| ASBESTOS WORKER/HEAT & FROST INSULATOR (INDUSTRIAL; MECHANICAL- DUCT, PIPE & MECHANICAL SYSTEM INSULATION) | 46.50 | 29.43 | 75.93 |
| BOILERMAKER | 48.28 | 33.17 | 81.45 |
| TILE FINISHER | 28.76 | 17.16 | 45.92 |
| TILE SETTER | 35.64 | 21.63 | 57.27 |
| BRICKLAYER (INCLUDING POINTING, CAULKING, CLEANING AND BRICK REFRACTORY WORK) | 32.79 | 23.32 | 56.11 |
| MASON - STONE | 32.79 | 23.32 | 56.11 |
| CARPENTER (FLOOR LAYING-CARPET ONLY) | 35.94 | 19.02 | 54.96 |
| CARPENTER (ACOUSTICAL CEILING INSTALLATION, FLOOR LAYING-HARDWOOD FLOORS AND VINYL ONLY) | 35.94 | 19.02 | 54.96 |
| MILLWRIGHT | 43.00 | 23.44 | 66.44 |
| CARPENTER (SCAFFOLD BUILDING ONLY) | 35.94 | 19.02 | 54.96 |
| ELECTRICIAN (INSTALLATION OF SOUND AND COMMUNICATION SYSTEM ONLY) | 49.11 | 36.79 | 85.90 |
| ELECTRICIAN (INCLUDING HVAC/TEMPERATURE CONTROLS, LOW VOLTAGE WIRING, ALARM INSTALLATION; EXCLUDING INSTALLATION OF SOUND AND COMMUNICATION SYSTEMS) | 51.45 | 29.77 | 81.22 |
| POWER EQUIPMENT OPERATOR BACKHOE/EXCAVATOR/TRACKHOE, BOBCAT/SKID STEER/SKID LOADER, LOADER, CRANE*, BULLDOZER *ADD TO CRANE RATE: BOOMS 101-150 JIBS- ADD $.75 BOOMS 151-200 JIBS- ADD $1.50 BOOMS 201-251 JIBS- ADD $2.25 | 36.87 | 21.32 | 58.19 |
| POWER EQUIPMENT OPERATOR: OILER | 29.70 | 21.32 | 51.02 |
| POWER EQUIPMENT OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE), DRILL RIG CAISSONS, BULLDOZER, FORKLIFT (LULL), MAN LIFT/OUTSIDE ELEVATOR | 36.87 | 21.32 | 58.19 |
| POWER EQUIPMENT OPERATOR: ROLLER, FORKLIFT (RIDDEN OR SELF-PROPELLED) | 32.25 | 21.32 | 53.57 |
| IRONWORKER, STRUCTURAL | 33.57 | 32.23 | 65.80 |
| IRONWORKER (REINFORCING AND METAL ROOF INSTALLATION ONLY) | 36.26 | 28.16 | 64.42 |
| LABORER (COMMON OR GENERAL; CONCRETE WORKER) | 26.82 | 19.39 | 46.21 |
| PAINTER (SPRAY ONLY, EXCLUDES WORK ON INDUSTRIAL SITES) | 27.95 | 16.12 | 44.07 |
| PAINTER (BRUSH AND ROLLER ONLY) | 30.56 | 23.72 | 54.28 |
| PAINTER (DRYWALL FINISHING/TAPING ONLY) | 32.39 | 23.26 | 55.65 |
| PAINTER: BRUSH AND ROLLER ONLY | 30.56 | 23.72 | 54.28 |
| PAINTER: DRYWALL FINISHING/TAPING ONLY | 32.39 | 23.26 | 55.65 |
| PAINTER (DRYWALL FINISHING/TAPING ONLY) | 27.10 | 18.02 | 45.12 |
| PAINTER: DRYWALL FINISHING/TAPING ONLY | 27.10 | 18.02 | 45.12 |
| PAINTER (INDUSTRIAL: SPRAY ONLY) | 36.01 | 23.72 | 59.73 |
| GLAZIER | 28.30 | 10.73 | 39.03 |
| CEMENT MASON/CONCRETE FINISHER | 31.77 | 21.89 | 53.66 |
| PLASTERER | 30.69 | 18.99 | 49.68 |
| PLUMBER | 46.98 | 25.47 | 72.45 |
| PIPEFITTER (INDUSTRIAL) | 47.75 | 26.55 | 74.30 |
| PIPEFITTER (EXCLUDES HVAC PIPE INSTALLATION AND WORK ON INDUSTRIAL SITES) | 40.02 | 26.55 | 66.57 |
| PIPEFITTER (HVAC PIPE INSTALLATION ONLY) | 48.15 | 29.17 | 77.32 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | 49.75 | 30.26 | 80.01 |
| CARPENTER (FORM WORK ONLY) | 24.75 | 9.48 | 34.23 |
| CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING AND METAL STUD INSTALLATION, FLOOR LAYER - CARPET, HARDWOOD, AND VINYL, FORM WORK AND SCAFFOLD BUILDING | 22.68 | 7.71 | 30.39 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | 18.41 | 6.45 | 24.86 |
| MECHANICAL INSULATOR, INCLUDING DUCT AND PIPE AND EXCLUDING WORK ON INDUSTRIAL SITES | 30.60 | 17.16 | 47.76 |
| ROOFER, EXCLUDES INSTALLATION OF METAL ROOFS | 22.98 | 11.86 | 34.84 |
| SHEET METAL WORKER (METAL FLASHING INSTALLATION ONLY) | 31.43 | 20.05 | 51.48 |
| TRUCK DRIVER: DUMP TRUCK | 24.98 | 11.88 | 36.86 |
| LABORER: MASON TENDER - BRICK | 23.23 | 18.53 | 41.76 |
| OPERATOR: MECHANIC | 36.53 | 22.01 | 58.54 |
| IRONWORKER: ORNAMENTAL | 34.91 | 30.85 | 65.76 |
| IRONWORKER, RIGGER | 35.22 | 30.56 | 65.78 |
| CARPENTER (DRYWALL HANGING AND METAL STUD INSTALLATION ONLY) | 35.94 | 19.02 | 54.96 |
| PAINTER (BRUSH AND ROLLER ONLY) | 28.84 | 24.30 | 53.14 |
| PAINTER: BRUSH AND ROLLER ONLY | 28.84 | 24.30 | 53.14 |