| ASBESTOS WORKER/HEAT & FROST INSULATOR | 34.69 | 22.84 | 57.53 |
| BRICKLAYER | 31.51 | 15.00 | 46.51 |
| TILE SETTER | 31.51 | 15.00 | 46.51 |
| CARPENTER (INCLUDING FORMWORK) | 32.59 | 21.85 | 54.44 |
| CARPENTER (FLOOR LAYER) (VINYL INSTALLATION ONLY) | 40.08 | 21.85 | 61.93 |
| ELECTRICIAN | 49.29 | 33.64 | 82.93 |
| ELEVATOR MECHANIC. FOOTNOTES: A) EMPLOYER CONTRIBUTES 8% OF REGULAR BASIC HOURLY RATE AS AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YEARS OF SERVICE, AND 6% FOR LESS THAN 5 YEARS OF SERVICE B) EIGHT PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY FRIDAY AFTER THANKSGIVING DAY, VETERANS' DAY AND CHRISTM | 62.73 | 38.44 | 101.17 |
| POWER EQUIPMENT OPERATOR: ROLLER | 39.06 | 30.38 | 69.44 |
| POWER EQUIPMENT OPERATOR: BULLDOZER | 39.06 | 30.38 | 69.44 |
| POWER EQUIPMENT OPERATOR BACKHOE/EXCAVATOR/TRACKHOE | 39.06 | 30.38 | 69.44 |
| POWER EQUIPMENT OPERATOR: (PAVER) | 39.06 | 30.38 | 69.44 |
| POWER EQUIPMENT OPERATOR: (LOADER) | 39.06 | 30.38 | 69.44 |
| IRONWORKER: REINFORCING AND STRUCTURAL | 34.47 | 24.85 | 59.32 |
| LABORER (BRICK MASON TENDER) | 30.48 | 14.91 | 45.39 |
| CEMENT MASON/CONCRETE FINISHER | 35.10 | 18.78 | 53.88 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATION (ON ANY WORK UNDER 7.0 MILLION TOTAL OF ALL PROJECT MECHANICAL CONTRACTS OUTSTATE AREA WAGES AND FRINGES) | 50.66 | 23.34 | 74.00 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATION (ON ANY WORK OVER $7.0 MILLION TOTAL OF ALL PROJECT MECHANICAL CONTRACTS ST. LOUIS AREA WAGES AND FRINGES.) | 52.60 | 29.93 | 82.53 |
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION (ON ANY WORK UNDER 7.0 MILLION TOTAL OF ALL PROJECT MECHANICAL CONTRACTS OUTSTATE AREA WAGES AND FRINGES) | 50.66 | 23.34 | 74.00 |
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION (ON ANY WORK OVER $7.0 MILLION TOTAL OF ALL PROJECT MECHANICAL CONTRACTS ST. LOUIS AREA WAGES AND FRINGES.) | 52.60 | 29.93 | 82.53 |
| ROOFER | 32.25 | 17.46 | 49.71 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | 45.94 | 27.53 | 73.47 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION | 52.00 | 27.12 | 79.12 |
| TRUCK DRIVER: DUMP TRUCK | 25.57 | — | 25.57 |
| PAINTER: SPRAY | 18.79 | 8.12 | 26.91 |
| PAINTER: ROLLER | 16.44 | 6.01 | 22.45 |
| PAINTER: BRUSH ONLY | 16.44 | 6.01 | 22.45 |
| OPERATOR: GRADER/BLADE | 22.80 | 10.78 | 33.58 |
| LABORER: COMMON OR GENERAL | 23.63 | 3.72 | 27.35 |