Davis-Bacon Rate Lookupfree · sourced from sam.gov · no sign-up

Davis-Bacon rates — Saginaw County, Michigan

Every active general wage determination covering this county, one section per construction type. These rates are the minimum that must be paid on a federal or federally assisted contract.

Pick the construction type that matches your contract, not the highest rate. Building, Residential, Highway and Heavy are separate determinations with different rates, and using the wrong one is a common reason a certified payroll comes back rejected. Where your trade appears under several classifications the choice between them is a judgement call — the plainest match is usually right, and the contracting officer can confirm it.
Building
MI20260097 rev 1 · 05/18/2026 · 41 classifications
ClassificationBase rateFringeTotal
ASBESTOS WORKER/HEAT & FROST INSULATOR40.0023.6563.65
BOILERMAKER43.5036.7480.24
HOLIDAY WITHIN THE CURRENT CALENDAR YEAR31.4321.1352.56
TILE FINISHER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER IS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR26.2421.1347.37
HOLIDAY WITHIN THE CURRENT CALENDAR YEAR33.0124.5457.55
HOLIDAY WITHIN THE CURRENT CALENDAR YEAR35.1424.2059.34
CARPENTER (INCLUDING ACOUSTICAL CEILING INSTALLATION & DRYWALL HANGING; EXCLUDING FORM WORK)35.8623.6959.55
LATHER24.2913.6637.95
ELECTRICIAN (EXCLUDING ALARM INSTALLATION)39.5025.0364.53
ELECTRICIAN (ALARM INSTALLATION)30.2515.0045.25
OPERATOR: POWER EQUIPMENT: GROUP 7 OILER FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY31.2325.2556.48
OPERATOR: POWER EQUIPMENT: GROUP 6 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) FOOTNOTES CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY33.7125.2558.96
DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY39.5725.2564.82
OPERATOR: POWER EQUIPMENT: GROUP 4 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK (OVER 20' LIFT) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY39.5725.2564.82
OPERATOR: POWER EQUIPMENT: GROUP 3 CONCRETE PUMP; CRANE; GRADER/BLADE; HIGHLIFT; HOIST; ROLLER; SCRAPER; STIFF LEG DERRICK; TRENCHER FOOTNOTES CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY41.2825.2566.53
OPERATOR: POWER EQUIPMENT: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER, TOWER CRANE, GANTRY CRANE, WHIRLEY DERRICK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY43.9325.2569.18
OPERATOR: POWER EQUIPMENT: GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER. FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY47.2825.2572.53
IRONWORKER: STRUCTURAL36.5535.9372.48
IRONWORKER: REINFORCING36.5533.3769.92
LABORER: LANDSCAPE AND IRRIGATION: GROUP 2 LANDSCAPE LABORER: SMALL POWER TOOL OPERATOR, MATERIAL MOVER, TRUCK DRIVER AND LAWN SPRINKLER INSTALLER TENDER27.719.1036.81
LABORER: LANDSCAPE AND IRRIGATION: GROUP 1 LANDSCAPE SPECIALIST, INCLUDING AIR, GAS AND DIESEL EQUIPMENT OPERATOR, LAWN SPRINKLER INSTALLER AND SKIDSTEER (OR EQUIVALENT)29.939.1039.03
LABORER: SANDBLASTER28.2113.4541.66
LABORER: COMMON OR GENERAL; GRADE CHECKER; MASON TENDER - BRICK/CEMENT/CONCRETE; PIPELAYER27.6813.4541.13
PAINTER: DRYWALL FINISHING/TAPING30.2222.2252.44
PAINTER: BRUSH AND SPRAY29.2319.1148.34
CEMENT MASON/CONCRETE FINISHER25.4712.3837.85
PLUMBER, EXCLUDES HVAC PIPE AND UNIT INSTALLATION46.0022.9968.99
PIPEFITTER, INCLUDES HVAC PIPE AND UNIT INSTALLATION46.0022.9968.99
ROOFER30.3819.8750.25
SPRINKLER FITTER (FIRE SPRINKLERS)41.3427.3968.73
SHEET METAL WORKER (INCLUDING HVAC DUCT INSTALLATION; EXCLUDING HVAC SYSTEM INSTALLATION)26.8323.7850.61
TRUCK DRIVER: TRACTOR HAUL TRUCK13.571.1814.75
TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK12.00—12.00
PAINTER: ROLLER22.026.0228.04
OPERATOR: LOADER17.62—17.62
OPERATOR: TRACTOR19.108.4827.58
OPERATOR: BULLDOZER17.508.6726.17
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE18.3113.8432.15
IRONWORKER, ORNAMENTAL18.487.9326.41
FLOOR LAYER: VINYL FLOORING16.813.7320.54
CARPENTER (FORM WORK ONLY)16.501.6518.15
Residential
MI20260021 rev 1 · 05/18/2026 · 17 classifications
ClassificationBase rateFringeTotal
ELECTRICIAN37.0023.1360.13
MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY44.0025.2569.25
