Davis-Bacon Rate Lookupfree · sourced from sam.gov · no sign-up

Davis-Bacon rates — Brooke County, West Virginia

Every active general wage determination covering this county, one section per construction type. These rates are the minimum that must be paid on a federal or federally assisted contract.

Pick the construction type that matches your contract, not the highest rate. Building, Residential, Highway and Heavy are separate determinations with different rates, and using the wrong one is a common reason a certified payroll comes back rejected. Where your trade appears under several classifications the choice between them is a judgement call — the plainest match is usually right, and the contracting officer can confirm it.
Building
WV20260050 rev 1 · 05/18/2026 · 39 classifications
ClassificationBase rateFringeTotal
ASBESTOS WORKER/HEAT & FROST INSULATOR46.5029.4375.93
BOILERMAKER47.1328.9376.06
TILE SETTER31.6525.5657.21
BRICKLAYER (BRICKLAYER & BRICK POINTER/CAULKER/CLEANER)31.7025.9357.63
BRICKLAYER (BRICK REFRACTORY/BRICK PLACEMENT WORKER)32.6423.9556.59
MASON - STONE33.0026.1859.18
TILE FINISHER27.0022.5749.57
CARPENTER (INCLUDING BATT INSULATION, FORM WORK AND SCAFFOLD BUILDER)30.5126.0556.56
MILLWRIGHT37.4026.0663.46
ELECTRICIAN39.2531.2370.48
POWER EQUIPMENT OPERATOR: GROUP 4 BOBCAT/SKID STEER/SKID LOADER, FARM TYPE TRACTOR, LOADER34.7122.0556.76
POWER EQUIPMENT OPERATOR: GROUP 3 BULLDOZER, EXCAVATOR, FORKLIFT, NON-FARM TYPE TRACTOR, ALL OTHER CRANES, ALL OTHER MECHANICS45.2122.0567.26
POWER EQUIPMENT OPERATOR: GROUP 2 OPERATING CRANES AND TOWER CRANES WITH A LIFTING CAPACITY OF 15 TONS AND OVER46.2122.0568.26
POWER EQUIPMENT OPERATOR: GROUP 1 ALL FRICTION CRANES, TOWER CRANES AND ALL CRANES WITH 180 FT. OR MORE OF BOOM INCLUDING MAST AND JIBS OR LIFTING CAPACITY OF 100 TONS OR MORE AND HOISTS WITH 30,000 POUND LINE PULL OR MORE, MECHANICS WITH TOOLS WITH 3/4 INCH DRIVE AND BELOW46.5622.0568.61
IRONWORKER: ORNAMENTAL, REINFORCING, SHEETING AND STRUCTURAL35.1925.6660.85
LABORER: GROUP 4 FLAGGER24.9416.2041.14
LABORER: GROUP 3 PIPELAYER24.9416.2041.14
LABORER: GROUP 2 CHAIN SAW, CONCRETE SAW (HAND HELD/WALK BEHIND), DEWATERING, CONCRETE WORKER, FENCE ERECTION, GROUTING, MASON TENDER-BRICK, MASON TENDER-CEMENT/CONCRETE, RODMAN24.9416.2041.14
LABORER: GROUP 1 LANDSCAPE, COMMON OR GENERAL24.9416.2041.14
LABORER: ASPHALT RAKER, DEMOLITION, GRADE CHECKER, JACK HAMMER, MORTAR MIXER, PLASTER TENDER, SCAFFOLD BUILDER (BRICK AND MASONRY), SKYTRAK FORKLIFT OPERATOR, TAMPER (HAND HELD), WATER BOY25.9216.8842.80
PAINTER (BRUSH, ROLLER AND SPRAY)29.4718.7248.19
PAINTER: DRYWALL FINISHING/TAPING30.5720.0650.63
GLAZIER32.8913.3846.27
PLASTERER (EIFS AND FIREPROOFING)30.5022.2252.72
CEMENT MASON/CONCRETE FINISHER30.3822.8753.25
PLUMBER38.0439.7277.76
ROOFER34.0019.1153.11
SHEET METAL WORKER (INCLUDES HVAC DUCT INSTALLATION)34.9229.7064.62
PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION25.3219.9745.29
OPERATOR: ROLLER25.2416.1541.39
OPERATOR: BACKHOE21.517.3628.87
LABORER: WACKER ROLLER OPERATOR23.0711.0734.14
CARPENTER (DRYWALL HANGING ONLY)23.2312.1335.36
TRUCK DRIVER: GROUP 3 DUMP TRUCK (5 CU. YDS. & OVER), TRACTOR HAUL TRUCK, WATER TANK TRUCK (SEMI)29.9622.5052.46
TRUCK DRIVER: GROUP 2 DUMP TRUCK (UP TO 5 CU YDS.), WATER TANK TRUCK (STRAIGHT)29.8122.5052.31
LABORER: POWER TOOL OPERATOR22.8116.5039.31
LABORER: MOTORIZED BUGGY OPERATOR21.8316.0037.83
LABORER (CARPENTER TENDER)21.8616.0237.88
LABORER (BOBCAT OPERATOR- CLEANUP/DEMOLITION)21.8816.0337.91
Residential
