE CITY LIMITS OF LOS ANGELES); SAN BERNARDINO COUNTY (THE NORTHERN PART OF THE CITY OF CHINO, AND THE CITIES OF MONTCLAIR AND ONTARIO); VENTURA COUNTY (PORT HUENEME, PORT MUGU, THE CITY OF SANTA PAULA, AND THAT PART OF VENTU | 58.60 | 33.65 | 92.25 |
| SHEET METAL WORKER: (AREA 1) AREA 1: LOS ANGELES COUNTY (South of a straight line drawn between gorman and Big Pines, excluding the area South of Imperial Highway East of the Los Angeles River, excluding the cities of Long Beach, Claremont, and Pomona, excluding Catalina Island) Work on general sheet metal and heating and air conditioning on single family dwellings, multiple family dwellings, track homes and apartment buildings individually conditioned by separate and independent units or systems | 33.10 | 10.81 | 43.91 |
| SHEET METAL WORKER: (AREA 2) AREA 2: LOS ANGELES (Remainder), ORANGE, RIVERSIDE & SAN BERNARDINO COUNTIES Work on general sheet metal and heating and air conditioning on single family dwellings, multiple family dwellings, track homes and apartment buildings individually conditioned by separate and independent units or systems | 29.54 | 19.09 | 48.63 |
| SHEET METAL TECHNICIAN (IMPERIA) SHEET METAL TECHNICIAN - SCOPE: A. EXISTING RESIDENTIAL BUILDINGS, BOTH SINGLE AND MULTI-FAMILY, WHERE EACH UNIT IS HEATED AND/OR COOLED BY A SEPARATE SYSTEM B. NEW SINGLE FAMILY RESIDENTIAL BUILDINGS INCLUDING TRACTS. C. NEW MULTI-FAMILY RESIDENTIAL BUILDINGS, NOT EXCEEDING FIVE STORIES OF LIVING SPACE IN HEIGHT, PROVIDED EACH UNIT IS HEATED OR COOLED BY A SEPARATE SYSTEM. HOTELS AND MOTELS ARE EXCLUDED. D. LIGHT COMMERCIAL WORK ANY SHEET METAL, HEATING AND AIR CONDITIONING WORK PERFORMED ON A PROJECT WHERE THE TOTAL CONSTRUCTION COST, EXCLUDING LAND, IS UNDER $1,000,000 E TENANT IMPROVEMENT WORK: ANY WORK NECESSARY TO FINISH INTERIOR SPACES TO CONFORM TO THE OCCUPANTS OF COMMERCIAL BUILDINGS, AFTER COMPLETION OF THE BUILDING SHELL | 38.65 | 10.31 | 48.96 |
| SHEET METAL WORKER (IMPERIAL) | 51.45 | 30.92 | 82.37 |
| SHEET METAL WORKER (SAN LUIS OBISPO, SANTA BARBARA AND VENTURA) HOLIDAYS: NEW YEAR'S DAY, MARTIN LUTHER KING DAY, PRESIDENT'S DAY, GOOD FRIDAY, MEMORIAL DAY, INDEPDENDENCE DAY, LABOR DAY, VETERANS DAY,THANKISGIVING DAY & FRIDAY AFTER, CHRISTMAS DAY | 46.87 | 31.15 | 78.02 |
| TRUCK DRIVERS: GROUP 12 BOOM TRUCK 17K AND ABOVE WORK ON ALL MILITARY BASES - $3.00 PER HOUR ADDITIONAL: [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, GEORGE AFB, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB] | 44.05 | 35.69 | 79.74 |
| TRUCK DRIVERS: GROUP 11 WATER PULL - TWIN ENGINE; WATER PULL - TWIN ENGINE WITH ATTACHMENTS; WINCH TRUCK DRIVER - $1.25 ADDITIONAL WHEN OPERATING WINCH OR SIMILAR SPECIAL ATTACHMENTS WORK ON ALL MILITARY BASES - $3.00 PER HOUR ADDITIONAL: [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, GEORGE AFB, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB] | 43.62 | 35.69 | 79.31 |
| TRUCK DRIVERS: GROUP 10 DUMP TRUCK - 50 YDS. OR MORE WATER LEVEL; WATER PULL - SINGLE ENGINE WITH ATTACHMENT WORK ON ALL MILITARY BASES - $3.00 PER HOUR ADDITIONAL: [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, GEORGE AFB, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB] | 43.12 | 35.69 | 78.81 |
