| ASBESTOS WORKERS/INSULATOR: INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS, AND FINISHES TO ALL TYPES OF MECHANICAL SYSTEMS (AREA 2) | 64.56 | 25.07 | 89.63 |
| ASBESTOS WORKERS/INSULATOR: INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS, AND FINISHES TO ALL TYPES OF MECHANICAL SYSTEMS (AREA 1) | 84.76 | 25.07 | 109.83 |
| ASBESTOS REMOVAL WORKER/HAZARDOUS MATERIAL HANDLER INCLUDES PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPPING, VACUUMING, BAGGING AND DISPOSING OF ALL INSULATION MATERIALS FROM MECHANICAL SYSTEMS, WHETHER THEY CONTAIN ASBESTOS OR NOT (AREA 2) | 44.73 | 12.75 | 57.48 |
| ASBESTOS REMOVAL WORKER/HAZARDOUS MATERIAL HANDLER INCLUDES PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPPING, VACUUMING, BAGGING AND DISPOSING OF ALL INSULATION MATERIALS FROM MECHANICAL SYSTEMS, WHETHER THEY CONTAIN ASBESTOS OR NOT (AREA 1) | 35.31 | 12.75 | 48.06 |
| BOILERMAKER: (2) REMAINING COUNTIES | 45.60 | 38.99 | 84.59 |
| BOILERMAKER: (1) MARIN & SOLANO COUNTIES | 49.62 | 41.27 | 90.89 |
| MARBLE FINISHER | 42.06 | 19.80 | 61.86 |
| BRICKLAYER (AREA 2) | 57.02 | 28.50 | 85.52 |
| BRICKLAYER (AREA 1) | 52.76 | 25.01 | 77.77 |
| TERRAZZO WORKER/SETTER | 60.58 | 29.79 | 90.37 |
| TERRAZZO FINISHER | 44.93 | 20.98 | 65.91 |
| TILE LAYER AREA 4: SONOMA | 56.79 | 22.54 | 79.33 |
| TILE LAYER AREA 3: MARIN, NAPA, SOLANO, SISKIYOU | 59.92 | 22.62 | 82.54 |
| TILE LAYER AREA 2: ALPINE, AMADOR | 55.17 | 22.52 | 77.69 |
| TILE LAYER AREA 1: BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SUTTER, TEHEMA, YOLO, YUBA | 55.55 | 21.08 | 76.63 |
| TILE FINISHER AREA 2: ALPINE, AMADOR | 34.76 | 19.22 | 53.98 |
| TILE FINISHER AREA 4: SONOMA | 35.78 | 19.23 | 55.01 |
| TILE FINISHER AREA 3: MARIN, NAPA, SOLANO, SISKIYOU | 37.75 | 19.28 | 57.03 |
| TILE FINISHER AREA 1: BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SUTTER, TEHEMA, YOLO, YUBA | 35.00 | 17.44 | 52.44 |
| MARBLE MASON | 61.72 | 30.31 | 92.03 |
| DIVING CREW (EXCEPT DIVE SUPERVISOR) IN A SHIFT ARE PAID IN THE CLASSIFICATION WITH THE HIGHEST RATE FOR THAT SHIFT | 59.51 | 34.69 | 94.20 |
| DIVING CREW (EXCEPT DIVE SUPERVISOR) IN A SHIFT ARE PAID IN THE CLASSIFICATION WITH THE HIGHEST RATE FOR THAT SHIFT | 64.51 | 34.69 | 99.20 |
| HIGHEST RATE FOR THAT SHIFT | 103.62 | 34.69 | 138.31 |
| HIGHEST RATE FOR THAT SHIFT | 59.51 | 34.69 | 94.20 |
| HIGHEST RATE FOR THAT SHIFT | 60.51 | 34.69 | 95.20 |
| DIVING CREW (EXCEPT DIVE SUPERVISOR) IN A SHIFT ARE PAID IN THE CLASSIFICATION WITH THE HIGHEST RATE FOR THAT SHIFT | 54.10 | 34.69 | 88.79 |
| PILEDRIVER | 54.10 | 34.69 | 88.79 |
| DRYWALL STOCKER/SCRAPPER: (AREA 4) | 22.97 | 18.22 | 41.19 |
| DRYWALL STOCKER/SCRAPPER: (AREA 3) | 23.64 | 18.22 | 41.86 |
| DRYWALL STOCKER/SCRAPPER: (AREA 1) | 26.33 | 18.22 | 44.55 |
| DRYWALL INSTALLERS/LATHERS:: (AREA 4) | 45.92 | 31.26 | 77.18 |
| DRYWALL INSTALLERS/LATHERS:: (AREA 3) | 47.27 | 31.26 | 78.53 |
| DRYWALL INSTALLERS/LATHERS:: (AREA 1) | 52.65 | 31.26 | 83.91 |
| CARPENTER: MILLWRIGHT MARIN COUNTY | 52.75 | 32.41 | 85.16 |
| CARPENTER: JOURNEYMAN CARPENTER MARIN COUNTY | 52.65 | 30.82 | 83.47 |
| CARPENTER: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER MARIN COUNTY | 52.80 | 30.82 | 83.62 |
| CARPENTER: BRIDGE BUILDER/HIGHWAY CARPENTER MARIN COUNTY | 52.65 | 30.82 | 83.47 |
| MASTER INSTALLER (MODULAR FURNITURE INSTALLER) AREA 3 | 31.38 | 23.03 | 54.41 |
| MASTER INSTALLER (MODULAR FURNITURE INSTALLER) AREA 2 | 32.71 | 23.03 | 55.74 |
| MASTER INSTALLER (MODULAR FURNITURE INSTALLER) AREA 1 | 36.43 | 23.03 | 59.46 |
| LEAD INSTALLER (MODULAR FURNITURE INSTALLER) AREA 3.$ 27.96 23.03 LEAD INSTALLER (MODULAR FURNITURE INSTALLER) AREA 2.$ 29.08 23.03 LEAD INSTALLER (MODULAR FURNITURE INSTALLER) AREA 1.$ 32.21 23.03 INSTALLER (MODULAR FURNITURE INSTALLER) AREA 3 | 25.16 | 22.53 | 47.69 |
| INSTALLER (MODULAR FURNITURE INSTALLER) AREA 2 | 26.11 | 22.53 | 48.64 |
| INSTALLER (MODULAR FURNITURE INSTALLER) AREA 1 | 28.76 | 22.53 | 51.29 |
| CARPENTERS: MILLWRIGHT EL DORADO (WEST), PLACER (WEST), SACRAMENTO AND YOLO COUNTIES FOOTNOTE PLACER COUNTY (WEST) INCLUDES TERRITORY WEST OF AND INCLUDING HIGHWAY 49 AND EL DORADO COUNTY (WEST) INCLUDES TERRITORY WEST OF AND INCLUDING HIGHWAY 49 AND TERRITORY INSIDE THE CITY LIMITS OF PLACERVILLE | 57.01 | 35.11 | 92.12 |
| CARPENTERS: JOURNEYMAN CARPENTER EL DORADO (WEST), PLACER (WEST), SACRAMENTO AND YOLO COUNTIES FOOTNOTE: PLACER COUNTY (WEST) INCLUDES TERRITORY WEST OF AND INCLUDING HIGHWAY 49 AND EL DORADO COUNTY (WEST) INCLUDES TERRITORY WEST OF AND INCLUDING HIGHWAY 49 AND TERRITORY INSIDE THE CITY LIMITS OF PLACERVILLE | 54.51 | 33.52 | 88.03 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER EL DORADO (WEST), PLACER (WEST), SACRAMENTO AND YOLO COUNTIES FOOTNOTE PLACER COUNTY (WEST) INCLUDES TERRITORY WEST OF AND INCLUDING HIGHWAY 49 AND EL DORADO COUNTY (WEST) INCLUDES TERRITORY WEST OF AND INCLUDING HIGHWAY 49 AND TERRITORY INSIDE THE CITY LIMITS OF PLACERVILLE | 54.66 | 33.52 | 88.18 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER EL DORADO (WEST), PLACER (WEST), SACRAMENTO AND YOLO COUNTIES FOOTNOTE: PLACER COUNTY (WEST) INCLUDES TERRITORY WEST OF AND INCLUDING HIGHWAY 49 AND EL DORADO COUNTY (WEST) INCLUDES TERRITORY WEST OF AND INCLUDING HIGHWAY 49 AND TERRITORY INSIDE THE CITY LIMITS OF PLACERVILLE | 60.39 | 33.52 | 93.91 |
| CARPENTERS: MILLWRIGHT ALPINE, COLUSA, EL DORADO (EAST), NEVADA, PLACER (EAST), SIERRA, SUTTER AND YUBA COUNTIES | 55.66 | 35.11 | 90.77 |
| CARPENTERS: JOURNEYMAN CARPENTER ALPINE, COLUSA, EL DORADO (EAST), NEVADA, PLACER (EAST), SIERRA, SUTTER AND YUBA COUNTIES | 53.16 | 33.52 | 86.68 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER ALPINE, COLUSA, EL DORADO (EAST), NEVADA, PLACER (EAST), SIERRA, SUTTER AND YUBA COUNTIES | 53.31 | 33.52 | 86.83 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER ALPINE, COLUSA, EL DORADO (EAST), NEVADA, PLACER (EAST), SIERRA, SUTTER AND YUBA COUNTIES | 60.39 | 33.52 | 93.91 |
| CARPENTERS: MILLWRIGHT AMADOR COUNTY | 47.92 | 32.41 | 80.33 |
| CARPENTERS: JOURNEYMAN CARPENTER AMADOR COUNTY | 45.42 | 30.82 | 76.24 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER AMADOR COUNTY | 45.57 | 30.82 | 76.39 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER AMADOR COUNTY | 52.65 | 30.82 | 83.47 |
| CARPENTERS: MILLWRIGHT SOLANO COUNTY | 54.95 | 33.08 | 88.03 |
| CARPENTERS: JOURNEYMAN CARPENTER SOLANO COUNTY | 54.85 | 31.49 | 86.34 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER SOLANO COUNTY | 55.00 | 31.49 | 86.49 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER SOLANO COUNTY | 54.85 | 31.49 | 86.34 |
