Every active general wage determination covering this county, one section per construction type. These rates are the minimum that must be paid on a federal or federally assisted contract.
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| BRICKLAYER | 30.00 | 17.78 | 47.78 |
| ELECTRICIAN | 40.00 | 18.74 | 58.74 |
| IRONWORKER, STRUCTURAL | 33.37 | 22.98 | 56.35 |
| LABORER:MASON TENDER-CEMENT/CONCRETE | 33.93 | 16.50 | 50.43 |
| PLUMBER | 39.90 | 18.67 | 58.57 |
| ROOFER | 29.02 | 19.90 | 48.92 |
| SHEET METAL WORKER (EXCLUDES HVAC DUCT INSTALLATION) | 39.20 | 23.59 | 62.79 |
| TRUCK DRIVER: DUMP TRUCK | 17.82 | 2.18 | 20.00 |
| PAINTER: BRUSH, ROLLER AND SPRAY | 16.12 | — | 16.12 |
| OPERATOR: CRANE | 27.29 | 10.53 | 37.82 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | 18.96 | 4.42 | 23.38 |
| LABORER: TAMPER (HAND HELD) | 15.00 | 5.00 | 20.00 |
| LABORER: PIPELAYER | 14.26 | — | 14.26 |
| LABORER: COMMON OR GENERAL | 14.82 | — | 14.82 |
| HVAC MECHANIC: DUCT INSTALLATION | 23.63 | 6.63 | 30.26 |
| CEMENT MASON/CONCRETE FINISHER | 14.76 | 2.80 | 17.56 |
| CARPENTER | 21.44 | — | 21.44 |
| TRUCK DRIVER: GROUP 3 WATER TRUCK | 35.00 | 17.00 | 52.00 |
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| POWER EQUIPMENT OPERATORS: (BACKHOE) | 8.36 | 1.42 | 9.78 |
| PLUMBER | 12.92 | — | 12.92 |
| LABORER | 7.25 | 1.02 | 8.27 |
| INSULATION MECHANIC | 9.99 | — | 9.99 |
| ELECTRICIAN | 9.45 | — | 9.45 |
| CEMENT MASON/CONCRETE FINISHER | 7.25 | 1.20 | 8.45 |
| CARPENTER | 9.09 | — | 9.09 |
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN | 40.00 | 18.74 | 58.74 |
| POWER EQUIPMENT OPERATOR: GROUP 7 MECHANIC ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES $35.00/PER DAY. IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE | 37.35 | 16.10 | 53.45 |
| CEMENT MASON/CONCRETE FINISHER (ZONE 1) ZONE DIFFERENTIAL (ADD TO ZONE 1 RATE): ZONE 2 - $3.00 BASE POINTS: SPOKANE, PASCO, LEWISTON, WENATCHEE ZONE 1: 0-45 RADIUS MILES FROM THE MAIN POST OFFICE ZONE 2: OVER 45 RADIUS MILES FROM THE MAIN POST OFFICE | 40.89 | 18.64 | 59.53 |
| TRUCK DRIVER: WATER TRUCK | 21.61 | 13.05 | 34.66 |
| TRUCK DRIVER: OIL DISTRIBUTOR TRUCK | 22.54 | 12.35 | 34.89 |
| TRUCK DRIVER: LOWBOY TRUCK | 21.53 | 12.98 | 34.51 |
| TRUCK DRIVER: DUMP TRUCK | 21.19 | 13.30 | 34.49 |
| TRUCK DRIVER: DISTRIBUTOR TRUCK | 21.35 | 13.05 | 34.40 |
| TRAFFIC CONTROL: LABORER-CONES/ BARRICADES/BARRELS - SETTER/MOVER/SWEEPER | 22.66 | 10.90 | 33.56 |
| TRAFFIC CONTROL: FLAGGER | 22.68 | 10.90 | 33.58 |
| OPERATOR: SCREED | 25.63 | 10.34 | 35.97 |
| OPERATOR: ROTOMILL | 26.54 | 10.00 | 36.54 |
| OPERATOR: ROLLER (SUBGRADE) | 22.24 | 8.57 | 30.81 |
| OPERATOR: ROLLER | 25.47 | 10.32 | 35.79 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | 25.67 | 10.56 | 36.23 |
| OPERATOR: OILER | 25.66 | 9.23 | 34.89 |
| OPERATOR: LOADER | 25.78 | 10.17 | 35.95 |
| OPERATOR: HYDROSEEDER | 24.76 | 11.51 | 36.27 |
| OPERATOR: GRADER/BLADE | 26.14 | 10.69 | 36.83 |
| OPERATOR: CRUSHER | 25.06 | 9.23 | 34.29 |
| OPERATOR: CRANE | 26.04 | 10.00 | 36.04 |
