| ASBESTOS WORKER/HEAT & FROST INSULATOR (MECHANICAL- DUCT, PIPE & MECHANICAL SYSTEM INSULATION) | 39.18 | 26.07 | 65.25 |
| BOILERMAKER | 55.00 | 35.48 | 90.48 |
| MASON - STONE | 32.66 | 21.58 | 54.24 |
| BRICKLAYER (INCLUDING POINTING, CAULKING, AND CLEANING) | 32.66 | 21.58 | 54.24 |
| TILE FINISHER | 27.63 | 13.94 | 41.57 |
| TILE SETTER | 32.85 | 17.56 | 50.41 |
| CARPENTER (ACOUSTICAL CEILING INSTALLER ONLY) | 36.84 | 20.19 | 57.03 |
| CARPENTER (INCLUDES DRYWALL HANGING, METAL STUD INSTALLATION, FORM WORK AND SCAFFOLD BUILDING; EXCLUDES ACOUSTICAL CEILING INSTALLATION) | 36.84 | 20.19 | 57.03 |
| MILLWRIGHT | 43.00 | 23.44 | 66.44 |
| ELECTRICIAN (ALARM INSTALLATION, HVAC/TEMPERATURE CONTROLS INSTALLATION AND LOW VOLTAGE WIRING ONLY) | 41.00 | 31.06 | 72.06 |
| ELEVATOR MECHANIC FOOTNOTES: A. EMPLOYER CONTRIBUTES 8% OF BASIC HOURLY RATE FOR 5 YEARS OR MORE OF SERVICE AS VACATION PAY CREDIT, AND 6% OF BASIC HOURLY RATE FOR LESS THAN 5 YEARS OF SERVICE B. EIGHT PAID HOLIDAYS (PROVIDED EMPLOYEE HAS WORKED 5 CONSECUTIVE DAYS BEFORE AND THE WORKING DAY AFTER THE HOLIDAY): NEW YEARS'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY AND THE FRIDAY AFTER THANKSGIVING DAY, AND CHRISTMAS DAY | 58.70 | 38.44 | 97.14 |
| POWER EQUIPMENT OPERATOR (PUMP) | 28.36 | 18.10 | 46.46 |
| POWER EQUIPMENT OPERATOR: CRANE | 47.14 | 31.58 | 78.72 |
| POWER EQUIPMENT OPERATOR (OILER) | 39.42 | 29.30 | 68.72 |
| POWER EQUIPMENT OPERATOR (HOIST (SINGLE DRUM), FORKLIFT (UNDER 20 FT ,EXCLUDES MASONRY WORK)) | 41.88 | 30.03 | 71.91 |
| POWER EQUIPMENT OPERATOR (BACKHOE/ EXCAVATOR/ TRACKHOE, BOBCAT/ SKID/ STEER/ SKID LOADER, BULLDOZER, HOIST (WITH TWO TOWERS), MECHANIC, LOADER, FORKLIFT (20 FT AND OVER, EXCLUDES MASONRY WORK)) | 44.61 | 30.83 | 75.44 |
| IRONWORKER, STRUCTURAL | 37.26 | 32.63 | 69.89 |
| IRONWORKER (ORNAMENTAL & REINFORCING) | 37.26 | 32.63 | 69.89 |
| LABORER: MASON TENDER-BRICK | 26.91 | 17.18 | 44.09 |
| LABORER (FORKLIFT (MASONRY WORK ONLY)) | 28.41 | 17.18 | 45.59 |
| LABORER (COMMON OR GENERAL; CONCRETE SAW (WALK BEHIND/HAND HELD)) | 22.61 | 17.18 | 39.79 |
| PAINTER (BRUSH, ROLLER, SPRAY, AND DRYWALL FINISHING/TAPING) | 27.95 | 16.12 | 44.07 |
| PLUMBER | 41.36 | 29.45 | 70.81 |
| PIPEFITTER (INCLUDES HVAC PIPE AND HVAC UNIT INSTALLATION) | 41.36 | 29.45 | 70.81 |
| PLUMBER | 51.69 | 27.07 | 78.76 |
| ROOFER (EXCLUDES WATERPROOFING) | 40.33 | 32.62 | 72.95 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | 49.75 | 30.26 | 80.01 |
| SHEET METAL WORKER (INCLUDES HVAC DUCT AND SIDING INSTALLATION - METAL/ALUMINUM/VINYL) | 36.13 | 30.32 | 66.45 |
| TRUCK DRIVER: DUMP TRUCK | 23.36 | 7.60 | 30.96 |
| ROOFER: WATERPROOFING ONLY | 28.60 | 18.02 | 46.62 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | 33.01 | 18.37 | 51.38 |
| OPERATOR: GRADER/BLADE | 32.51 | 17.98 | 50.49 |
| OPERATOR: GRADALL | 32.70 | 18.43 | 51.13 |
| OPERATOR: DRILL | 28.55 | 15.78 | 44.33 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | 27.89 | 19.81 | 47.70 |
| CEMENT MASON/CONCRETE FINISHER | 32.66 | 21.32 | 53.98 |