| CARPENTERS: MILLWRIGHT NAPA AND SONOMA COUNTIES | 54.95 | 33.08 | 88.03 |
| CARPENTERS: JOURNEYMAN CARPENTER NAPA AND SONOMA COUNTIES | 54.85 | 31.49 | 86.34 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER NAPA AND SONOMA COUNTIES | 55.00 | 31.49 | 86.49 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER NAPA AND SONOMA COUNTIES | 54.85 | 31.49 | 86.34 |
| CARPENTERS: MILLWRIGHT BUTTE, GLENN, LASSEN, MODOC, PLUMAS, SHASTA, SISKIYOU, TEHAMA AND TRINITY COUNTIES | 47.92 | 32.41 | 80.33 |
| CARPENTERS: JOURNEYMAN CARPENTER BUTTE, GLENN, LASSEN, MODOC, PLUMAS, SHASTA, SISKIYOU, TEHAMA AND TRINITY COUNTIES | 45.42 | 30.82 | 76.24 |
| CARPENTERS: HARDWOOD FLOORLAYER, SHINGLER, POWER SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING ERECTOR, SAW FILER BUTTE, GLENN, LASSEN, MODOC, PLUMAS, SHASTA, SISKIYOU, TEHAMA AND TRINITY COUNTIES | 45.57 | 30.82 | 76.39 |
| CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER BUTTE, GLENN, LASSEN, MODOC, PLUMAS, SHASTA, SISKIYOU, TEHAMA AND TRINITY COUNTIES | 52.65 | 30.82 | 83.47 |
| ELECTRICIAN NAPA AND SOLANO COUNTIES | 61.56 | 31.13 | 92.69 |
| CABLE SPLICER NAPA AND SOLANO COUNTIES | 69.26 | 31.36 | 100.62 |
| EXCLUDES ENERGY MANAGEMENT SYSTEMS | 61.04 | 31.08 | 92.12 |
| EXCLUDES ENERGY MANAGEMENT SYSTEMS | 53.08 | 30.84 | 83.92 |
| ALARM SYSTEMS WHEN INSTALLED IN RACEWAYS (INCLUDING WIRE AND CABLE PULLING) SHALL BE PERFORMED AT THE ELECTRICIAN WAGE RATE, WHEN EITHER OF THE FOLLOWING TWO (2) CONDITIONS APPLY: 1. THE PROJECT INVOLVES NEW OR MAJOR REMODEL BUILDING TRADES CONSTRUCTION. 2. THE CONDUCTORS FOR THE FIRE ALARM SYSTEM ARE INSTALLED IN CONDUIT | 46.00 | 25.68 | 71.68 |
| ALARM SYSTEMS WHEN INSTALLED IN RACEWAYS (INCLUDING WIRE AND CABLE PULLING) SHALL BE PERFORMED AT THE ELECTRICIAN WAGE RATE, WHEN EITHER OF THE FOLLOWING TWO (2) CONDITIONS APPLY: 1. THE PROJECT INVOLVES NEW OR MAJOR REMODEL BUILDING TRADES CONSTRUCTION. 2. THE CONDUCTORS FOR THE FIRE ALARM SYSTEM ARE INSTALLED IN CONDUIT | 40.00 | 25.50 | 65.50 |
| ELECTRICIAN (REMAINING AREA) ALPINE (WEST OF SIERRA MT. WATERSHED), AMADOR, BUTTE, COLUSA, EL DORADO (WEST OF SIERRA MT. WATERSHED), GLENN, LASSEN, NEVADA (WEST OF SIERRA MT. WATERSHED), PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA (WEST OF SIERRA MT. WATERSHED), SUTTER, TEHAMA, TRINITY, YOLO & YUBA COUNTIES CABLE SPLICER: RECEIVES 110% OF THE ELECTRICIAN BASIC HOURLY RATE | 52.70 | 38.68 | 91.38 |
| ELECTRICIAN MARIN AND SONOMA COUNTIES | 59.17 | 32.04 | 91.21 |
| ELECTRICIAN MODOC AND SISKIYOU COUNTIES | 47.04 | 21.84 | 68.88 |
| LINE CONSTRUCTION: (1) CABLE SPLICER DEL NORTE, MODOC & SISKIYOU COUNTIES | 67.80 | 25.20 | 93.00 |
| LINE CONSTRUCTION: (2) LINEMAN, POLE SPRAYER, HEAVY LINE EQUIPMENT MAN DEL NORTE, MODOC & SISKIYOU COUNTIES | 60.54 | 24.87 | 85.41 |
| LINE CONSTRUCTION: (3) GROUNDMAN ALL COUNTIES EXCEPT DEL NORTE, MODOC & SISKIYOU HOLIDAYS: NEW YEAR'S DAY, M.L. KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY AND DAY AFTER THANKSGIVING, CHRISTMAS DAY | 40.76 | 21.76 | 62.52 |
| LINE CONSTRUCTION: (2) EQUIPMENT SPECIALIST OPERATES CRAWLER TRACTORS, COMMERCIAL MOTOR VEHICLES, BACKHOES, TRENCHERS, CRANES (50 TONS AND BELOW), OVERHEAD & UNDERGROUND DISTRIBUTION LINE EQUIPMENT ALL COUNTIES EXCEPT DEL NORTE, MODOC & SISKIYOU HOLIDAYS: NEW YEAR'S DAY, M.L. KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY AND DAY AFTER THANKSGIVING, CHRISTMAS DAY | 53.30 | 22.26 | 75.56 |
| LINE CONSTRUCTION (1) LINEMAN; CABLE SPLICER HOLIDAYS: NEW YEAR'S DAY, M.L. KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY AND DAY AFTER THANKSGIVING, CHRISTMAS DAY ALL COUNTIES EXCEPT DEL NORTE, MODOC & SISKIYOU | 70.16 | 24.71 | 94.87 |
| ELEVATOR MECHANIC FOOTNOTE: A. PAID VACATION EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YEARS OF SERVICE, AND 6% FOR 6 MONTHS TO 5 YEARS OF SERVICE. B. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS' DAY, THANKSGIVING DAY, FRIDAY AFTER THANKSGIVING, AND CHRISTMAS DAY | 84.05 | 38.44 | 122.49 |
| EASTERN PART AREA 2: EASTERN PART MARIPOSA COUNTY AREA 1: EXCEPT EASTERN PART AREA 2 EASTERN PART MONTERREY COUNTY AREA 1: EXCEPT SOUTHWESTERN PART AREA 2: SOUTHWESTERN PART NEVADA COUNTY: AREA 1: ALL BUT THE NORTHERN PORTION ALONG THE BORDER OF SIERRA COUNTY AREA 2 REMAINDER PLACER COUNTY: AREA 1: AL BUT THE CENTRAL PORTION AREA 2: REMAINDER PLUMAS COUNTY AREA 1: WESTERN PORTION AREA 2: REMAINDER SHASTA COUNTY: AREA 1: ALL BUT THE NORTHEASTERN CORNER AREA 2: REMAINDER SIERRA COUNTY: AREA 1 WESTERN PART AREA 2: REMAINDER SISKIYOU COUNTY AREA 1: CENTRAL PART AREA 2: REMAINDER SONOMA COUNTY: AREA 1: ALL BUT THE NORTHWESTERN CORNER AREA 2: REMAINDER TEHAMA COUNTY: AREA 1: ALL BUT THE WESTERN BORDER WITH MENDOCINO & TRINITY COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2: REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2 EASTERN PART | 53.23 | 39.55 | 92.78 |
| EASTERN PART AREA 2: EASTERN PART MARIPOSA COUNTY AREA 1: EXCEPT EASTERN PART AREA 2 EASTERN PART MONTERREY COUNTY AREA 1: EXCEPT SOUTHWESTERN PART AREA 2: SOUTHWESTERN PART NEVADA COUNTY: AREA 1: ALL BUT THE NORTHERN PORTION ALONG THE BORDER OF SIERRA COUNTY AREA 2 REMAINDER PLACER COUNTY: AREA 1: AL BUT THE CENTRAL PORTION AREA 2: REMAINDER PLUMAS COUNTY AREA 1: WESTERN PORTION AREA 2: REMAINDER SHASTA COUNTY: AREA 1: ALL BUT THE NORTHEASTERN CORNER AREA 2: REMAINDER SIERRA COUNTY: AREA 1 WESTERN PART AREA 2: REMAINDER SISKIYOU COUNTY AREA 1: CENTRAL PART AREA 2: REMAINDER SONOMA COUNTY: AREA 1: ALL BUT THE NORTHWESTERN CORNER AREA 2: REMAINDER TEHAMA COUNTY: AREA 1: ALL BUT THE WESTERN BORDER WITH MENDOCINO & TRINITY COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2: REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2 EASTERN PART | 56.53 | 39.55 | 96.08 |
| MADERA COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2: EASTERN PART MARIPOSA COUNTY AREA 1: EXCEPT EASTERN PART AREA 2: EASTERN PART MONTERREY COUNTY AREA 1: EXCEPT SOUTHWESTERN PART AREA 2 SOUTHWESTERN PART NEVADA COUNTY: AREA 1: ALL BUT THE NORTHERN PORTION ALONG THE BORDER OF SIERRA COUNTY AREA 2: REMAINDER PLACER COUNTY: AREA 1 AL BUT THE CENTRAL PORTION AREA 2: REMAINDER PLUMAS COUNTY: AREA 1: WESTERN PORTION AREA 2 REMAINDER SHASTA COUNTY: AREA 1: ALL BUT THE NORTHEASTERN CORNER AREA 2: REMAINDER SIERRA COUNTY: AREA 1: WESTERN PART AREA 2: REMAINDER SISKIYOU COUNTY: AREA 1: CENTRAL PART AREA 2 REMAINDER SONOMA COUNTY: AREA 1: ALL BUT THE NORTHWESTERN CORNER AREA 2: REMAINDER TEHAMA COUNTY: AREA 1: ALL BUT THE WESTERN BORDER WITH MENDOCINO & TRINITY COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2 REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2: EASTERN PART | 57.65 | 39.55 | 97.20 |
