Every active general wage determination covering this county, one section per construction type. These rates are the minimum that must be paid on a federal or federally assisted contract.
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | 40.00 | 23.65 | 63.65 |
| BOILERMAKER | 43.50 | 36.74 | 80.24 |
| TILE SETTER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER HAS BEEN EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | 32.20 | 23.46 | 55.66 |
| TILE FINISHER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER HAS BEEN EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | 27.94 | 21.15 | 49.09 |
| BRICKLAYER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER HAS BEEN EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | 35.83 | 22.18 | 58.01 |
| CARPENTER (INCLUDING FORM WORK; EXCLUDING DRYWALL HANGING) | 31.50 | 21.15 | 52.65 |
| OPERATOR: POWER EQUIPMENT: GROUP 5 OILER PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 31.23 | 25.25 | 56.48 |
| OPERATOR: POWER EQUIPMENT: GROUP 4 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) PAID HOLIDAYS NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 33.71 | 25.25 | 58.96 |
| OPERATOR: POWER EQUIPMENT: GROUP 3 BOOM TRUCK (NON-SWINGING) PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 39.57 | 25.25 | 64.82 |
| OPERATOR: POWER EQUIPMENT: GROUP 2 BROOM/SWEEPER; FORK TRUCK (OVER 20' LIFT) PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 39.57 | 25.25 | 64.82 |
| OPERATOR: POWER EQUIPMENT: GROUP 1 BACKHOE/EXCAVATOR/TRACKHOE; CONCRETE PUMP; GRADER/BLADE; HIGHLIFT; HOIST; ROLLER; SCRAPER; TRENCHER PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 41.28 | 25.25 | 66.53 |
| IRONWORKER: STRUCTURAL | 36.55 | 29.51 | 66.06 |
| IRONWORKER: REINFORCING | 36.55 | 29.51 | 66.06 |
| LABORER: COMMON OR GENERAL; GRADE CHECKER; MASON TENDER - BRICK; SANDBLASTER | 28.56 | 12.95 | 41.51 |
| PAINTER: BRUSH AND SPRAY | 28.75 | 18.68 | 47.43 |
| CEMENT MASON/CONCRETE FINISHER | 21.15 | 12.78 | 33.93 |
| PLUMBER, EXCLUDES HVAC PIPE AND UNIT INSTALLATION | 47.40 | 23.35 | 70.75 |
| PIPEFITTER (INCLUDING HVAC PIPE INSTALLATION; EXCLUDING HVAC SYSTEM INSTALLATION) | 47.40 | 23.35 | 70.75 |
| ROOFER | 32.65 | 14.80 | 47.45 |
| SHEET METAL WORKER, EXCLUDES HVAC DUCT AND UNIT INSTALLATION | 35.41 | 15.86 | 51.27 |
| TRUCK DRIVER: TRACTOR HAUL TRUCK | 13.57 | 1.18 | 14.75 |
| TRUCK DRIVER: DUMP TRUCK | 17.00 | 5.71 | 22.71 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | 16.70 | 4.02 | 20.72 |
| SHEET METAL WORKER (HVAC DUCT INSTALLATION ONLY) | 19.05 | 6.51 | 25.56 |
| PAINTER: ROLLER | 17.28 | 3.43 | 20.71 |
| OPERATOR: LOADER | 16.38 | 3.44 | 19.82 |
| OPERATOR: TRACTOR | 15.72 | 1.92 | 17.64 |
| OPERATOR: CRANE | 19.13 | 7.02 | 26.15 |
| OPERATOR: BULLDOZER | 17.56 | 4.95 | 22.51 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | 14.96 | 4.01 | 18.97 |
| LABORER: PIPELAYER | 18.32 | 3.28 | 21.60 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | 14.82 | 3.59 | 18.41 |
| LABORER: LANDSCAPE & IRRIGATION | 8.93 | 1.62 | 10.55 |
| IRONWORKER, ORNAMENTAL | 18.48 | 7.93 | 26.41 |
| HVAC MECHANIC (LOW VOLTAGE WIRING AND INSTALLATION OF HVAC TEMPERATURE CONTROLS) | 21.32 | 8.01 | 29.33 |
| HVAC MECHANIC (INSTALLATION OF HVAC UNIT ONLY, EXCLUDES INSTALLATION OF HVAC PIPE AND DUCT) | 18.92 | 4.71 | 23.63 |
| ELECTRICIAN, EXCLUDES LOW VOLTAGE WIRING AND INSTALLATION OF HVAC/TEMPERATURE CONTROLS | 22.69 | 9.10 | 31.79 |
| CARPENTER (DRYWALL HANGING ONLY) | 17.26 | 2.69 | 19.95 |
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| OPERATOR: POWER EQUIPMENT: BACKHOE/EXCAVATOR; BULLDOZER; GRADER/BLADE; LOADER; SCRAPER PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | 41.28 | 25.25 | 66.53 |
