| BRICKLAYERS, STONE MASONS; CEMENT MASONS, PLASTERERS, POINTER, CLEANERS & CAULKERS: MADISON COUNTY (TOWNSHIPS OF SULLIVAN AND CAZENOVIA) (UTICA CHAPTER) | 38.30 | 23.71 | 62.01 |
| BRICKLAYERS, STONE MASONS; CEMENT MASONS, PLASTERERS, POINTER, CLEANERS & CAULKERS: MADISON COUNTY, (EXCLUDING TOWNSHIPS OF SULLIVAN AND CAZENOVIA) (UTICA CHAPTER) | 38.30 | 23.71 | 62.01 |
| MARBLE, TILE & TERRAZZO FINISHERS: MADISON COUNTY (TOWNSHIPS OF SULLIVAN AND CAZENOVIA) (UTICA CHAPTER) | 28.52 | 19.59 | 48.11 |
| MARBLE, TILE & TERRAZZO WORKERS: MADISON COUNTY (TOWNSHIPS OF SULLIVAN AND CAZENOVIA) (UTICA CHAPTER) | 35.85 | 20.37 | 56.22 |
| MARBLE, TILE & TERRAZZO WORKERS: MADISON COUNTY, (EXCLUDING TOWNSHIPS OF SULLIVAN AND CAZENOVIA) (UTICA CHAPTER) | 35.85 | 20.37 | 56.22 |
| AFTER THE HOLIDAY) | 37.23 | 19.51 | 56.74 |
| CARPENTER | 44.52 | 27.16 | 71.68 |
| CABLE SPLICER | 55.55 | 35.03 | 90.58 |
| ELECTRICIAN | 50.50 | 35.03 | 85.53 |
| THE HOLIDAY | 31.72 | 29.87 | 61.59 |
| ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN (TRUCK DRIVER) FOOTNOTE: A NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | 42.29 | 30.66 | 72.95 |
| OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | 47.57 | 31.03 | 78.60 |
| ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS LINEMAN & TECHNICIAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | 52.86 | 35.60 | 88.46 |
| THE HOLIDAY | 42.29 | 30.66 | 72.95 |
| ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES : LINEMAN AND TECHNICIAN FOOTNOTE A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | 61.56 | 36.21 | 97.77 |
| EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | 49.25 | 31.15 | 80.40 |
| ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUDING ANY AND ALL FIBER OPTIC GROUND PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES), PIPETYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS, AND MAINTENANCE BONDING OF RAILS; PIPETYPE CABLE INSTALLATION GROUNDMAN TRUCK DRIVER (TRACTOR-TRAILER UNIT) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | 49.25 | 31.15 | 80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Substation:) | 63.14 | 33.82 | 96.96 |
| ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | 64.59 | 42.92 | 107.51 |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | 35.34 | 30.12 | 65.46 |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Substation:) | 35.34 | 30.12 | 65.46 |
| fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | 35.34 | 30.12 | 65.46 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | 55.40 | 31.78 | 87.18 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Substation:) | 55.40 | 31.78 | 87.18 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab | 55.40 | 31.78 | 87.18 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | 49.25 | 31.15 | 80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat | 49.25 | 31.15 | 80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | 49.25 | 31.15 | 80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Substation:) | 49.25 | 31.15 | 80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Substation:) | 61.56 | 36.21 | 97.77 |
| ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins | 61.56 | 36.21 | 97.77 |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | 49.25 | 31.15 | 80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Substation:) | 49.25 | 31.15 | 80.40 |
| fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | 49.25 | 31.15 | 80.40 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | 40.81 | 6.99 | 47.80 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | 20.53 | 6.39 | 26.92 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | 38.73 | 6.93 | 45.66 |
| HYDRAULICALLY OPERATED) (GRADALL OR SIMILAR), FRONT END LOADER ( 4 CU. YD. AND OVER), HEAD TOWER (SAUERMAN OR EQUAL), HOIST (TWO OR THREE DRUM), HOLLAND LOADER, MAINTENANCE ENGINEER, MINE HOIST, MUCKING MACHINE OR MOLE PAVEMENT BREAKER(SP) WERTGEN; PB-4 AND SIMILAR TYPE, POWER GRADER, PROFILER (OVER 105 H.P.) QUAD 9, QUARRY MASTER (OR EQUIVALENT), SCRAPER, FIREMAN, FORK LIFT, FORM TAMPER, GROUT PUMP, GUNITE MACHINE, HAMMERS (HYDRAULIC SELF-PROPELLED), HYDRA-SPIKER, RIDE-ON, HYDRAULIC PUMP (JACKING SYSTEM), HYDRO-BLASTER (WATER), MULCHING MACHINE, OILER, PARAPET CONCRETE OR PAVEMENT, SHOVEL, SIDE BOOM, SLIP FORM PAVER, TRACTOR DRAWN, BELTTYPE LOADER, TRUCK OR TRAILER MOUNTED LOG , CHIPPER (SELF FEEDER), TUG OPERATOR (MANNED RENTED EQUIPMENT EXCLUDED), TUNNEL SHOVEL FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 55.85 | 33.40 | 89.25 |
| HOIST (ONE DRUM), HYDRO-AXE, KOLMAN PLANT LOADER AND SIMILAR TYPE LOADERS, L.C.M. WORK BOAT OPERATOR, LOCOMOTIVE MIXER (FOR STABILIZED BASE SELFPROPELLED), MONORAIL MACHINE, PLANT ENGINEER, PROFILER (105 H.P. AND UNDER), GRINDER, POST HOLE DIGGER AND POST DRIVER, POWER BROOM (TOWED), POWER HEATERMAN, POWER SWEEPER, REVINIUS WIDENER, ROLLER (GRADE AND FILL), SCARIFIER, RIDE-ON, SHELL WINDER, SKID STEER LOADER (BOBCAT OR SIMILAR), SPAN-SAW, RIDE-ON, STEAM CLEANER, PUG MILL, PUMP CRETE READY MIX CONCRETE PLANT REFRIGERATION EQUIPMENT (FOR SOIL STABILIZATION)ROAD WIDENER, ROLLER (ALL ABOVE SUBGRADE), SEA MULE, SELF-CONTAINED RIDE-ON ROCK DRILL, EXCLUDING AIR-TRACK TYPE DRILL, SKIDDER, TRACTOR WITH DOZER AND/OR PUSHER, TRENCHER. TUGGER HOIST, VERMEER SAW (RIDE ON, ANY SIZE OR TYPE), WINCH, WINCH CAT FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 54.97 | 33.40 | 88.37 |
| POWER EQUIPMENT OPERATORS: GROUP 3 | 51.69 | 33.40 | 85.09 |
| POWER EQUIPMENT OPERATORS: GROUP 4 TOWER CRANES FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 65.51 | 33.40 | 98.91 |
| POWER EQUIPMENT OPERATORS: GROUP 5 CRANES 50 TONS AND OVER FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 60.35 | 33.40 | 93.75 |
| POWER EQUIPMENT OPERATORS: GROUP 6 CRANES 49 TONS AND BELOW FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 58.85 | 33.40 | 92.25 |
| POWER EQUIPMENT OPERATORS: GROUP 7 MASTER MECHANIC FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | 57.20 | 33.40 | 90.60 |
| IRONWORKER: STRUCTURAL, ORNAMENTAL, REINFORCING, PRE-CAST CONCRETE ERECTOR, MACHINERY MOVER & RIGGER, FENCE ERECTOR, STONE DERRICKMAN WELDER, SHEETER, SHEETER BUCKER-UP (TOWNSHIPS OF CAZENOVIA, DERUYTER, FENNER, GEORGETOWN, LENOX, LINCOLN, NELSON, SMITHFIELD AND SULLIVAN) | 37.16 | 30.68 | 67.84 |
| IRONWORKER: STRUCTURAL, ORNAMENTAL, RODMAN, MACHINERY MOVER, RIGGER, FENCE ERECTOR, REINFORCEMENT, AND STONE DERRICKMAN (TOWNSHIPS OF BROOKFIELD, EATON, HAMILTON, LEBANON, MADISON, ONEIDA, AND STOCKBRIDGE) | 35.50 | 31.39 | 66.89 |
