| ASBESTOS WORKER/HEAT & FROST INSULATOR - MECHANICAL (DUCT, PIPE & MECHANICAL SYSTEM INSULATION) | 43.00 | 29.81 | 72.81 |
| BOILERMAKER | 48.28 | 33.17 | 81.45 |
| MASON - STONE | 31.35 | 13.85 | 45.20 |
| BRICKLAYER (INCLUDING POINTING, CAULKING, AND CLEANING) | 31.35 | 13.85 | 45.20 |
| TILE SETTER | 35.64 | 21.63 | 57.27 |
| TILE FINISHER | 28.76 | 17.16 | 45.92 |
| CARPENTER (SCAFFOLD BUILDING AND FLOOR LAYING-HARDWOOD ONLY) | 33.01 | 18.09 | 51.10 |
| CARPENTER (INCLUDES ACOUSTICAL CEILING INSTALLATION, BATT INSULATION, DRYWALL HANGING, METAL STUD INSTALLATION, FLOOR LAYING-CARPET AND VINYL, FORM WORK AND GUTTER INSTALLATION; EXCLUDES SCAFFOLD BUILDING AND FLOOR LAYING-HARDWOOD FLOORS.) | 33.01 | 18.09 | 51.10 |
| MILLWRIGHT | 43.00 | 23.44 | 66.44 |
| ELECTRICIAN (INCLUDES ALARM INSTALLATION, INSTALLATION OF SOUND AND COMMUNICATION SYSTEM AND LOW VOLTAGE WIRING; EXCLUDES HVAC TEMPERATURE CONTROL INSTALLATION) | 50.86 | 31.78 | 82.64 |
| ELECTRICIAN (HVAC/TEMPERATURE CONTROLS INSTALLATION ONLY) | 40.00 | 27.42 | 67.42 |
| POWER EQUIPMENT OPERATOR: ROLLER | 32.25 | 21.32 | 53.57 |
| POWER EQUIPMENT OPERATOR: OILER | 29.70 | 21.32 | 51.02 |
| POWER EQUIPMENT OPERATOR: HOIST, PUMP | 29.70 | 21.32 | 51.02 |
| POWER EQUIPMENT OPERATOR: BOBCAT/SKID STEER/SKID LOADER, DRILL, GRADALL, GRADER/BLADE, PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | 36.87 | 21.32 | 58.19 |
| POWER EQUIPMENT OPERATOR BACKHOE/EXCAVATOR/TRACKHOE, BULLDOZER, CRANE* LOADER, MECHANIC) *ADD TO CRANE RATE BOOMS 101-150 JIBS- ADD $.75 BOOMS 151-200 JIBS- ADD $1.50 BOOMS 201-251 JIBS- ADD $2.25 | 36.87 | 21.32 | 58.19 |
| IRONWORKER: ORNAMENTAL, REINFORCING, RIGGER, AND STRUCTURAL | 32.29 | 32.41 | 64.70 |
| LABORER (MASON TENDER - CEMENT/CONCRETE) | 30.24 | 12.05 | 42.29 |
| LABORER: MASON TENDER-BRICK | 29.56 | 17.05 | 46.61 |
| PAINTER: BRUSH, ROLLER, AND SPRAY ONLY | 30.56 | 23.72 | 54.28 |
| PAINTER (DRYWALL FINISHING/TAPING ONLY) | 32.39 | 23.26 | 55.65 |
| GLAZIER | 25.40 | 25.47 | 50.87 |
| PLASTERER | 29.20 | 12.86 | 42.06 |
| PLUMBER (INDUSTRIAL) | 47.75 | 26.55 | 74.30 |
| PLUMBER (EXCLUDES WORK ON INDUSTRIAL SITES) | 41.36 | 29.45 | 70.81 |
| PIPEFITTER (INCLUDES HVAC PIPE INSTALLATION) | 41.36 | 29.45 | 70.81 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | 49.75 | 28.96 | 78.71 |
| SHEET METAL WORKER: HVAC DUCT INSTALLATION ONLY FOOTNOTE: PAID HOLIDAY: ELECTION DAY | 45.02 | 44.09 | 89.11 |
| TRUCK DRIVER: DUMP TRUCK | 23.36 | 7.60 | 30.96 |
| SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION.$ 32.03 22.87 ROOFER: WATERPROOFING ONLY | 29.50 | 21.10 | 50.60 |
| ROOFER, EXCLUDES WATERPROOFING | 33.50 | 22.10 | 55.60 |
| OPERATOR: FORKLIFT, ALL TYPES | 23.69 | 13.13 | 36.82 |
| LABORER: COMMON OR GENERAL | 18.55 | 9.67 | 28.22 |
| CEMENT MASON/CONCRETE FINISHER | 26.02 | 13.86 | 39.88 |