| ASBESTOS WORKER/HEAT & FROST INSULATOR (MECHANICAL- DUCT, PIPE & MECHANICAL SYSTEM INSULATION) | 39.18 | 26.07 | 65.25 |
| BOILERMAKER | 55.00 | 35.48 | 90.48 |
| TILE SETTER | 35.13 | 16.52 | 51.65 |
| TILE FINISHER | 32.62 | 15.62 | 48.24 |
| MASON - STONE | 37.07 | 18.82 | 55.89 |
| BRICKLAYER (INCLUDING POINTING, CAULKING, AND CLEANING) | 37.07 | 18.82 | 55.89 |
| CARPENTER (INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, METAL STUD INSTALLATION, FLOOR LAYING-CARPET AND VINYL; EXCLUDES FORM WORK) | 36.57 | 20.04 | 56.61 |
| ELECTRICIAN (INCLUDING HVAC/TEMPERATURE CONTROLS AND LOW VOLTAGE WIRING) | 47.97 | 23.29 | 71.26 |
| ELECTRICIAN (INSTALLATION OF SOUND AND COMMUNICATION SYSTEMS ONLY) | 45.08 | 25.35 | 70.43 |
| ELEVATOR MECHANIC FOOTNOTES: A. VACATION CREDIT: EMPLOYER CONTRIBUTES 8% BASIC HOURLY RATE FOR 5 YEARS OR MORE OF SERVICE AS VACATION PAY CREDIT, AND 6% FOR 6 MONTHS TO 5 YEARS OF SERVICE B. EIGHT PAID HOLIDAYS (PROVIDED EMPLOYEE HAS WORKED 5 CONSECUTIVE DAYS BEFORE AND THE WORKING DAY AFTER THE HOLIDAY): NEW YEARS'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERAN'S DAY; THANKSGIVING DAY AND THE FRIDAY AFTER THANKSGIVING DAY, AND CHRISTMAS DAY | 61.41 | 38.44 | 99.85 |
| POWER EQUIPMENT OPERATOR (PUMP) | 29.58 | 20.15 | 49.73 |
| POWER EQUIPMENT OPERATOR: ROLLER | 35.72 | 26.72 | 62.44 |
| POWER EQUIPMENT OPERATOR: CRANE | 42.12 | 28.60 | 70.72 |
| POWER EQUIPMENT OPERATOR (OILER) | 34.40 | 26.32 | 60.72 |
| POWER EQUIPMENT OPERATOR (FORKLIFT (LULL OR SIMILAR, EXCLUDES MASONRY WORK)) | 39.59 | 27.85 | 67.44 |
| POWER EQUIPMENT OPERATOR (CONCRETE PUMP, FORKLIFT (UNDER 20 FT, EXCLUDES MASONRY WORK)) | 36.87 | 27.04 | 63.91 |
| POWER EQUIPMENT OPERATOR (BOBCAT/SKID STEER/SKID LOADER, BULLDOZER, HOIST, LOADER, MECHANIC, FORKLIFT (20 FT AND OVER, EXCLUDES MASONRY WORK)) | 39.59 | 27.85 | 67.44 |
| IRONWORKER (ORNAMENTAL, STRUCTURAL, & REINFORCING) | 37.26 | 32.63 | 69.89 |
| LABORER: COMMON OR GENERAL | 20.80 | 16.88 | 37.68 |
| LABORER (SCAFFOLD BUILDER (BRICK AND MASONRY ONLY)).$ 23.67 16.88 LABORER (MASON TENDER: BRICK, STONE) | 23.67 | 16.88 | 40.55 |
| LABORER (FORKLIFT (MASONRY WORK ONLY)) | 25.17 | 16.88 | 42.05 |
| LABORER (ASBESTOS ABATEMENT: REMOVAL FROM FLOORS, WALLS, CEILINGS AND MECHANICAL SYSTEMS) | 22.80 | 16.88 | 39.68 |
| PAINTER (BRUSH, ROLLER, SPRAY, AND DRYWALL FINISHING/TAPING) | 27.95 | 16.12 | 44.07 |
| CEMENT MASON/CONCRETE FINISHER | 37.13 | 14.30 | 51.43 |
| PLUMBER | 51.69 | 27.07 | 78.76 |
| PIPEFITTER (INCLUDES HVAC PIPE INSTALLATION) | 51.69 | 27.07 | 78.76 |
| ROOFER (EXCLUDES METAL ROOF INSTALLATION AND WATERPROOFING) | 34.25 | 21.89 | 56.14 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | 49.75 | 30.26 | 80.01 |
| SHEET METAL WORKER (INCLUDES HVAC DUCT AND METAL ROOF INSTALLATION) | 36.13 | 30.32 | 66.45 |
| TRUCK DRIVER: DUMP TRUCK | 23.36 | 7.60 | 30.96 |
| ROOFER: WATERPROOFING ONLY | 28.60 | 18.02 | 46.62 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | 33.01 | 18.37 | 51.38 |
| OPERATOR: GRADER/BLADE | 32.51 | 17.98 | 50.49 |
| OPERATOR: GRADALL | 32.70 | 18.43 | 51.13 |
| OPERATOR: DRILL | 28.55 | 15.78 | 44.33 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | 30.09 | 16.43 | 46.52 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | 27.89 | 19.81 | 47.70 |
| CARPENTER (FORM WORK ONLY) | 34.07 | 19.54 | 53.61 |
| LABORER: CONCRETE WORKER | 22.65 | 19.17 | 41.82 |