| COUNTY: AREA 1: WESTERN PORTION AREA 2 REMAINDER SHASTA COUNTY: AREA 1: ALL BUT THE NORTHEASTERN CORNER AREA 2: REMAINDER SIERRA COUNTY: AREA 1: WESTERN PART AREA 2: REMAINDER SISKIYOU COUNTY: AREA 1: CENTRAL PART AREA 2 REMAINDER SONOMA COUNTY: AREA 1: ALL BUT THE NORTHWESTERN CORNER AREA 2: REMAINDER TEHAMA COUNTY: AREA 1: ALL BUT THE WESTERN BORDER WITH MENDOCINO & TRINITY COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2 REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2: EASTERN PART | 62.61 | 39.55 | 102.16 |
| EASTERN PART AREA 2: EASTERN PART MARIPOSA COUNTY AREA 1: EXCEPT EASTERN PART AREA 2 EASTERN PART MONTERREY COUNTY AREA 1: EXCEPT SOUTHWESTERN PART AREA 2: SOUTHWESTERN PART NEVADA COUNTY: AREA 1: ALL BUT THE NORTHERN PORTION ALONG THE BORDER OF SIERRA COUNTY AREA 2 REMAINDER PLACER COUNTY: AREA 1: AL BUT THE CENTRAL PORTION AREA 2: REMAINDER PLUMAS COUNTY AREA 1: WESTERN PORTION AREA 2: REMAINDER SHASTA COUNTY: AREA 1: ALL BUT THE NORTHEASTERN CORNER AREA 2: REMAINDER SIERRA COUNTY: AREA 1 WESTERN PART AREA 2: REMAINDER SISKIYOU COUNTY AREA 1: CENTRAL PART AREA 2: REMAINDER SONOMA COUNTY: AREA 1: ALL BUT THE NORTHWESTERN CORNER AREA 2: REMAINDER TEHAMA COUNTY: AREA 1: ALL BUT THE WESTERN BORDER WITH MENDOCINO & TRINITY COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2: REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2 EASTERN PART | 51.23 | 39.55 | 90.78 |
| EASTERN PART AREA 2: EASTERN PART MARIPOSA COUNTY AREA 1: EXCEPT EASTERN PART AREA 2 EASTERN PART MONTERREY COUNTY AREA 1: EXCEPT SOUTHWESTERN PART AREA 2: SOUTHWESTERN PART NEVADA COUNTY: AREA 1: ALL BUT THE NORTHERN PORTION ALONG THE BORDER OF SIERRA COUNTY AREA 2 REMAINDER PLACER COUNTY: AREA 1: AL BUT THE CENTRAL PORTION AREA 2: REMAINDER PLUMAS COUNTY AREA 1: WESTERN PORTION AREA 2: REMAINDER SHASTA COUNTY: AREA 1: ALL BUT THE NORTHEASTERN CORNER AREA 2: REMAINDER SIERRA COUNTY: AREA 1 WESTERN PART AREA 2: REMAINDER SISKIYOU COUNTY AREA 1: CENTRAL PART AREA 2: REMAINDER SONOMA COUNTY: AREA 1: ALL BUT THE NORTHWESTERN CORNER AREA 2: REMAINDER TEHAMA COUNTY: AREA 1: ALL BUT THE WESTERN BORDER WITH MENDOCINO & TRINITY COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2: REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2 EASTERN PART | 54.53 | 39.55 | 94.08 |
| COUNTY: AREA 1: WESTERN PORTION AREA 2 REMAINDER SHASTA COUNTY: AREA 1: ALL BUT THE NORTHEASTERN CORNER AREA 2: REMAINDER SIERRA COUNTY: AREA 1: WESTERN PART AREA 2: REMAINDER SISKIYOU COUNTY: AREA 1: CENTRAL PART AREA 2 REMAINDER SONOMA COUNTY: AREA 1: ALL BUT THE NORTHWESTERN CORNER AREA 2: REMAINDER TEHAMA COUNTY: AREA 1: ALL BUT THE WESTERN BORDER WITH MENDOCINO & TRINITY COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2 REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2: EASTERN PART | 60.61 | 39.55 | 100.16 |
| MADERA COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2: EASTERN PART MARIPOSA COUNTY AREA 1: EXCEPT EASTERN PART AREA 2: EASTERN PART MONTERREY COUNTY AREA 1: EXCEPT SOUTHWESTERN PART AREA 2 SOUTHWESTERN PART NEVADA COUNTY: AREA 1: ALL BUT THE NORTHERN PORTION ALONG THE BORDER OF SIERRA COUNTY AREA 2: REMAINDER PLACER COUNTY: AREA 1 AL BUT THE CENTRAL PORTION AREA 2: REMAINDER PLUMAS COUNTY: AREA 1: WESTERN PORTION AREA 2 REMAINDER SHASTA COUNTY: AREA 1: ALL BUT THE NORTHEASTERN CORNER AREA 2: REMAINDER SIERRA COUNTY: AREA 1: WESTERN PART AREA 2: REMAINDER SISKIYOU COUNTY: AREA 1: CENTRAL PART AREA 2 REMAINDER SONOMA COUNTY: AREA 1: ALL BUT THE NORTHWESTERN CORNER AREA 2: REMAINDER TEHAMA COUNTY: AREA 1: ALL BUT THE WESTERN BORDER WITH MENDOCINO & TRINITY COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2 REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2: EASTERN PART | 55.65 | 39.55 | 95.20 |
| OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY GROUP 3 (AREA 2) | 49.64 | 28.56 | 78.20 |
| OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY GROUP 3 (AREA 1) | 47.64 | 28.56 | 76.20 |
| OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY GROUP 2 (AREA 2) | 54.25 | 28.56 | 82.81 |
| OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY GROUP 2 (AREA 1) | 52.25 | 28.56 | 80.81 |
| OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY GROUP 1 (AREA 2) | 57.85 | 28.56 | 86.41 |
| OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY GROUP 1 (AREA 1) | 55.85 | 28.56 | 84.41 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1 GROUP 6 | 42.50 | 31.15 | 73.65 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1 GROUP 5 | 44.73 | 31.15 | 75.88 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1 GROUP 4 | 47.37 | 31.15 | 78.52 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1 GROUP 3 (Truck Crane Oiler) | 45.12 | 31.15 | 76.27 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1 GROUP 3 (Oiler) | 42.89 | 31.15 | 74.04 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1 GROUP 3 (Lifting devices) | 49.14 | 31.15 | 80.29 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1 GROUP 2 (Truck Crane Oiler) | 45.41 | 31.15 | 76.56 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1 GROUP 2 (Oiler) | 43.11 | 31.15 | 74.26 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1 GROUP 2 (Lifting devices) | 50.82 | 31.15 | 81.97 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1 GROUP 1 (Truck Crane Oiler) | 45.66 | 31.15 | 76.81 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1 GROUP 1 (Oiler) | 43.38 | 31.15 | 74.53 |
| OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1 GROUP 1 (Lifting devices) | 52.64 | 31.15 | 83.79 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 5) | 58.09 | 32.53 | 90.62 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 4) | 59.23 | 32.53 | 91.76 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 3) | 60.37 | 32.53 | 92.90 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 2) | 61.70 | 32.53 | 94.23 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 1-A) | 65.43 | 32.53 | 97.96 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 1) | 62.96 | 32.53 | 95.49 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 5) | 58.19 | 32.53 | 90.72 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 4) | 59.33 | 32.53 | 91.86 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 3) | 60.47 | 32.53 | 93.00 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 2) | 61.80 | 32.53 | 94.33 |
| OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 1-A).$ 65.53 32.53 OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 1) | 63.06 | 32.53 | 95.59 |
| OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 5 | 62.24 | 32.53 | 94.77 |
| OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 4 | 63.54 | 32.53 | 96.07 |
| OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 3 | 65.56 | 32.53 | 98.09 |
| OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 2 | 67.04 | 32.53 | 99.57 |
| OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 1 | 68.81 | 32.53 | 101.34 |
| OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 4 | 61.30 | 32.53 | 93.83 |
| OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 3 (Hydraulic) | 60.61 | 32.53 | 93.14 |
| OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 3 (Cranes) | 64.34 | 32.53 | 96.87 |
| OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 2 | 66.08 | 32.53 | 98.61 |
| OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 1 | 68.59 | 32.53 | 101.12 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 8-A | 55.49 | 32.53 | 88.02 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 8 | 57.70 | 32.53 | 90.23 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 7 | 58.84 | 32.53 | 91.37 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 6 | 59.98 | 32.53 | 92.51 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 5 | 61.30 | 32.53 | 93.83 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 4 | 62.57 | 32.53 | 95.10 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 3 | 63.95 | 32.53 | 96.48 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 2 | 65.43 | 32.53 | 97.96 |
| OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 1 | 66.96 | 32.53 | 99.49 |
| IRONWORKER ALPINE, LASSEN, MODOC, SISKIYOU AND TRINITY COUNTIES | 43.75 | 34.45 | 78.20 |
| IRONWORKER AMADOR, BUTTE, COLUSA,EL DORADO, GLENN,MARIN, NAPA, NEVADA, PLACER,PLUMAS, SACRAMENTO, SHASTA, SIERRA, SOLANO, SONOMA, SUTTER, TEHAMA, YOLO AND YUBA COUNTIES | 50.70 | 35.15 | 85.85 |
| LABORER, ASBESTOS/MOLD/LEAD LABORER: REMAINING COUNTIES | 36.75 | 29.69 | 66.44 |
| LABORER, ASBESTOS/MOLD/LEAD LABORER: MARIN AND NAPA COUNTIES | 37.75 | 29.69 | 67.44 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC CONTROL PERSON II (Area B) | 34.06 | 27.32 | 61.38 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC CONTROL PERSON II (Area A) | 35.06 | 27.32 | 62.38 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC CONTROL PERSON I (Area B) | 36.56 | 27.32 | 63.88 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC CONTROL PERSON I (Area A) | 37.56 | 27.32 | 64.88 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: ESCORT DRIVER, FLAG PERSON (Area B) | 36.26 | 27.32 | 63.58 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: ESCORT DRIVER, FLAG PERSON (Area A) | 37.26 | 27.32 | 64.58 |
| LABORER: MASON TENDER-BRICK ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO AND YUBA COUNTIES | 36.29 | 25.55 | 61.84 |
| TUNNEL AND SHAFT LABORERS: SHOTCRETE SPECIALIST ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO AND YUBA COUNTIES | 46.41 | 27.72 | 74.13 |
| TUNNEL AND SHAFT LABORERS: GROUP 5: GROUT CREW; REBOUNDMAN; SWAMPER/ BRAKEMAN (ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO AND YUBA COUNTIES) | 44.42 | 27.72 | 72.14 |
| TUNNEL AND SHAFT LABORERS: GROUP 4: VIBRATOR OPERATOR, PAVEMENT BREAKER; BULL GANG - MUCKERS, TRACKMEN; CONCRETE CREW - INCLUDES RODDING AND SPREADING, DUMPMEN (ANY METHOD) (ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO AND YUBA COUNTIES) | 44.96 | 27.72 | 72.68 |
| POTMAN; GUNITE & SHOTCRETE GUNMAN & POTMAN; HEADERMEN; HIGH PRESSURE NOZZLEMAN; MINER - TUNNEL, INCLUDING TOP AND BOTTOM MAN ON SHAFT AND RAISE WORK; NIPPER; NOZZLEMAN ON SLICK LINE; SANDBLASTER - POTMAN, ROBOTIC SHOTCRETE PLACER, SEGMENT ERECTOR, TUNNEL MUCK HAULER, STEEL FORM RAISER AND SETTER; TIMBERMAN, RETIMBERMAN (WOOD OR STEEL OR SUBSTITUTE MATERIALS THEREFORE); TUGGER (FOR TUNNEL LABORER WORK); CABLE TENDER; CHUCK TENDER; POWDERMAN - PRIMER HOUSE (ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO AND YUBA COUNTIES) | 45.41 | 27.72 | 73.13 |
| TUNNEL AND SHAFT LABORERS: GROUP 2: RODMEN; SHAFT WORK & RAISE (BELOW ACTUAL OR EXCAVATED GROUND LEVEL) (ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO AND YUBA COUNTIES) | 45.66 | 27.72 | 73.38 |
| TUNNEL AND SHAFT LABORERS: GROUP 1: DIAMOND DRILLER; GROUNDMEN; GUNITE AND SHOTCRETE NOZZLEMEN (ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO AND YUBA COUNTIES) | 45.89 | 27.72 | 73.61 |
| LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA B: (ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHIASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO, YUBA COUNTIES)- (2) Establishment Warranty Period | 28.94 | 27.30 | 56.24 |
| LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA B: (ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHIASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO, YUBA COUNTIES)- (1) New Construction | 35.25 | 27.30 | 62.55 |
| WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | 35.35 | 27.30 | 62.65 |
| COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHIASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO, YUBA COUNTIES | 35.50 | 27.30 | 62.80 |
| WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | 35.25 | 27.30 | 62.55 |
| WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | 35.37 | 27.30 | 62.67 |
| LABORER, GUNITE - AREA B: GROUP 2: NOZZLEMAN, GUNMAN, POTMAN, GROUNDMAN (ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHIASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO, YUBA COUNTIES) FOOTNOTES: LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | 35.96 | 27.30 | 63.26 |
| COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHIASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO, YUBA COUNTIES | 36.46 | 27.30 | 63.76 |
| SACRAMENTO, SHIASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO, YUBA COUNTIES) FOOTNOTES LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. Sewer cleaners shall receive $4.00 per day above Group 1 wage rates. ""Sewer cleaner"" means any worker who handles or comes in contact with raw sewage in small diameter sewers. Those who work inside recently active, large diameter sewers, and all recently active sewer manholes shal receive $5.00 per day above Group 1 wage rates Maintenance and repair track and road beds. All employees performing work covered herein shall receive $ .25 per hour above their regular rate for all work performed on underground structures not specifically covered herein. This paragraph shall not be construed to apply to work below ground level in open cut. It shall apply to cut and cover work of subway construction after the temporary cover has been placed | 28.94 | 27.30 | 56.24 |