| OPERATOR: BULLDOZER | 26.19 | 9.60 | 35.79 |
| OPERATOR: BROOM/SWEEPER | 25.01 | 10.16 | 35.17 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | 25.35 | 11.55 | 36.90 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | 25.80 | 10.00 | 35.80 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | 23.69 | 10.97 | 34.66 |
| LABORER: GRADE CHECKER | 23.45 | 10.97 | 34.42 |
| LABORER: CONCRETE SAW (HAND HELD/WALK BEHIND) | 23.98 | 11.05 | 35.03 |
| LABORER: COMMON OR GENERAL | 23.19 | 11.00 | 34.19 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | 23.13 | 11.01 | 34.14 |
| HIGHWAY/PARKING LOT STRIPING: PAINTER | 26.38 | 7.89 | 34.27 |
| CARPENTER (FORM WORK ONLY) | 26.57 | 8.10 | 34.67 |
| Classification | Base rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN | 40.00 | 18.74 | 58.74 |
| POWER EQUIPMENT OPERATOR: GROUP 8 BULLDOZER, SCRAPER (OVER 80 YDS TO 100 YDS) ZONE PAY ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES $30.00/PER DAY ZONE 3 MORE THAN 60 MILES $35.00/PER DAY. IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE. BOOM PAY: ALL CRANES AND CONCRETE PUMP BOOM TRUCKS 100 FT TO 150 FT $.15 OVER SCALE 150 FT TO 200 FT $.30 OVER SCALE OVER 200 FT $.45 OVER SCALE | 37.58 | 16.10 | 53.68 |
| N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE. BOOM PAY: ALL CRANES AND CONCRETE PUMP BOOM TRUCKS 100 FT TO 150 FT $.15 OVER SCALE 150 FT TO 200 FT $.30 OVER SCALE OVER 200 FT $.45 OVER SCALE | 37.35 | 16.10 | 53.45 |
| apply ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE BOOM PAY: All Cranes and Concrete Pump Boom Trucks 100 ft to 150 ft $.15 over scale 150 ft to 200 ft $.30 over scale Over 200 ft $.45 over scale | 36.98 | 16.10 | 53.08 |
| POWER EQUIPMENT OPERATOR: GROUP 3 ROLLER ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES $35.00/PER DAY. IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE | 36.33 | 16.10 | 52.43 |
| 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE | 38.06 | 16.10 | 54.16 |
| IRONWORKER, STRUCTURAL | 33.37 | 22.98 | 56.35 |
| LABORER: GROUP 3 ASPHALT INCLUDING RAKER, SHOVELER, SPREADER, AND DISTRIBUTOR | 33.83 | 16.50 | 50.33 |
| LABORER: GROUP 1 FLAGGER | 33.63 | 16.50 | 50.13 |
| TRUCK DRIVER: WATER TRUCK | 23.89 | 9.52 | 33.41 |
| TRUCK DRIVER: LOWBOY TRUCK | 21.00 | 12.10 | 33.10 |
| TRUCK DRIVER: DUMP TRUCK | 17.11 | — | 17.11 |
| PAINTER: ROLLER AND SPRAY | 17.06 | 0.65 | 17.71 |
| OPERATOR: CONCRETE BATCH PLANT | 24.94 | 11.96 | 36.90 |
| OPERATOR: LOADER (FRONT END) | 21.33 | 4.25 | 25.58 |
| OPERATOR: GRADER/BLADE | 25.17 | 9.44 | 34.61 |
| OPERATOR: FORKLIFT | 21.98 | — | 21.98 |
| OPERATOR: CRANE | 27.59 | 9.60 | 37.19 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | 17.00 | — | 17.00 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | 21.06 | — | 21.06 |
| LABORER: PIPELAYER | 16.39 | — | 16.39 |
| LABORER: COMMON OR GENERAL | 22.13 | 11.98 | 34.11 |
| IRONWORKER, REINFORCING | 27.22 | 16.70 | 43.92 |
| CEMENT MASON/CONCRETE FINISHER | 17.16 | 5.67 | 22.83 |
| CARPENTER, EXCLUDES FORM WORK | 28.00 | — | 28.00 |
| CARPENTER (FORM WORK ONLY) | 28.00 | — | 28.00 |