| IRONWORKER, STRUCTURAL | 36.55 | 29.51 | 66.06 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | 23.34 | 11.60 | 34.94 |
| PAINTER: BRUSH AND ROLLER | 21.84 | 18.63 | 40.47 |
| PLUMBER (EXCLUDING HVAC PIPE INSTALLATION) | 37.09 | 22.52 | 59.61 |
| PIPEFITTER (HVAC PIPE INSTALLATION ONLY) | 39.89 | 23.82 | 63.71 |
| ROOFER | 32.65 | 14.80 | 47.45 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION | 21.44 | 11.44 | 32.88 |
| TRUCK DRIVER: DUMP TRUCK | 17.00 | 5.71 | 22.71 |
| OPERATOR: CRANE | 18.50 | 5.10 | 23.60 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | 17.66 | 7.65 | 25.31 |
| LABORER: PIPELAYER | 17.95 | 5.46 | 23.41 |
| LABORER: LANDSCAPE | 9.64 | 2.81 | 12.45 |
| LABORER: COMMON OR GENERAL | 13.03 | 4.65 | 17.68 |
| ELECTRICIAN | 20.18 | 4.96 | 25.14 |
| CEMENT MASON/CONCRETE FINISHER | 16.13 | 3.47 | 19.60 |
| CARPENTER | 17.71 | 5.58 | 23.29 |
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| CARPENTER, INCLUDES FORM WORK | 31.50 | 21.15 | 52.65 |
| ELECTRICIAN | 36.52 | 25.15 | 61.67 |
| POWER EQUIPMENT OPERATOR, UNDERGROUND CONSTRUCTION (INCLUDING SEWER): GROUP 4 BROOM/ SWEEPER, FORK TRUCK, TRACTOR, BOBCAT/ SKID STEER /SKID LOADER | 39.95 | 25.25 | 65.20 |
| POWER EQUIPMENT OPERATOR, UNDERGROUND CONSTRUCTION (INCLUDING SEWER): GROUP 3 BOOM TRUCK (NON-SWINGING, NON- POWERED TYPE BOOM) | 40.52 | 25.25 | 65.77 |
| POWER EQUIPMENT OPERATOR, UNDERGROUND CONSTRUCTION (INCLUDING SEWER): GROUP 2 TRENCHER (8-FT DIGGING CAPACITY AND SMALLER) | 41.25 | 25.25 | 66.50 |
| POWER EQUIPMENT OPERATOR, UNDERGROUND CONSTRUCTION (INCLUDING SEWER): GROUP 1 BORING MACHINE, ROLLER, SCRAPER, TRENCHER (OVER 8 FT. DIGGING CAPACITY) | 45.98 | 25.25 | 71.23 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 4 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. SWING BOOM TRUCK OPERATOR OVER 12 TONS-$.50 PER HOUR | 35.46 | 25.25 | 60.71 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 3 BOOM TRUCK (NON-SWINGING) PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. SWING BOOM TRUCK OPERATOR OVER 12 TONS-$.50 PER HOUR | 41.32 | 25.25 | 66.57 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 2 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK (OVER 20' LIFT) PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. SWING BOOM TRUCK OPERATOR OVER 12 TONS-$.50 PER HOUR | 41.32 | 25.25 | 66.57 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 1 BORING MACHINE; ROLLER; SCRAPER; TRACTOR; TRENCHER PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. SWING BOOM TRUCK OPERATOR OVER 12 TONS-$.50 PER HOUR | 44.00 | 25.25 | 69.25 |
| IRONWORKER: STRUCTURAL | 36.55 | 34.04 | 70.59 |
| IRONWORKER: REINFORCING | 36.55 | 34.04 | 70.59 |
| LABORER ((4) GRADE CHECKER) | 22.73 | 12.95 | 35.68 |
| LABORER ((2) MASON TENDER-CEMENT/CONCRETE) | 22.55 | 12.95 | 35.50 |
| LABORER ((1) COMMON OR GENERAL) | 22.42 | 12.95 | 35.37 |
| LABORER (COMMON OR GENERAL; GRADE CHECKER; MASON TENDER - CEMENT/CONCRETE) (EXCLUDES OPEN CUT CONSTRUCTION) | 24.55 | 13.45 | 38.00 |
| PAINTER: BRUSH, ROLLER AND SPRAY | 21.89 | 11.85 | 33.74 |
| CEMENT MASON/CONCRETE FINISHER | 21.15 | 12.78 | 33.93 |
| PLUMBER | 39.80 | 23.82 | 63.62 |
| TRUCK DRIVER: TRACTOR HAUL TRUCK | 16.50 | 4.89 | 21.39 |
| TRUCK DRIVER: OFF THE ROAD TRUCK | 20.82 | 3.69 | 24.51 |
| TRUCK DRIVER: DUMP TRUCK | 17.00 | 5.71 | 22.71 |
| OPERATOR: LOADER | 17.52 | 5.51 | 23.03 |
| OPERATOR: GRADER/BLADE | 16.64 | — | 16.64 |
| OPERATOR: CRANE | 18.50 | 5.10 | 23.60 |
| OPERATOR: BULLDOZER | 20.48 | 6.14 | 26.62 |
| OPERATOR: BACKHOE/EXCAVATOR | 20.94 | 8.15 | 29.09 |
| LABORER: PIPELAYER | 15.54 | 4.16 | 19.70 |
| LABORER: LANDSCAPE | 12.21 | 1.96 | 14.17 |
| TRUCK DRIVER: LOWBOY/SEMI-TRAILER TRUCK FOOTNOTE: A. $470.70 PER WEEK. B. $68.70 DAILY | 33.55 | 0.75 | 34.30 |