OPERATOR: POWER EQUIPMENT: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER, TOWER CRANE, GANTRY CRANE, WHIRLEY DERRICK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY45.6825.2570.93
OPERATOR: POWER EQUIPMENT: GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER. FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY48.9825.2574.23
IRONWORKER, STRUCTURAL36.5535.9372.48
LABORER: COMMON OR GENERAL; MASON TENDER - CEMENT/CONCRETE27.6813.4541.13
PAINTER: BRUSH AND ROLLER21.8312.8034.63
PIPEFITTER (HVAC PIPE INSTALLATION ONLY)30.4510.6441.09
PLUMBER (EXCLUDING HVAC PIPE INSTALLATION)30.4510.6441.09
ROOFER30.3819.8750.25
SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION21.5411.9133.45
TRUCK DRIVER: DUMP TRUCK17.005.7122.71
OPERATOR: BOBCAT/SKID STEER/SKID LOADER17.667.6525.31
LABORER: PIPELAYER17.955.4623.41
LABORER: LANDSCAPE9.642.8112.45
CEMENT MASON/CONCRETE FINISHER19.275.8525.12
CARPENTER20.119.5029.61
Heavy
MI20260071 rev 1 · 05/18/2026 · 30 classifications
ClassificationBase rateFringeTotal
CARPENTER, INCLUDES FORM WORK35.8623.6959.55
ELECTRICIAN40.0029.9569.95
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 4 BROOM/ SWEEPER, FORK TRUCK, TRACTOR, BOBCAT/ SKID STEER /SKID LOADER39.9525.2565.20
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 3 BOOM TRUCK (NON-SWINGING, NON- POWERED TYPE BOOM)40.5225.2565.77
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 2 TRENCHER (8-FT DIGGING CAPACITY AND SMALLER)41.2525.2566.50
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 1 BACKHOE/ EXCAVATOR, BORING MACHINE, BULLDOZER, CRANE, GRADER/ BLADE, LOADER, ROLLER, SCRAPER, TRENCHER (OVER 8 FT DIGGING CAPACITY)45.9825.2571.23
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 6 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY35.4625.2560.71
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 5 BOOM TRUCK (NON-SWINGING) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY41.3225.2566.57
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 4 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK (OVER 20' LIFT) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY41.3225.2566.57
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 3 BACKHOE/EXCAVATOR; BORING MACHINE; BULLDOZER; CRANE; GRADER/BLADE; LOADER; ROLLER; SCRAPER; TRACTOR; TRENCHER FOOTNOTES CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY44.0025.2569.25
MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY45.6825.2570.93
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER. FOOTNOTES CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY48.9825.2574.23
IRONWORKER: STRUCTURAL36.5535.9372.48
IRONWORKER: REINFORCING36.5533.3769.92
LABORER ((7) LANDSCAPER)18.4112.9531.36
LABORER ((5) PIPELAYER)22.8512.9535.80
LABORER ((4) GRADE CHECKER)22.7312.5535.28
LABORER ((2) MASON TENDER-CEMENT/CONCRETE)22.5512.9535.50
LABORER ((1) COMMON OR GENERAL)22.4212.9535.37
LANDSCAPE LABORER, EXCLUDES OPEN CUT CONSTRUCTION GROUP 2 LANDSCAPE LABORER: SMALL POWER TOOL OPERATOR, MATERIAL MOVER, TRUCK DRIVER AND LAWN SPRINKLER INSTALLER TENDER27.719.1036.81
LANDSCAPE LABORER, EXCLUDES OPEN CUT CONSTRUCTION GROUP 1 LANDSCAPE SPECIALIST, INCLUDING AIR, GAS AND DIESEL EQUIPMENT OPERATOR, LAWN SPRINKLER INSTALLER AND SKIDSTEER (OR EQUIVALENT)29.939.1039.03
LABORER: COMMON OR GENERAL; GRADE CHECKER; MASON TENDER - CEMENT/CONCRETE; PIPELAYER (EXCLUDES OPEN CUT CONSTRUCTION)27.6813.4541.13
PAINTER: SPRAY23.5812.8036.38
PAINTER: BRUSH & ROLLER22.5812.8035.38
CEMENT MASON/CONCRETE FINISHER25.4712.3837.85
PLUMBER38.2521.0759.32
TRUCK DRIVER: OFF THE ROAD TRUCK20.823.6924.51
TRUCK DRIVER: LOWBOY/SEMI-TRAILER TRUCK FOOTNOTE: A. $470.70 PER WEEK. B. $68.70 DAILY33.550.7534.30
TRUCK DRIVER: DUMP TRUCK, 8 CU. YDS. AND OVER33.400.7534.15
TRUCK DRIVER: DUMP TRUCK UNDER 8 CU. YDS.; TRACTOR HAUL TRUCK FOOTNOTE: A. $470.70 PER WEEK. B $68.70 DAILY33.300.7534.05
Filing the WH-347 that these rates feed into? I build certified payroll tools, and I will prepare your first weekly filing from your payroll register free, with worker names removed — partly to be useful, partly because real registers are the only way to test the thing properly. hamza.aiemployee@gmail.com. No sign-up on this site, and nothing here is tracked.