| PLUMAS, SACRAMENTO, SHIASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO, YUBA COUNTIES) FOOTNOTES: LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. Sewer cleaners shall receive $4.00 per day above Group 1 wage rates. ""Sewer cleaner"" means any worker who handles or comes in contact with raw sewage in small diameter sewers. Those who work inside recently active, large diameter sewers, and all recently active sewer manholes shal receive $5.00 per day above Group 1 wage rates Maintenance and repair track and road beds. All employees performing work covered herein shall receive $ .25 per hour above their regular rate for all work performed on underground structures not specifically covered herein. This paragraph shall not be construed to apply to work below ground level in open cut. It shall apply to cut and cover work of subway construction after the temporary cover has been placed | 35.25 | 27.30 | 62.55 |
| SACRAMENTO, SHIASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO, YUBA COUNTIES) FOOTNOTES LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. Sewer cleaners shall receive $4.00 per day above Group 1 wage rates. ""Sewer cleaner"" means any worker who handles or comes in contact with raw sewage in small diameter sewers. Those who work inside recently active, large diameter sewers, and all recently active sewer manholes shal receive $5.00 per day above Group 1 wage rates Maintenance and repair track and road beds. All employees performing work covered herein shall receive $ .25 per hour above their regular rate for all work performed on underground structures not specifically covered herein. This paragraph shall not be construed to apply to work below ground level in open cut. It shall apply to cut and cover work of subway construction after the temporary cover has been placed | 35.35 | 27.30 | 62.65 |
| AND WORK ON AND IN DEEP FOOTINGS. (A DEEP FOOTING IS A HOLE 15 FEET OR MORE IN DEPTH.) FOOTNOTES LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. Sewer cleaners shall receive $4.00 per day above Group 1 wage rates. ""Sewer cleaner"" means any worker who handles or comes in contact with raw sewage in small diameter sewers. Those who work inside recently active, large diameter sewers, and all recently active sewer manholes shal receive $5.00 per day above Group 1 wage rates Maintenance and repair track and road beds. All employees performing work covered herein shall receive $ .25 per hour above their regular rate for all work performed on underground structures not specifically covered herein. This paragraph shall not be construed to apply to work below ground level in open cut. It shall apply to cut and cover work of subway construction after the temporary cover has been placed | 36.05 | 27.30 | 63.35 |
| SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO, YUBA COUNTIES) FOOTNOTES: LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. Sewer cleaners shall receive $4.00 per day above Group 1 wage rates ""Sewer cleaner"" means any worker who handles or comes in contact with raw sewage in small diameter sewers. Those who work inside recently active, large diameter sewers, and all recently active sewer manholes shal receive $5.00 per day above Group 1 wage rates. Maintenance and repair track and road beds. All employees performing work covered herein shall receive $ .25 per hour above their regular rate for all work performed on underground structures not specifically covered herein. This paragraph shall not be construed to apply to work below ground level in open cut. It shall apply to cut and cover work of subway construction after the temporary cover has been placed | 35.55 | 27.30 | 62.85 |
| SCALERS (INCLUDING DRILLING OF SAME); TREE TOPPER; BIT GRINDER (ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHIASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO, YUBA COUNTIES) Sewer cleaners shall receive $4.00 per day above Group 1 wage rates. ""Sewer cleaner"" means any worker who handles or comes in contact with raw sewage in small diameter sewers. Those who work inside recently active, large diameter sewers, and all recently active sewer manholes shal receive $5.00 per day above Group 1 wage rates Maintenance and repair track and road beds. All employees performing work covered herein shall receive $ .25 per hour above their regular rate for all work performed on underground structures not specifically covered herein. This paragraph shall not be construed to apply to work below ground level in open cut. It shall apply to cut and cover work of subway construction after the temporary cover has been placed | 35.72 | 27.30 | 63.02 |
| WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | 36.20 | 27.30 | 63.50 |
| PLASTERER TENDER WORK ON A SWING STAGE SCAFFOLD $1.00 PER HOUR ADDITIONAL | 39.77 | 28.54 | 68.31 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC CONTROL PERSON II INSTALLATION AND REMOVAL OF TEMPORARY/PERMANENT SIGNS, MARKERS, DELINEATORS AND CRASH CUSHIONS. MARIN COUNTY | 35.06 | 27.30 | 62.36 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC CONTROL PERSON I LAYOUT OF TRAFFIC CONTROL, CRASH CUSHIONS, CONSTRUCTION AREA AND ROADSIDE SIGNAGE MARIN COUNTY | 37.56 | 27.30 | 64.86 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: ESCORT DRIVER, FLAG PERSON (MARIN COUNTY) | 37.26 | 27.30 | 64.56 |
| TUNNEL AND SHAFT LABORERS: SHOTCRETE SPECIALIST MARIN COUNTY | 46.41 | 27.72 | 74.13 |
| TUNNEL AND SHAFT LABORERS: GROUP 5 GROUT CREW; REBOUNDMAN; SWAMPER/ BRAKEMAN (MARIN COUNTY) | 44.42 | 27.72 | 72.14 |
| TUNNEL AND SHAFT LABORERS: GROUP 4 VIBRATOR OPERATOR, PAVEMENT BREAKER; BULL GANG - MUCKERS, TRACKMEN; CONCRETE CREW - INCLUDES RODDING AND SPREADING, DUMPMEN (ANY METHOD) (MARIN COUNTY) | 44.96 | 27.72 | 72.68 |
| POTMAN; GUNITE & SHOTCRETE GUNMAN & POTMAN; HEADERMEN; HIGH PRESSURE NOZZLEMAN; MINER - TUNNEL, INCLUDING TOP AND BOTTOM MAN ON SHAFT AND RAISE WORK; NIPPER; NOZZLEMAN ON SLICK LINE; SANDBLASTER - POTMAN, ROBOTIC SHOTCRETE PLACER, SEGMENT ERECTOR, TUNNEL MUCK HAULER, STEEL FORM RAISER AND SETTER; TIMBERMAN, RETIMBERMAN (WOOD OR STEEL OR SUBSTITUTE MATERIALS THEREFORE); TUGGER (FOR TUNNEL LABORER WORK); CABLE TENDER; CHUCK TENDER; POWDERMAN - PRIMER HOUSE (MARIN COUNTY) | 45.41 | 27.72 | 73.13 |
| TUNNEL AND SHAFT LABORERS: GROUP 2 RODMEN; SHAFT WORK & RAISE (BELOW ACTUAL OR EXCAVATED GROUND LEVEL) (MARIN COUNTY) | 45.66 | 27.72 | 73.38 |
| TUNNEL AND SHAFT LABORERS: GROUP 1 DIAMOND DRILLER; GROUNDMEN; GUNITE AND SHOTCRETE NOZZLEMEN (MARIN COUNTY) | 45.89 | 27.72 | 73.61 |
| LABORER: MASON TENDER-BRICK MARIN COUNTY | 37.54 | 25.55 | 63.09 |
| LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA A: (MARIN COUNTY)- (2) Establishment Warranty Period | 29.94 | 27.30 | 57.24 |
| LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA A: (MARIN COUNTY)- (1) New Construction | 36.25 | 27.30 | 63.55 |
| LABORER, WRECKING - AREA A:: GROUP 1 (MARIN COUNTY).$ 36.50 27.30 LABORER, WRECKING - AREA A: GROUP 2 Semi-skilled wrecker (salvaging of other building materials) (MARIN COUNTY) FOOTNOTES: LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | 36.35 | 27.30 | 63.65 |
| LABORER, GUNITE - AREA A:: GROUP 1 (MARIN COUNTY) | 37.46 | 27.30 | 64.76 |
| LABORER, GUNITE - AREA A: GROUP 4 GUNITE LABORER (MARIN COUNTY) FOOTNOTES: LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | 36.25 | 27.30 | 63.55 |
| LABORER, GUNITE - AREA A: GROUP 3 REBOUNDMAN (MARIN COUNTY) FOOTNOTES: LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | 36.37 | 27.30 | 63.67 |
| LABORER, GUNITE - AREA A: GROUP 2 NOZZLEMAN, GUNMAN, POTMAN, GROUNDMAN (MARIN COUNTY) FOOTNOTES: LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | 36.96 | 27.30 | 64.26 |
| LABORER, CONSTRUCTION CRAFT LABORERS - AREA A GROUP 1 (MARIN COUNTY) | 36.50 | 27.30 | 63.80 |
| HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES. MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | 29.94 | 27.30 | 57.24 |
| HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES. MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | 36.25 | 27.30 | 63.55 |
| $4.00 PER DAY ABOVE GROUP 1 WAGE RATES. ""SEWER CLEANER"" MEANS ANY WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES. MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | 36.35 | 27.30 | 63.65 |
| FOOTNOTES: LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW SEWER CLEANERS SHALL RECEIVE $4.00 PER DAY ABOVE GROUP 1 WAGE RATES. ""SEWER CLEANER"" MEANS ANY WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | 37.05 | 27.30 | 64.35 |
| HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES. MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | 36.55 | 27.30 | 63.85 |
| HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES. MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | 36.72 | 27.30 | 64.02 |
| RECEIVE $4.00 PER DAY ABOVE GROUP 1 WAGE RATES ""SEWER CLEANER"" MEANS ANY WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES. MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | 37.20 | 27.30 | 64.50 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC CONTROL PERSON II INSTALLATION AND REMOVAL OF TEMPORARY/PERMANENT SIGNS, MARKERS, DELINEATORS AND CRASH CUSHIONS. NAPA, SOLANO, AND SONOMA, COUNTIES.$ 34.06 27.30 LABORER, TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC CONTROL PERSON I LAYOUT OF TRAFFIC CONTROL, CRASH CUSHIONS, CONSTRUCTION AREA AND ROADSIDE SIGNAGE NAPA, SOLANO, AND SONOMA, COUNTIES | 36.56 | 27.30 | 63.86 |
| LABORER, TRAFFIC CONTROL/LANE CLOSURE: ESCORT DRIVER, FLAG PERSON NAPA, SOLANO, AND SONOMA, COUNTIES | 36.26 | 27.30 | 63.56 |
| TUNNEL AND SHAFT LABORERS: SHOTCRETE SPECIALIST NAPA, SOLANO, AND SONOMA COUNTIES | 46.41 | 27.72 | 74.13 |
| TUNNEL AND SHAFT LABORERS: GROUP 5 GROUT CREW; REBOUNDMAN; SWAMPER/ BRAKEMAN (NAPA, SOLANO, AND SONOMA COUNTIES) | 44.42 | 27.72 | 72.14 |
| TUNNEL AND SHAFT LABORERS: GROUP 4 VIBRATOR OPERATOR, PAVEMENT BREAKER; BULL GANG - MUCKERS, TRACKMEN; CONCRETE CREW - INCLUDES RODDING AND SPREADING, DUMPMEN (ANY METHOD) (NAPA, SOLANO, AND SONOMA COUNTIES) | 44.96 | 27.72 | 72.68 |
| POTMAN; GUNITE & SHOTCRETE GUNMAN & POTMAN; HEADERMEN; HIGH PRESSURE NOZZLEMAN; MINER - TUNNEL, INCLUDING TOP AND BOTTOM MAN ON SHAFT AND RAISE WORK; NIPPER; NOZZLEMAN ON SLICK LINE; SANDBLASTER - POTMAN, ROBOTIC SHOTCRETE PLACER, SEGMENT ERECTOR, TUNNEL MUCK HAULER, STEEL FORM RAISER AND SETTER; TIMBERMAN, RETIMBERMAN (WOOD OR STEEL OR SUBSTITUTE MATERIALS THEREFORE); TUGGER (FOR TUNNEL LABORER WORK); CABLE TENDER; CHUCK TENDER; POWDERMAN - PRIMER HOUSE (NAPA, SOLANO, AND SONOMA COUNTIES) | 45.41 | 27.72 | 73.13 |
| TUNNEL AND SHAFT LABORERS: GROUP 2 RODMEN; SHAFT WORK & RAISE (BELOW ACTUAL OR EXCAVATED GROUND LEVEL) (NAPA, SOLANO, AND SONOMA COUNTIES) | 45.66 | 27.72 | 73.38 |
| TUNNEL AND SHAFT LABORERS: GROUP 1 DIAMOND DRILLER; GROUNDMEN; GUNITE AND SHOTCRETE NOZZLEMEN (NAPA, SOLANO, AND SONOMA COUNTIES) | 45.89 | 27.72 | 73.61 |
| LABORER: MASON TENDER-BRICK SOLANO AND SONOMA COUNTIES | 36.84 | 26.24 | 63.08 |
| LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA B: (NAPA, SOLANO, AND SONOMA COUNTIES)- (2) Establishment Warranty Period | 28.94 | 27.30 | 56.24 |
| LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA B: (NAPA, SOLANO, AND SONOMA COUNTIES)- (1) New Construction | 35.25 | 27.30 | 62.55 |
| LABORER, WRECKING - AREA B:: GROUP 1 (NAPA, SOLANO, AND SONOMA COUNTIES) | 35.50 | 27.30 | 62.80 |
| LABORER, WRECKING - AREA B: GROUP 2 Semi-skilled wrecker (salvaging of other building materials) NAPA, SOLANO, AND SONOMA COUNTIES) FOOTNOTES LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | 35.35 | 27.30 | 62.65 |
| LABORER, GUNITE - AREA B:: GROUP 1 (NAPA, SOLANO, AND SONOMA COUNTIES) | 36.46 | 27.30 | 63.76 |
| LABORER, GUNITE - AREA B: GROUP 4 GUNITE LABORER (NAPA, SOLANO, AND SONOMA COUNTIES) FOOTNOTES LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | 35.25 | 27.30 | 62.55 |
| LABORER, GUNITE - AREA B: GROUP 3 REBOUNDMAN (NAPA, SOLANO, AND SONOMA COUNTIES) FOOTNOTES LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | 35.37 | 27.30 | 62.67 |
| LABORER, GUNITE - AREA B: GROUP 2 NOZZLEMAN, GUNMAN, POTMAN, GROUNDMAN (NAPA, SOLANO, AND SONOMA COUNTIES) FOOTNOTES: LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW | 35.96 | 27.30 | 63.26 |
| FOOTNOTES: LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW SEWER CLEANERS SHALL RECEIVE $4.00 PER DAY ABOVE GROUP 1 WAGE RATES. ""SEWER CLEANER"" MEANS ANY WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | 28.94 | 27.30 | 56.24 |
| FOOTNOTES: LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW SEWER CLEANERS SHALL RECEIVE $4.00 PER DAY ABOVE GROUP 1 WAGE RATES. ""SEWER CLEANER"" MEANS ANY WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | 35.25 | 27.30 | 62.55 |
| FOOTNOTES: LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW SEWER CLEANERS SHALL RECEIVE $4.00 PER DAY ABOVE GROUP 1 WAGE RATES. ""SEWER CLEANER"" MEANS ANY WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | 35.35 | 27.30 | 62.65 |
| $4.00 PER DAY ABOVE GROUP 1 WAGE RATES. ""SEWER CLEANER"" MEANS ANY WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES. MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | 36.08 | 27.30 | 63.38 |