| TRUCK DRIVERS: GROUP 9 TRUCK REPAIR PERSON/WELDER; LOW BED DRIVER, 9 AXLES OR OVER WORK ON ALL MILITARY BASES - $3.00 PER HOUR ADDITIONAL: [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, GEORGE AFB, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB] | 42.82 | 35.69 | 78.51 |
| TRUCK DRIVERS: GROUP 8 DUMP TRUCK, 25 YDS. TO 49 YDS. WATER LEVEL; TRUCK REPAIR PERSON; WATER PULL - SINGLE ENGINE; WELDER WORK ON ALL MILITARY BASES - $3.00 PER HOUR ADDITIONAL: [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, GEORGE AFB, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB] | 42.62 | 35.69 | 78.31 |
| TRUCK DRIVERS: GROUP 7 A Frame, Swedish crane or similar; Forklift driver; Ross carrier driver WORK ON ALL MILITARY BASES - $3.00 PER HOUR ADDITIONAL [29 palms Marine Base, Camp Roberts, China Lake, Edwards AFB, El Centro Naval Facility, Fort Irwin, George AFB, Marine Corps Logistics Base at Nebo & Yermo, Mountain Warfare Training Center, Bridgeport, Point Arguello, Point Conception, Vandenberg AFB] | 42.37 | 35.69 | 78.06 |
| TRUCK DRIVERS: GROUP 6 TRANSIT MIX TRUCK, 3 YDS OR MORE; DUMPCRETE TRUCK, 6-1/2 YDS. WATER LEVEL AND OVER; VEHICLE OR COMBINATION OF VEHICLES - 4 OR MORE AXLES; OIL SPREADER TRUCK; DUMP TRUCK, 16 YDS TO 25 YDS. WATER LEVEL WORK ON ALL MILITARY BASES - $3.00 PER HOUR ADDITIONAL: [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, GEORGE AFB, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB] | 42.12 | 35.69 | 77.81 |
| TRUCK DRIVERS: GROUP 5 WATER TRUCK, 3 OR MORE AXLES; TRUCK GREASER AND TIRE PERSON ($0.50 ADDITIONAL FOR TIRE PERSON); PIPELINE AND UTILITY WORKING TRUCK DRIVER, INCLUDING WINCH TRUCK AND PLASTIC FUSION, LIMITED TO PIPELINE AND UTILITY WORK; SLURRY TRUCK DRIVER WORK ON ALL MILITARY BASES - $3.00 PER HOUR ADDITIONAL: [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, GEORGE AFB, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB] | 42.09 | 35.69 | 77.78 |
| TRUCK DRIVERS: GROUP 4 DRIVER OF TRANSIT MIX TRUCK, UNDER 3 YDS.; DUMPCRETE TRUCK, LESS THAN 6-1/2 YDS. WATER LEVEL WORK ON ALL MILITARY BASES - $3.00 PER HOUR ADDITIONAL: [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, GEORGE AFB, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB] | 42.06 | 35.69 | 77.75 |
| TRUCK DRIVERS: GROUP 3 DRIVER OF VEHICLE OR COMBINATION OF VEHICLES - 3 AXLES; BOOT PERSON; CEMENT MASON DISTRIBUTION TRUCK; FUEL TRUCK DRIVER; WATER TRUCK - 2 AXLE; DUMP TRUCK, LESS THAN 16 YDS WATER LEVEL; EROSION CONTROL DRIVER WORK ON ALL MILITARY BASES - $3.00 PER HOUR ADDITIONAL: [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, GEORGE AFB, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB] | 41.87 | 35.69 | 77.56 |
| TRUCK DRIVERS: GROUP 2 DRIVER OF VEHICLE OR COMBINATION OF VEHICLES - 2 AXLES; TRAFFIC CONTROL PILOT CAR EXCLUDING MOVING HEAVY EQUIPMENT PERMIT LOAD; TRUCK MOUNTED BROOM WORK ON ALL MILITARY BASES - $3.00 PER HOUR ADDITIONAL: [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, GEORGE AFB, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB] | 41.74 | 35.69 | 77.43 |
| TRUCK DRIVERS: GROUP 1 TRUCK DRIVER WORK ON ALL MILITARY BASES - $3.00 PER HOUR ADDITIONAL: [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, GEORGE AFB, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB] | 41.59 | 35.69 | 77.28 |