| LABORER GROUP 1 LABORER, FLAGMEN, OUTBOARD AND HAND BOATS FOOTNOTE: PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY | 28.05 | 23.74 | 51.79 |
| LABORER GROUP 2 BULL FLOAT, CHAIN SAW, CONCRETE AGGREGATE BIN, CONCRETE BOOTMAN, GIN BUGGY, HAND OR MACHINE VIBRATOR, JACK HAMMER, MASON TENDER, MORTAR MIXER, PAVEMENT BREAKER, HANDLERS OF ALL STEEL MESH, SMALL GENERATORS FOR LABORERS TOOLS, INSTALLATION OF BRIDGE DRAINAGE PIPE LAYERS, VIBRATOR TYPE ROLLERS, TAMPER, DRILL DOCTOR, TAIL OR SCREW OPERATOR ON ASPHALT PAVER, WATER PUMP OPERATOR (L-1/2"" AND SINGLE DIAPHRAGM), NOZZLE (ASPHALT, GUNNITE, SEEDING AND SAND BLASTING), LABORERS ON CHAIN LINK FENCE ERECTION, ROCK SPLITTER AND POWER UNIT, PUSHER TYPE CONCRET SAW AND ALL OTHER GAS, ELECTIC, OIL, AND AIR TOOL OPERATORS, WRECKING LABORERS. FOOTNOTE: PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY | 28.25 | 23.74 | 51.99 |
| LABORER GROUP 3 ALL ROCK OR DRILLING MACHINE OPERATORS (EXCEPT QUARRY MASTER AND SIMILAR TYPE) ACETYLENE TORCH OPERATORS, ASPHALT PAVER, POWDERMAN. FOOTNOTE: PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY | 28.45 | 23.74 | 52.19 |
| LABORER GROUP 4 BLASTERS, FORM SETTERS, STONE OR GRANITE CURB SETTERS. FOOTNOTE: PAID HOLIDAYS NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY | 28.65 | 23.74 | 52.39 |
| PAINTERS: (BRIDGES) | 42.06 | 30.59 | 72.65 |
| PLUMBER, INCLUDING STEAMFITTING (NORTHERN ZONE TOWNSHIPS OF BROOKFIELD, EATON, FENNER, HAMILTON, LEBANON, LENOX, LINCOLN, MADISON, NELSON, ONEIDA, SMITHFIELD, STOCKBRIDGE) | 45.93 | 33.77 | 79.70 |
| PLUMBER, INCLUDING STEAMFITTING (SOUTHERN ZONE TOWNSHIP OF GEORGETOWN) | 44.91 | 33.31 | 78.22 |
| PLUMBER, PIPEFITTER, STEAMFITTER: INCLUDING HVAC WORK (THE TOWNSHIPS WHICH ADJOIN THE EASTERN BORDERS OF ONONDAGA COUNTY) | 35.51 | 24.57 | 60.08 |
| ROOFER | 35.80 | 25.99 | 61.79 |
| SPRINKLER FITTER | 47.85 | 28.94 | 76.79 |
| SHEET METAL WORKER (PROJECTS 10 MILLION OR LESS) | 36.29 | 23.31 | 59.60 |
| SHEET METAL WORKER (PROJECTS OVER $10 MILLION) | 46.29 | 23.31 | 69.60 |
| GLAZIER | 15.76 | 2.80 | 18.56 |
| LABORER | 13.37 | 3.67 | 17.04 |
| PAINTER | 16.84 | 2.86 | 19.70 |
| POWER EQUIPMENT OPERATOR - BACKHOE | 19.08 | 7.50 | 26.58 |
| TRUCK DRIVER GROUP 1 PICKUPS, PANEL TRUCKS, FLATBOY MATERIAL TRUCKS (STRAIGHT JOBS), SINGLE-AXLE DUMP TRUCKS, DUPSTERS, RECEIVERS, GREASERS, TRUCK TIREMEN, TANDEMS AND BATCH TRUCKS, SEMI-TRAILERS, LOW-BOY TRUCKS, ASPHALT DISTRIBUTOR TRUCKS, & AGITATOR, MIXER TRUCKS & DUMPCRETE TYPE VEHICLES, FUEL TRUCKS FOOTNOTES: PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY PROVIDED EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY. WORK ON HAZARDOUS WASTE SITES RECEIVE ADDITIONAL $1.50/HR | 35.48 | 31.58 | 67.06 |
| TRUCK DRIVER GROUP 2 SPECIALIZED EARTH MOVING EQUIPMENT-EUCLID TYPE, OR SIMILAR OFF-HIGHWAY EQUIPMENT, WHERE NOT SELF LOADED,STRADDLE (ROSS) CARRIER, AND SELF-CONTAINED CONCRETE MOBILE UNIT, OFF-HIGHWAY TANDEM BACK-DUMP, TWIN ENGINE EUIPMENT AND DOUBLE-HITCHED EQUIPMENT WHERE NOT SELF LOADED FOOTNOTES: PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY PROVIDED EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY. WORK ON HAZARDOUS WASTE SITES RECEIVE ADDITIONAL $1.50/HR | 35.83 | 31.58 | 67.41 |