| $4.00 PER DAY ABOVE GROUP 1 WAGE RATES. ""SEWER CLEANER"" MEANS ANY WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES. MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | 36.05 | 27.30 | 63.35 |
| $4.00 PER DAY ABOVE GROUP 1 WAGE RATES. ""SEWER CLEANER"" MEANS ANY WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES. MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | 35.55 | 27.30 | 62.85 |
| WORK OF LOADING, PLACING AND BLASTING OF ALL POWDER AND EXPLOSIVES OF WHATEVER TYPE REGARDLESS OF METHOD USED FOR SUCH LOADING AND PLACING; HIGH SCALERS (INCLUDING DRILLING OF SAME); TREE TOPPER; BIT GRINDER (NAPA, SOLANO, AND SONOMA COUNTIES) SEWER CLEANERS SHALL RECEIVE $4.00 PER DAY ABOVE GROUP 1 WAGE RATES. ""SEWER CLEANER"" MEANS ANY WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | 35.72 | 27.30 | 63.02 |
| RECEIVE $4.00 PER DAY ABOVE GROUP 1 WAGE RATES ""SEWER CLEANER"" MEANS ANY WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES. MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | 35.50 | 27.30 | 62.80 |
| LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW SEWER CLEANERS SHALL RECEIVE $4.00 PER DAY ABOVE GROUP 1 WAGE RATES. ""SEWER CLEANER"" MEANS ANY WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED | 36.20 | 27.30 | 63.50 |
| PAINTERS MARIN, NAPA, SOLANO & SONOMA COUNTIES PREMIUMS: EXOTIC MATERIALS - $1.25 ADDITIONAL PER HOUR. SPRAY WORK: - $0.50 ADDITIONAL PER HOUR INDUSTRIAL PAINTING - $0.25 ADDITIONAL PER HOUR [WORK ON INDUSTRIAL BUILDINGS USED FOR THE MANUFACTURE AND PROCESSING OF GOODS FOR SALE OR SERVICE; STEEL CONSTRUCTION (BRIDGES), STACKS, TOWERS, TANKS, AND SIMILAR STRUCTURES] HIGH WORK OVER 50 FEET - $2.00 PER HOUR ADDITIONAL 100 TO 180 FEET - $4.00 PER HOUR ADDITIONAL OVER 180 FEET - $6.00 PER HOUIR ADDITIONAL | 53.38 | 28.04 | 81.42 |
| DRYWALL FINISHER/TAPER ALPINE, BUTTE, COLUSA, EL DORADO (WEST OF THE SIERRA NEVADA MOUNTAINS), GLENN, LASSEN (WEST OF HWY. 395, EXCLUDING HONEY LAKE); MARIN, MODOC, NAPA, NEVADA (WEST OF THE SIERRA NEVADA MOUNTAINS), PLACER (WEST OF THE SIERRA NEVADA MOUNTAINS), PLUMAS, SACRAMENTO, SHASTA, SIERRA (WEST OF THE SIERRA NEVADA MOUNTAINS), SISKIYOU, SOLANO, SONOMA, SUTTER, TEHAMA, TRINITY, YOLO AND YUBA COUNTIES | 59.63 | 31.29 | 90.92 |
| PAINTERS ALPINE, AMADOR, BUTTE, COLUSA. EL DORADO (WEST OF THE SIERRA NEVADA MOUNTAINS), GLENN, LASSEN (WEST OF HIGHWAY 395, EXCLUDING HONEY LAKE), MODOC, NEVADA (WEST OF THE SIERRA NEVADA MOUNTAINS), PLACER (WEST OF THE SIERRA NEVADA MOUNTAINS), PLUMAS, SACRAMENTO, SHASTA, SIERRA (WEST OF THE SIERRA NEVADA MOUNTAINS), SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO & YUBA COUNTIES SPRAY/SANDBLAST: $0.50 ADDITIONAL PER HOUR. EXOTIC MATERIALS: $1.25 ADDITIONAL PER HOUR. HIGH TIME OVER 50 FT ABOVE GROUND OR WATER LEVEL $2.00 ADDITIONAL PER HOUR. 100 TO 180 FT ABOVE GROUND OR WATER LEVEL $4.00 ADDITIONAL PER HOUR. OVER 180 FT ABOVE GROUND OR WATER LEVEL $6.00 ADDITIONAL PER HOUR | 43.45 | 22.80 | 66.25 |
| SOFT FLOOR LAYER MARIN, NAPA, SOLANO AND SONOMA COUNTIES | 59.00 | 33.03 | 92.03 |
| GLAZIER MARIN , NAPA & SONOMA COUNTIES; SOLANO COUNTY (WEST OF A LINE DEFINED AS FOLLOWS: HWY. 80 CORRIDOR BEGINNING AT THE CITY OF FAIRFIELD, INCLUDING TRAVIS AIR FORCE BASE AND SUISUN CITY; GOING NORTH OF MANAKAS CORNER RD., CONTINUE NORTH ON SUISUN VALLEY RD. TO THE NAPA COUNTY LINE; HWY 80 CORRIDOR SOUTH ON GRIZZLY ISLAND RD. TO THE GRIZZLY ISLAND MANAGEMENT AREA) | 56.22 | 34.00 | 90.22 |
| OF HIGHWAY 395, BEGINNING AT STACEY AND INCLUDING HONEY LAKE); NEVADA COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS); PLACER COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS); AND SIERRA COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS) PREMIUMS: SPECIAL COATINGS (BRUSH), AND SANDBLASTING = $0.50/HR SPECIAL COATINGS (SPRAY), AND STEEPLEJACK = $1.00/HR SPECIAL COATING SPRAY STEEL = $1.25/HR SWING STAGE = $2.00/HR *A SPECIAL COATING IS A COATING THAT REQUIRES THE MIXING OF 2 OR MORE PRODUCTS | 41.43 | 16.16 | 57.59 |
| OF HIGHWAY 395, BEGINNING AT STACEY AND INCLUDING HONEY LAKE); NEVADA COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS); PLACER COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS); AND SIERRA COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS) PREMIUMS: SPECIAL COATINGS (BRUSH), AND SANDBLASTING = $0.50/HR SPECIAL COATINGS (SPRAY), AND STEEPLEJACK = $1.00/HR SPECIAL COATING SPRAY STEEL = $1.25/HR SWING STAGE = $2.00/HR *A SPECIAL COATING IS A COATING THAT REQUIRES THE MIXING OF 2 OR MORE PRODUCTS | 42.19 | 16.16 | 58.35 |
| (EAST OF THE SIERRA NEVADA MOUNTAINS) PREMIUMS SPECIAL COATINGS (BRUSH), AND SANDBLASTING = $0.50/HR SPECIAL COATINGS (SPRAY), AND STEEPLEJACK = $1.00/HR SPECIAL COATING SPRAY STEEL = $1.25/HR SWING STAGE = $2.00/HR *A SPECIAL COATING IS A COATING THAT REQUIRES THE MIXING OF 2 OR MORE PRODUCTS | 39.43 | 16.16 | 55.59 |
| SOFT FLOOR LAYER EL DORADO COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS); LASSEN COUNTY (EAST OF HIGHWAY 395, BEGINNING AT STACEY AND INCLUDING HONEY LAKE); NEVADA COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS); PLACER COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS) AND SIERRA COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS)) | 34.27 | 16.47 | 50.74 |
| DRYWALL: (2) STEEPLEJACK - TAPER, OVER 40 FT WITH OPEN SPACE BELOW EL DORADO COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS); LASSEN COUNTY (EAST OF HIGHWAY 395, BEGINNING AT STACEY AND INCLUDING HONEY LAKE); NEVADA COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS); PLACER COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS); AND SIERRA COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS) | 44.29 | 16.12 | 60.41 |
| DRYWALL: (1) TAPER (EL DORADO COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS); LASSEN COUNTY (EAST OF HIGHWAY 395, BEGINNING AT STACEY AND INCLUDING HONEY LAKE); NEVADA COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS); PLACER COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS); AND SIERRA COUNTY (EAST OF THE SIERRA NEVADA MOUNTAINS) | 42.79 | 16.12 | 58.91 |
| GLAZIER ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU, SOLANO (REMAINDER), SUTTER, TEHAMA, TRINITY, YOLO, YUBA | 43.25 | 35.62 | 78.87 |
| PARKING LOT STRIPING/HIGHWAY MARKING: HIGHWAY IMPROVEMENT: GROUP 3 PROTECTIVE COATING, PAVEMENT SEALING | 35.11 | 17.62 | 52.73 |
| PARKING LOT STRIPING/HIGHWAY MARKING: HIGHWAY IMPROVEMENT: GROUP 1 STRIPER: LAYOUT AND APPLICATION OF PAINTED TRAFFIC STRIPES AND MARKING; HOT THERMO PLASTIC; TAPE, TRAFFIC STRIPES AND MARKINGS | 40.83 | 17.62 | 58.45 |
| PARKING LOT STRIPING/HIGHWAY MARKING: HIGHWAY IMPROVEMEMT: GROUP 2 GAMECOURT & PLAYGROUND INSTALLER | 34.71 | 17.62 | 52.33 |