WV20260001 rev 1 · 05/18/2026 · 7 classifications
ClassificationBase rateFringeTotal
ROOFER15.273.2018.47
PAINTER8.21—8.21
LABORER7.35—7.35
ELECTRICIAN10.601.5412.14
DRYWALL HANGER12.86—12.86
CARPENTER (EXCLUDING DRYWALL HANGING)8.36—8.36
BRICKLAYER9.29—9.29
Highway
WV20260109 rev 1 · 05/18/2026 · 26 classifications
ClassificationBase rateFringeTotal
CARPENTER33.8027.3461.14
TRAFFIC SIGNALIZATION: GROUNDSMAN22.1226.2648.38
OPERATOR: CRANE40.3520.3060.65
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE37.5920.3057.89
OPERATOR: BOBCAT/SKID STEER/SKID LOADER37.5920.3057.89
OPERATOR: BROOM/SWEEPER37.5920.3057.89
OPERATOR: BULLDOZER37.5920.3057.89
OPERATOR: DRILL37.5920.3057.89
OPERATOR: FORKLIFT37.5920.3057.89
OPERATOR: GRADER/BLADE37.5920.3057.89
OPERATOR: MILLING MACHINE37.5920.3057.89
OPERATOR: PAVER/SPREADER/FINISH EQUIPMENT(ASPHALT, AGGREGATE, & CONCRETE)37.5920.3057.89
OPERATOR: LOADER (UP TO SIX (6) CUBIC YARD CAPACITY)37.5920.3057.89
OPERATOR: MECHANIC37.5920.3057.89
OPERATOR: POST DRIVER (GUARDRAIL/FENCES)37.5920.3057.89
OPERATOR: ROLLER36.4820.3056.78
IRONWORKER35.5029.1164.61
LABORER: COMMON OR GENERAL29.0017.4046.40
TRAFFIC CONTROL PERSON27.9117.4045.31
LABORER: GRADE CHECKER29.0017.4046.40
LABORER: LASER SCREED OPERATOR30.0317.4047.43
LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR29.0017.4046.40
LABORER: PIPELAYER29.0017.4046.40
CEMENT MASON/CONCRETE FINISHER35.7727.5463.31
TRUCK DRIVER: DUMP TRUCK28.2216.1544.37
LABORER: MASON TENDER - CEMENT/CONCRETE26.7416.4043.14
Heavy
WV20260065 rev 1 · 05/18/2026 · 29 classifications
ClassificationBase rateFringeTotal
CARPENTER, INCLUDES FORM WORK33.8017.6151.41
ELECTRICIAN42.5037.2379.73
POWER EQUIPMENT OPERATOR: GROUP 3 ROLLER38.0820.4558.53
POWER EQUIPMENT OPERATOR: GROUP 2 BACKHOE, BULLDOZERS, COMPACTOR, FORKLIFT, GRADER/BLADE, MECHANIC, TRACTOR, TRENCHER39.1920.4559.64
POWER EQUIPMENT OPERATOR: GROUP 1 CRANES (ALL TYPES)41.9520.4562.40
IRONWORKER, ORNAMENTAL, REINFORCING AND STRUCTURAL35.5029.1164.61
LABORER: GROUP 2 CARPENTER TENDER, DEMOLITION, FLAGGER25.2616.5041.76
LABORER: GROUP 1 BOBCAT OPERATOR (CLEAN UP/DEMOLITION), CHAIN SAW, CONCRETE SAW(HAND HELD/WALK BEHIND), CONCRETE WORKER, HAND HELD DRILL, GRADE CHECKER, MASON TENDER-CEMENT/CONCRETE, PIPELAYER, WACKER ROLLER OPERATOR26.3216.5042.82
LABORER: TAMPER (HAND HELD)26.1716.7542.92
LABORER: JACK HAMMER26.1716.7542.92
LABORER: ASPHALT RAKER26.1716.7542.92
PAINTER: SPRAY34.4917.5352.02
CEMENT MASON/CONCRETE FINISHER35.7727.5463.31
TRUCK DRIVER, DUMP (EXCLUDING OFF THE ROAD TRUCKS)23.5011.4934.99
PIPEFITTER35.8619.3055.16
OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE)24.3915.5039.89
OPERATOR: OILER22.0314.6436.67
OPERATOR: LOADER23.4114.9538.36
OPERATOR: EXCAVATOR23.4114.9538.36
OPERATOR: BOOM28.7111.5940.30
OPERATOR: BOBCAT/SKID STEER/SKID LOADER24.7514.9439.69
LABORER: COMMON OR GENERAL21.5110.4531.96
TRUCK DRIVER: TRACTOR HAUL TRUCK31.7715.9847.75
TRUCK DRIVER: PICK-UP TRUCK30.0115.9845.99
TRUCK DRIVER: OFF THE ROAD TRUCK31.7715.9847.75
TRUCK DRIVER: FLATBED TRUCK30.9815.9846.96
LABORER: VIBRATING PLATE26.1716.5042.67
LABORER (MORTAR MIXER)26.1716.5042.67
POWER EQUIPMENT OPERATOR: DRILL35.1919.1854.37
Filing the WH-347 that these rates feed into? I build certified payroll tools, and I will prepare your first weekly filing from your payroll register free, with worker names removed — partly to be useful, partly because real registers are the only way to test the thing properly. hamza.aiemployee@gmail.com. No sign-up on this site, and nothing here is tracked.