| SOFT FLOOR LAYER ALPINE; COLUSA; EL DORADO (WEST OF THE SIERRA NEVADA MOUNTAINS); GLENN; LASSEN (WEST OF HIGHWAY 395, BEGINNING AT STACEY AND INCLUDING HONEY LAKE); MODOC; NEVADA (WEST OF THE SIERRA NEVADA MOUNTAINS); PLACER (WEST OF THE SIERRA NEVADA MOUNTAINS); PLUMAS; SACRAMENTO; SHASTA; SIERRA (WEST OF THE SIERRA NEVADA MOUNTAINS); SISKIYOU; SUTTER; TEHAMA; TRINITY; YOLO AND YUBA COUNTIES | 48.54 | 26.59 | 75.13 |
| PLASTERER AREA 355: NAPA & SONOMA COUNTIES | 32.70 | 31.68 | 64.38 |
| PLASTERER AREA 355: MARIN | 36.73 | 31.68 | 68.41 |
| PLASTERER AREA 295: ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU, SOLANO, SUTTER, TEHEMA, TRINITY, YOLO & YUBA COUNTIES | 32.70 | 31.68 | 64.38 |
| CEMENT MASON/CONCRETE FINISHER | 32.15 | 23.27 | 55.42 |
| PLUMBER, PLUMBER, STEAMFITTER, REFRIGERATION FITTER (MARIN AND SONOMA COUNTIES) | 91.00 | 49.40 | 140.40 |
| LANDSCAPE/IRRIGATION FITTER: UNDERGROUND/UTILITY FITTER MARIN & SONOMA COUNTIES | 77.35 | 36.53 | 113.88 |
| PLUMBER BUTTE, COLUSA, GLENN, LASSEN, MODOC, PLUMAS, SHASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY & YUBA COUNTIES | 52.75 | 41.39 | 94.14 |
| PLUMBER/PIPEFITTER: ALL OTHER WORK NAPA AND SOLANO COUNTIES FOOTNOTES: WHILE FITTING GALVANIZED MATERIAL: $.75 PER HOUR ADDITIONAL WORK FROM TRUSSES, TEMPORARY STAGING, UNGUARDED STRUCTURES 35' FROM THE GROUND OR WATER: $.75 PER HOUR ADDITIONAL. WORK FROM SWINGING SCAFFOLDS, BOATSWAINS CHAIRS OR SIMILAR DEVICES: $.75 PER HOUR ADDITIONAL | 71.60 | 38.38 | 109.98 |
| PLUMBER/PIPEFITTER EL DORADO COUNTY (LAKE TAHOE AREA ONLY); NEVADA COUNTY (LAKE TAHOE AREA ONLY); AND PLACER COUNTY (LAKE TAHOE AREA ONLY) | 52.14 | 18.71 | 70.85 |
| UNDERGROUND UTILITY WORKER: /LANDSCAPE FITTER ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NAPA, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU, SOLANO, SUTTER, TEHAMA, TRINITY, YOLO, AND YUBA COUNTIES | 36.01 | 18.50 | 54.51 |
| PLUMBER AMADOR (SOUTH OF SAN JOAQUIN RIVER) AND ALPINE COUNTIES | 58.45 | 38.74 | 97.19 |
| PLUMBER/PIPEFITTER: LIGHT COMMERCIAL WORK AMADOR (NORTH OF SAN JOAQUIN RIVER), EL DORADO (EXCLUDING LAKE TAHOE AREA), NEVADA (EXCLUDING LAKE TAHOE AREA); PLACER (EXCLUDING LAKE TAHOE AREA), SACRAMENTO AND YOLO COUNTIES | 55.58 | 24.02 | 79.60 |
| PLUMBER/PIPEFITTER: JOURNEYMAN AMADOR (NORTH OF SAN JOAQUIN RIVER), EL DORADO (EXCLUDING LAKE TAHOE AREA), NEVADA (EXCLUDING LAKE TAHOE AREA); PLACER (EXCLUDING LAKE TAHOE AREA), SACRAMENTO AND YOLO COUNTIES | 67.37 | 30.00 | 97.37 |
| ROOFER MARIN, NAPA, SOLANO AND SONOMA COUNTIES | 54.94 | 23.34 | 78.28 |
| ROOFER ALPINE, BUTTE, COLUSA, EL DORADO, GLENN,LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO, AND YUBA COUNTIES | 46.73 | 21.36 | 68.09 |
| SPRINKLER FITTER (FIRE SPRINKLERS) MARIN, NAPA, SOLANO AND SONOMA COUNTIES | 81.54 | 41.35 | 122.89 |
| SPRINKLER FITTER (ALPINE, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO AND YUBA COUNTIES) | 52.06 | 29.86 | 81.92 |
| SHEET METAL WORKER: MECHANICAL CONTRACTS $200,000 OR LESS MARIN, NAPA, SOLANO SONOMA & TRINITY COUNTIES | 55.92 | 45.29 | 101.21 |
| SHEET METAL WORKER: ALL OTHER WORK MARIN, NAPA, SOLANO SONOMA & TRINITY COUNTIES | 64.06 | 46.83 | 110.89 |
| SHEET METAL WORKER AMADOR, COLUSA, EL DORADO, NEVADA, PLACER, SACRAMENTO, SUTTER, YOLO AND YUBA COUNTIES | 47.85 | 41.90 | 89.75 |
| SHEET METAL WORKER ALPINE COUNTY | 43.50 | 37.42 | 80.92 |
| SHEET METAL WORKER: METAL DECKING AND SIDING ONLY BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA, YOLO AND YUBA COUNTIES | 44.45 | 35.55 | 80.00 |
| SHEET METAL WORKER: METAL DECKING AND SIDING ONLY (MARIN, NAPA, SOLANO, SONOMA AND TRINITY COUNTIES) | 44.45 | 35.55 | 80.00 |
| SHEET METAL WORKER: MECHANICAL JOBS OVER $200,000 BUTTE, GLENN, LASSEN, MODOC, PLUMAS, SHASTA, SIERRA, SISKIYOU AND TEHAMA COUNTIES | 46.60 | 40.21 | 86.81 |
| SHEET METAL WORKER: MECHANICAL JOBS $200,000 & UNDER BUTTE, GLENN, LASSEN, MODOC, PLUMAS, SHASTA, SIERRA, SISKIYOU AND TEHAMA COUNTIES | 35.16 | 35.88 | 71.04 |
| TRUCK DRIVERS: GROUP 5: DUMP TRUCKS, 65 YDS. AND OVER; HOLLAND HAULER; LOW BED HEAVY DUTY TRANSPORT OVER 7 AXLES FOOTNOTES: ARTICULATED DUMP TRUCK; BULK CEMENT SPREADER (WITH OR WITHOUT AUGER); DUMPCRETE TRUCK; SKID TRUCK (DEBRIS BOX); DRY PRE-BATCH CONCRETE MIX TRUCKS; DUMPSTER OR SIMILAR TYPE; SLURRY TRUCK: USE DUMP TRUCK YARDAGE RATE. HEATER PLANER; ASPHALT BURNER; SCARIFIER BURNER; INDUSTRIAL LIFT TRUCK (MECHANICAL TAILGATE); UTILITY AND CLEAN-UP TRUCK: USE APPROPRIATE RATE FOR THE POWER UNIT OR THE EQUIPMENT UTILIZED. TRUCK DRIVER CLASSIFICATIONS | 44.56 | 34.28 | 78.84 |
| AND UNDER 65 YDS.; WATER PULLS - DW 10'S, 20'S, 21'S AND OTHER SIMILAR EQUIPMENT WHEN PULLING AQUA/PAK OR WATER TANK TRAILERS; HELICOPTER PILOTS (WHEN TRANSPORTING MEN AND MATERIALS); LOWBEDK HEAVY DUTY TRANSPORT UP TO INCLUDING 7 AXLES; DW10'S, 20'S, 21'S AND OTHER SIMILAR CAT TYPE, TERRA COBRA, LETOURNEAU PULLS, TOURNOROCKER, EUCLID AND SIMILAR TYPE EQUIPMENT WHEN PULLING FUEL AND/OR GREASE TANK TRAILERS OR OTHER MISCELLANEOUS TRAILERS; VACUUM TRUCKS 7500 GALS AND OVER AND TRUCK REPAIRMAN FOOTNOTES: ARTICULATED DUMP TRUCK; BULK CEMENT SPREADER (WITH OR WITHOUT AUGER); DUMPCRETE TRUCK; SKID TRUCK (DEBRIS BOX); DRY PRE-BATCH CONCRETE MIX TRUCKS; DUMPSTER OR SIMILAR TYPE; SLURRY TRUCK: USE DUMP TRUCK YARDAGE RATE. HEATER PLANER; ASPHALT BURNER; SCARIFIER BURNER; INDUSTRIAL LIFT TRUCK (MECHANICAL TAILGATE); UTILITY AND CLEAN-UP TRUCK: USE APPROPRIATE RATE FOR THE POWER UNIT OR THE EQUIPMENT UTILIZED. TRUCK DRIVER CLASSIFICATIONS | 44.21 | 34.28 | 78.49 |
| DRIVER CLASSIFICATIONS | 43.86 | 34.28 | 78.14 |
| TRUCK DRIVERS: GROUP 2: DUMP TRUCKS, 6 YDS. AND UNDER 8 YDS.; TRANSIT MIXERS, THROUGH 10 YDS.; WATER TRUCKS, UNDER 7,000 GALS.; JETTING TRUCKS, UNDER 7,000 GALS.; SINGLE-UNIT FLAT RACK (3-AXLE UNIT); HIGHBED HEAVY DUTY TRANSPORT; SCISSOR TRUCK; RUBBER-TIRED MUCK CAR (NOT SELF-LOADED); RUBBER-TIRED TRUCK JUMBO; WINCH TRUCK AND ""A"" FRAME DRIVERS; COMBINATION WINCH TRUCK WITH HOIST; ROAD OIL TRUCK OR BOOTPERSON; BUGGYMOBILE; ROSS, HYSTER AND SIMILAR STRADDLE CARRIERS; SMALL RUBBER-TIRED TRACTOR FOOTNOTES: ARTICULATED DUMP TRUCK; BULK CEMENT SPREADER (WITH OR WITHOUT AUGER); DUMPCRETE TRUCK; SKID TRUCK (DEBRIS BOX); DRY PRE-BATCH CONCRETE MIX TRUCKS; DUMPSTER OR SIMILAR TYPE; SLURRY TRUCK: USE DUMP TRUCK YARDAGE RATE HEATER PLANER; ASPHALT BURNER; SCARIFIER BURNER; INDUSTRIAL LIFT TRUCK (MECHANICAL TAILGATE); UTILITY AND CLEAN-UP TRUCK: USE APPROPRIATE RATE FOR THE POWER UNIT OR THE EQUIPMENT UTILIZED TRUCK DRIVER CLASSIFICATIONS | 43.56 | 34.28 | 77.84 |
| DRIVER CLASSIFICATIONS | 43.26 | 34.28 | 77.54 |